Gantt Chart In Construction

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 8: Line 8:
  
 
== Gantt Chart Overview ==
 
== Gantt Chart Overview ==
 +
 +
The Gantt chart is a visual overview and representation of all planned tasks that are necessary for the completion of a project. These tasks are usually represented by a rectangle that indicates the expected duration of the task. When these rectangles are placed on a timeline, they can also represent the start and expected times for the tasks. As this timeline is expanded into 2 dimensions, the tasks can be subcategorised. These subcategories can be defined in various ways depending on the project at hand. Usually for construction, it will be the breakdown of larger tasks. An example being “Installation of Windows” being subdivided into “Mounting Frame”, “Mount glazing”, “Apply Caulk” etc.
 +
The 2 dimensionality of the timeline also allows for visualisation of concurrent tasks. This means that, especially for construction, it is evident which work will be ongoing during any specific day – a critical aspect in planning and allocation of the workforce.
 +
The timeline can be split into equidistant boxes. This standardisation of the timeline range gives a digestible overview of the tasks and their relative length. The time range can vary depending on the project. In cases of very complex construction projects and therefore planned to a high degree of detail, there can be Gantt charts with weekly time units and down to hourly or less.
 +
 +
==Dependencies==
 +
 +
Another information aspect that can be illustrated in Gantt charts are the dependencies across the tasks. In short, this is an illustration of which tasks need to be completed in order for others to be started or completed. These, as with most projects, typically occur in construction as many phases are completely contingent on other earlier ones. Understanding these dependencies allows for more effective planning of construction projects. This is especially true when setbacks do occur, as they allow for an overview of where accelerations can be made, and perhaps more pertinent, where they cannot. There are 4 types of dependencies.<ref name="Gantt Chart Dependencies: Understanding Task Dependency Types"> https://www.projectmanager.com/blog/gantt-chart-dependencies, Retrieved February 11, 2022</ref>)
 +
 +
===Finish-to-Start Task Dependency===
 +
 +
The finish to start dependency is likely the most common. As suggested by the name it refers to a a dependency in which one task needs to be completed for another to start. This type of dependency means that a delay in task A will postpone task B and therefore delay the schedule. This can cause a domino effect in which a delay of one task can propagate through successive tasks and delay these.
 +
 +
===Start-to-Start Task Dependency===
 +
 +
Start to start is the second type of dependency. Once again, the dependency is aptly named, as it refers to a task relationship in which one needs to start in order for another to start. It is important to understand that these tasks do not necessarily have to begin at the same time (and in most cases do not). These types of dependencies usually pose a lesser threat of compounding delays as they can, in theory, run concurrently.
 +
 +
===Finish-to-Finish Task Dependency===
 +
The third type of dependency is the Finish-to-Finish category. These dependencies occur when one task needs to be completed in order for another to be completed. As with the aforementioned start-to-start, finish-to-finish tasks can run concurrently. The two tasks are only contingent in regard to their completion (though this does not have to be at the same time).
 +
 +
===Start-to-Finish Task Dependency===
 +
Start-to-finish task dependencies are perharps the rarest form. This dependency is the inverse form of the first category. Here task A cannot be completed until task B has been started.
 +
  
 
== Applications in Construction Projects ==
 
== Applications in Construction Projects ==
 +
 +
Gantt charts are frequently used for construction projects. This spans the spectrum of construction project scopes from the largest infrastructure projects to the smallest renovations. This is due to a myriad of reasons. Construction projects fall under most of the general theories of projects, but they do exhibit a few traits that make applications of certain techniques more effective. A few of these differences are:
 +
#The usually fixed location of construction. This adds certain logistical complexities. This can take the form of procuring building materials which have to be transported to the site. This may also include traffic management, security and various other extraneous factors.
 +
#Construction projects are more prone to be affect by the uncertainty of weather and thus need to be more flexible in this regard. Extreme weather can have a negative impact on timelines and feasibility of certain work
 +
#The high level of focus on the green transition within construction has added several layers of risk and complexity to what used to be regarded as simpler projects
 +
#The time scope of construction projects tends to be measured more in years than days. This means that finer details or points may not be in place before construction commences.
 +
 +
  
 
== Advantages and limitations ==
 
== Advantages and limitations ==

Revision as of 00:41, 21 February 2022

Created by Peter Birkholm, February 2022

The Gantt chart is a type of work scheduling tool in which processes are visualised[1][2]. It is based on the Harmonygraph, which was developed by Karol Adamiecki at the end of the 19th century. The American engineer Henry Gantt was the one who successfully introduced the method to a wider audience and thus became the namesake for the method[2]. The Gantt chart has been used in many well-known construction projects after its conception, for example, Hoover Dam and the Interstate Highway System.

