Managing threats and opportunities in risk treatment

From apppm
(Difference between revisions)
Jump to: navigation, search
(Risk Treatment)
(Limitations)
 
(158 intermediate revisions by one user not shown)
Line 1: Line 1:
 
''Developed by Theis Rosenkvist Sørensen''
 
''Developed by Theis Rosenkvist Sørensen''
  
Risk management is the final stage in the risk management process. It is used to control and monitor the uncertainties during the project. When managing a project, uncertainties are one of the most important factors to control in order to achieve a successful project. Uncertainties occur when certain events in a project are unpredictable and it will only be possible to guess about a future event. Risk management is used to identify risks in the project that help maintain stability and used to prevent unforeseen events that can be cost, resource or time consuming. By using risk management, it is possible to ensure that the project team achieves the goals they are solving by not encountering many unpredictable obstacles during the project.
+
Risk treatment is the final stage in the risk management process. It is used to control and monitor the uncertainties during the project. When managing a project, uncertainties are one of the most important factors to control in order to achieve a successful project. Uncertainties occur when certain events in a project are unpredictable and it will only be possible to guess about a future event. Risk management is used to identify risks in the project that help maintain stability and used to prevent unforeseen events that can be cost, resource or time consuming. By using risk management, it is possible to ensure that the project team achieves the goals they are solving by not encountering many unpredictable obstacles during the project.
  
The risk management process is a five-step monitoring process that ''Establish Context/Scope, Identify, Analyze, Evaluate and Treat potential risks'' over the life of a project <ref name=ISO31000_2018/>. By managing the project using responses to threats and opportunities, it becomes possible to minimize the impact of the risk. If this can be done in a successful way, better risk management is achieved and it will thus be possible to reduce the impact of the uncertainties in the project. By using Rumsfeld's (un)known-unknowns, it becomes possible to reduce the risk by establishing precautions that can prevent or reduce the uncertainties from arising.
+
The risk management process is a seven-step iterative process: ''Communication & Consultation, Establish Context/Scope/Criteria, Identify Risks, Analyze Risks, Evaluate Risk, Risk treatment and Monitoring & Review'' <ref name=ISO31000_2018/>. This is done throughout the projects lifetime. By managing the project using responses to threats and opportunities, it becomes possible to minimize the impact of the risk. If it can be done in a successful way, better risk management is achieved and it will thus be possible to reduce the impact of the uncertainties in the project. By using Rumsfeld matrix, it becomes possible to reduce the risk by establishing precautions that can prevent or reduce the uncertainties from arising.
  
 
When working with risk treatment, there are some limitations. One of the crucial limitations is the lack of knowledge sharing. The lack of knowledge sharing leads to a greater amount of uncertainties that could have been prevented. However, not all uncertainties can be prevented and even perfectly planned projects have their limitations. By having a greater amount of expertise, a higher level of risk treatment can be performed and will minimize the risk by identifying crucial uncertainties in the project.  
 
When working with risk treatment, there are some limitations. One of the crucial limitations is the lack of knowledge sharing. The lack of knowledge sharing leads to a greater amount of uncertainties that could have been prevented. However, not all uncertainties can be prevented and even perfectly planned projects have their limitations. By having a greater amount of expertise, a higher level of risk treatment can be performed and will minimize the risk by identifying crucial uncertainties in the project.  
 +
 +
This paper aims to highlight the '''importance of the risk management process''' and more specifically '''delve into risk treatment process'''.
  
 
== Introduction ==
 
== Introduction ==
  
 
=== The Risk Management Process ===
 
=== The Risk Management Process ===
[[File:The_risk_management_process_v2.png|right|thumb|200px|Figure 1: The Risk Management Process <ref name=ISO31000_2018> Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines, Retrieved from https://sd.ds.dk/Viewer/Standard?ProjectNr=M296412&Status=60.60&VariantID=41&Page=0 </ref>]]
+
[[File:The_risk_management_process_v2.png|right|thumb|250px|Figure 1: The Risk Management Process <ref name=ISO31000_2018> Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines, Retrieved from https://sd.ds.dk/Viewer/Standard?ProjectNr=M296412&Status=60.60&VariantID=41&Page=0 </ref>]]
  
 
Risk management is a process that works to manage risks to ensure that it cause the least impact in the project. Risk management is based on assumptions and experience from previous projects. However, many assumptions are uncertain which can have an effect on the project's original scope. The Project Management Institute (PMI), describes risks as ''"An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives"'' <ref name=PMI> Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/pdf/id:kt012LZJB1/guide-project-management/opportunities </ref>. By successfully navigating the uncertainty, risk can be managed in a way that is most beneficial to the project scope.
 
