Risk Management and Response Planning for Successful Project Execution

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 24: Line 24:
 
7. Result documentation<br />
 
7. Result documentation<br />
  
With the help of the FMEA, the identified risks can be evaluated and assessed. For the evaluation, the severity(s), occurrence(o) and detection(d) of the failures are considered. Based on the risk assessment, the risk priority number (RPN) can be formed as a measure for analyzing the risk. The RPN is calculated by multiplying the three categories s, o and d and is between 1 and 1000. This means that the higher the RPN, the more necessary it is from a risk management point of view to consider a measure to improve the number. The RPN alone, however, is not a sufficient technique to draw conclusions for evaluating the risks due to the equal weighting of the categories. For the following reason, the FMEA Handbook of the Automotive Industry Action Group (AIAG) and the German Association of the Automotive Industry (VDA) has additionally introduced the action priority (AP). This method was created to assign different weights to the categories. In this case severity is given the highest priority, followed by occurrence and finally discovery. Based on this change, the involved participants can make better decisions to prevent future problems.  FMEA Handbook. The following article will mainly focus on steps 4,5 and 6 of the FMEA taking into account the cost-benefit analysis.
+
With the help of the FMEA, the identified risks can be evaluated and assessed. For the evaluation, the severity(s), occurrence(o) and detection(d) of the failures are considered. Based on the risk assessment, the risk priority number (RPN) can be formed as a measure for analyzing the risk. The RPN is calculated by multiplying the three categories s, o and d and is between 1 and 1000. This means that the higher the RPN, the more necessary it is from a risk management point of view to consider a measure to improve the number. The RPN alone, however, is not a sufficient technique to draw conclusions for evaluating the risks due to the equal weighting of the categories. For the following reason, the FMEA Handbook of the Automotive Industry Action Group (AIAG) and the German Association of the Automotive Industry (VDA) has additionally introduced the action priority (AP). This method was created to assign different weights to the categories. In this case severity is given the highest priority, followed by occurrence and finally discovery. Based on this change, the involved participants can make better decisions to prevent future problems.  FMEA Handbook. The following article will mainly focus on steps 4, 5 and 6 of the FMEA taking into account the cost-benefit analysis.<ref name="risk19"/>
 
+
  
 
===Cost-benefit analysis===
 
===Cost-benefit analysis===
 +
 +
A cost-benefit analysis is a method of data-driven decision-making and serves as a tool to weigh the expected costs and benefits of a project decision to assess whether it is reasonable from an economic point of view. Therefore it is a method that is mainly used in the business environment, by both large companies and start-ups. The fundamental principles and structure can be utilized in nearly any decision-making process, regardless of its commercial or non-commercial orientation.
 +
If the analysis shows that the expected benefits exceed the projected costs, it can be argued that the decision has a positive impact. However, if the costs surpass the benefits, a company may want to reconsider the decision or the overall project.
 +
There can be potential promising benefits from an economic perspective to performing such analysis before relevant organizational decisions are made. Conducting analysis can highlight important information, such as the organization's value chain, the ROI of a project, or the transparency of decisions.
 +
The cost-benefit analysis consists of the following four steps:
 +
 +
* Step 1: Definition of the framework: Determination of the aims and objectives that the analysis tries to achieve.
 +
* Step 2: Identification of cost and benefit:
 +
* Step 3: Estimate values for costs and benefits:
 +
* Step 4: Comparing values and determining conclusions:
 +
  
 
===Relation to project management===
 
===Relation to project management===

Revision as of 19:21, 11 February 2023

Developed by David Rühmkorf

In a time of growing global competition, the outcome of projects is crucial to an organization's business result. Despite this, many projects still suffer from postponements, scope changes, failures, and cancellations. These issues can stem from inadequate risk management practices in projects such as risk identification and decision-making.[1] The objective of project risk management is to enhance the likelihood of favorable outcomes and reduce the probability of potential risks to rise the chances of project success. The PMBOK® Guide describes that unhandled risk can result in deviations from the project strategy and hinder the accomplishment of the project goals. As a result, the outcome of a project is closely linked to the effectiveness of project risk management.[2]