Gantt charts are frequently used for construction projects to illustrate tasks along a timeline. They are effective for several reasons, though primarily due to their capability in showing a wide array of relevant project data in a simple fashion. At its core, the Gantt chart is built around illustration of tasks that are to be completed along a timeline. Each task is represented by a bar, with the location and length indicating start dates and durations. Furthermore, these tasks can have their dependencies illustrated through connecting lines. Being able to illustrate each type of dependency associated with a task (Finish to start, Start to Start etc.[3]) means that the tool can also be used to assess feasibility of, as well as attempt to optimise, workflows before the start of a project. After the construction project is underway, the Gantt chart can be used to track milestones and assess whether timelines are being followed.

There are a myriad of advantages and disadvantages to utilising Gantt charts for construction projects. A key benefit is the visualising of dependencies – as construction tends to be ordinal in nature. One disadvantage that is commonly seen is the Gantt chart becoming less usable as the size and scope of the construction project increases[4].

Contents

Gantt Chart Overview

The Gantt chart is a visual overview and representation of all planned tasks that are necessary for the completion of a project. These tasks are usually represented by a rectangle that indicates the expected duration of the task. When these rectangles are placed on a timeline, they can also represent the start and expected times for the tasks. As this timeline is expanded into 2 dimensions, the tasks can be subcategorised. These subcategories can be defined in various ways depending on the project at hand. Usually for construction, it will be the breakdown of larger tasks. An example being “Installation of Windows” being subdivided into “Mounting Frame”, “Mount glazing”, “Apply Caulk” etc. The 2 dimensionality of the timeline also allows for visualisation of concurrent tasks. This means that, especially for construction, it is evident which work will be ongoing during any specific day – a critical aspect in planning and allocation of the workforce. The timeline can be split into equidistant boxes. This standardisation of the timeline range gives a digestible overview of the tasks and their relative length. The time range can vary depending on the project. In cases of very complex construction projects and therefore planned to a high degree of detail, there can be Gantt charts with weekly time units and down to hourly or less.

Dependencies

Another information aspect that can be illustrated in Gantt charts are the dependencies across the tasks. In short, this is an illustration of which tasks need to be completed in order for others to be started or completed. These, as with most projects, typically occur in construction as many phases are completely contingent on other earlier ones. Understanding these dependencies allows for more effective planning of construction projects. This is especially true when setbacks do occur, as they allow for an overview of where accelerations can be made, and perhaps more pertinent, where they cannot. There are 4 types of dependencies.[3])

Finish-to-Start Task Dependency

The finish to start dependency is likely the most common. As suggested by the name it refers to a a dependency in which one task needs to be completed for another to start. This type of dependency means that a delay in task A will postpone task B and therefore delay the schedule. This can cause a domino effect in which a delay of one task can propagate through successive tasks and delay these.

Start-to-Start Task Dependency

Start to start is the second type of dependency. Once again, the dependency is aptly named, as it refers to a task relationship in which one needs to start in order for another to start. It is important to understand that these tasks do not necessarily have to begin at the same time (and in most cases do not). These types of dependencies usually pose a lesser threat of compounding delays as they can, in theory, run concurrently.

Finish-to-Finish Task Dependency

The third type of dependency is the Finish-to-Finish category. These dependencies occur when one task needs to be completed in order for another to be completed. As with the aforementioned start-to-start, finish-to-finish tasks can run concurrently. The two tasks are only contingent in regard to their completion (though this does not have to be at the same time).

Start-to-Finish Task Dependency

Start-to-finish task dependencies are perharps the rarest form. This dependency is the inverse form of the first category. Here task A cannot be completed until task B has been started.


Applications in Construction Projects

Gantt charts are frequently used for construction projects. This spans the spectrum of construction project scopes from the largest infrastructure projects to the smallest renovations. This is due to a myriad of reasons. Construction projects fall under most of the general theories of projects, but they do exhibit a few traits that make applications of certain techniques more effective. A few of these differences are:

  1. The usually fixed location of construction. This adds certain logistical complexities. This can take the form of procuring building materials which have to be transported to the site. This may also include traffic management, security and various other extraneous factors.
  2. Construction projects are more prone to be affect by the uncertainty of weather and thus need to be more flexible in this regard. Extreme weather can have a negative impact on timelines and feasibility of certain work
  3. The high level of focus on the green transition within construction has added several layers of risk and complexity to what used to be regarded as simpler projects
  4. The time scope of construction projects tends to be measured more in years than days. This means that finer details or points may not be in place before construction commences.


Advantages and limitations

Advantages

Limitations

Further Perspectives

Bibliography

References

  1. https://archive.org/details/cu31924004570853/page/n19/mode/2up, Retrieved February 11, 2022
  2. 2.0 2.1 https://www.gantt.com/, Retrieved February 11, 2022
  3. 3.0 3.1 https://www.projectmanager.com/blog/gantt-chart-dependencies, Retrieved February 11, 2022
  4. https://analysistabs.com/gantt-chart/advantages-disadvantages/, Retrieved February 11, 2022