One method that served already as an adequate tool in various areas for identifying risks is the FMEA (Failure Modes and Effects Analysis). By applying an FMEA the project team is able to detect potential risks before they occur, assess their impact on the project outcome and implement appropriate measures to reduce or prevent them.[3] For an enhancing evaluation and assessment of the measures, a cost-benefit analysis can be carried out anlong with the FMEA. By conducting this additional method it can be checked to what extent the execution of the measure makes sense from an economic point of view with regard to the respective project.[4] Overall, it can be crucial for organizations to integrate these methods into their project risk management processes to ensure the achievement of project goals and business results.


Contents

Method description

FMEA

FMEA is a systematic, qualitative method from risk management that is suitable for the identification, analysis and evaluation of risks. The aim of its application is to detect and prevent defects at an early stage in order to optimize product and process risks. Depending on the area of application, a number of different methods can be used in practice. The different types include design, system and process FMEA. A total of seven steps are considered for performing an FMEA. Each steps helps to further develop and to understand the risk profile of a product or a process.

1. Planning and Preparation
2. Structure analysis
3. Function analysis
4. Failure analysis
5. Risk analysis
6. Optimization
7. Result documentation

With the help of the FMEA, the identified risks can be evaluated and assessed. For the evaluation, the severity(s), occurrence(o) and detection(d) of the failures are considered. Based on the risk assessment, the risk priority number (RPN) can be formed as a measure for analyzing the risk. The RPN is calculated by multiplying the three categories s, o and d and is between 1 and 1000. This means that the higher the RPN, the more necessary it is from a risk management point of view to consider a measure to improve the number. The RPN alone, however, is not a sufficient technique to draw conclusions for evaluating the risks due to the equal weighting of the categories. For the following reason, the FMEA Handbook of the Automotive Industry Action Group (AIAG) and the German Association of the Automotive Industry (VDA) has additionally introduced the action priority (AP). This method was created to assign different weights to the categories. In this case severity is given the highest priority, followed by occurrence and finally discovery. Based on this change, the involved participants can make better decisions to prevent future problems. FMEA Handbook. The following article will mainly focus on steps 4, 5 and 6 of the FMEA taking into account the cost-benefit analysis.[2]

Cost-benefit analysis

A cost-benefit analysis is a method of data-driven decision-making and serves as a tool to weigh the expected costs and benefits of a project decision to assess whether it is reasonable from an economic point of view. Therefore it is a method that is mainly used in the business environment, by both large companies and start-ups. The fundamental principles and structure can be utilized in nearly any decision-making process, regardless of its commercial or non-commercial orientation. If the analysis shows that the expected benefits exceed the projected costs, it can be argued that the decision has a positive impact. However, if the costs surpass the benefits, a company may want to reconsider the decision or the overall project. There can be potential promising benefits from an economic perspective to performing such analysis before relevant organizational decisions are made. Conducting analysis can highlight important information, such as the organization's value chain, the ROI of a project, or the transparency of decisions. The cost-benefit analysis consists of the following four steps:

  • Step 1: Definition of the framework: Determination of the aims and objectives that the analysis tries to achieve.
  • Step 2: Identification of cost and benefit:
  • Step 3: Estimate values for costs and benefits:
  • Step 4: Comparing values and determining conclusions:


Relation to project management

Aplication of the tools

Benefits of application

Limitations

Annotated bibliography

References

  1. Bahrami, Mahdi et al. (2012). Innovation and Improvements In Project Implementation and Management; Using FMEA Technique. Elsevier Ltd.
  2. 2.0 2.1 Project Management Institute (2019). Standard for Risk Management in Portfolios, Programs, and Projects.
  3. AIAG & VDA (2019). FMEA Handbook.
  4. Tim Stobierski (2019). How to Do a Cost-Benefit Analysis & Why It’s Important. Harvard Business School Online. https://online.hbs.edu/blog/post/cost-benefit-analysis.