Risk management is a process that works to manage risks to ensure that it cause the least impact in the project. Risk management is based on assumptions and experience from previous projects. However, many assumptions are uncertain which can have an effect on the project's original scope. The Project Management Institute (PMI), describes risks as ''"An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives"'' <ref name=PMI> Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/pdf/id:kt012LZJB1/guide-project-management/opportunities </ref>. By successfully navigating the uncertainty, risk can be managed in a way that is most beneficial to the project scope.
Line 16: Line 18:
 
The process involves a ''"systematic application of policies, procedures and practices to the activities of communicating and consulting, establishing the context and assessing, treating, monitoring, reviewing, recording and reporting risk"'' <ref name=ISO31000_2018/>. It should be noted that there can be many different applications of the risk management process, as it can be adapted to a particular project to achieve specific goals within the organization.  
 
The process involves a ''"systematic application of policies, procedures and practices to the activities of communicating and consulting, establishing the context and assessing, treating, monitoring, reviewing, recording and reporting risk"'' <ref name=ISO31000_2018/>. It should be noted that there can be many different applications of the risk management process, as it can be adapted to a particular project to achieve specific goals within the organization.  
  
When operating the risk management process, take into account that the process is an iterative approach and it is important to go back and assess whether there have been changes in the previous stages that could create new potential risks that the project manager needs to adapt in their risk assessment. The stages are illustrated in Figure 1 <ref name=ISO31000_2018/>.  
+
When operating the risk management process, take into account that the process is an iterative approach and it is important to go back and assess whether there have been changes in the previous stages that could create new potential risks that the project manager needs to adapt in their risk assessment. The stages are illustrated in Figure 1 <ref name=ISO31000_2018/>.
  
(NOTE: Should I elaborate on the five stages as this is an introduction?)
+
=== Knowledge and awareness ===
 +
[[File:Knowledge_and_Awareness.png|right|thumb|250px|Figure 2: Knowledge and Awareness <ref name=Hillson/>]]
  
 +
David Hillson describes the difference between risk and uncertainties. He states that "risk" has a set of possible outcomes that are known, but that the precise outcome is not known in advance. In contrast, uncertainties relates to a lack of knowledge about the possible outcomes and are thus an unknown event from an unknown number of possible outcomes <ref name=Hillson> Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management".'' Marcel Dekker Inc. </ref>.
  
 +
Based on these descriptions, the relationship between risk and uncertainty can be described as:
  
 +
''"Risk is measurable uncertainty";''
 +
''"Uncertainty is unmeasurable risk" <ref name=Hillson/>.''
  
WILL BE DELETED:
+
Another way to distinguish the relationship between risk and uncertainty is by looking at the relationship between knowledge and awareness. Figure 2 illustrates four quadrants where knowledge and awareness are either present or absent. The figure is a similar concept to the Johari Window, which describes self-awareness and perception by others <ref name=Hillson/>. The top right corner of the quadrant '''certainty''' is illustrated, where both awareness and knowledge are present. An example could be a known number of square meters on which a building must be built or the appearance of the building so that it fits a certain cityscape. The top left corner illustrate '''caution''', which describe the things that are uncertain. This could be, for example, the weather conditions next week. Under certainty we have '''amnesia''' which describes the lack of awareness or a blind spot regarding the knowledge we have. An example of this could be, bad planning, poor communication or acting on intuition and biases. The project manager can practice self-awareness to identify them. The last quadrant is '''Ignorance''', where ''"we don't know what we don't know"''. An example of this could be the beginning of a war or an unpredictable natural disaster.
  
ref iso 31000_2018:
+
=== Donald Rumfeld's Unknown-unknowns ===
<ref name=ISO31000_2018/>
+
[[File:The_Connection_Between_Hillson's_Knowledge_and_Awareness_figure_&_Rumsfeld_Matrix.png|right|thumb|250px|Figure 3: The Connection Between Hillson's ''Knowledge and Awareness'' figure<ref name=Hillson/> & ''Rumsfeld Matrix''<ref name=Krogerus/> ]]
  
<ref name=ISO31000_2018> Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines, Retrieved from https://sd.ds.dk/Viewer/Standard?ProjectNr=M296412&Status=60.60&VariantID=41&Page=0 </ref>
+
The knowledge and awareness figure created by Hillson and the Johari Window is a comparison to the known description used by the former U.S. Secretary of Defense Donald Rumsfeld at a press conference in 2002. He described the types of uncertainties as:
  
 +
''"Reports that say that something hasn't happened are always interesting to me, because as we know, there are known knowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But there are also unknown unknowns – the ones we don't know we don't know"'' <ref name=Rumsfeld> Rumsfeld, Donald. ''"Defense.gov News Transcript: DoD News Briefing - Secretary Rumsfeld and Gen. Myers, United States Department of Defense (defense.gov)"''. February 12, 2002. Retrieved from https://archive.ph/20180320091111/http://archive.defense.gov/Transcripts/Transcript.aspx?TranscriptID=2636#selection-1053.10-1053.342 </ref>.
  
 +
This statement became known as Rumsfeld matrix when the author Mikael Krogerus refers to it in his book ''"The decision book : fifty models for strategic thinking"'' <ref name=unknown> ''There are unknown unknowns.'' Retrieved February 10, 2023. Retrieved from https://en.wikipedia.org/wiki/There_are_unknown_unknowns </ref>. Figure 3 illustrates the connection between Hillson's ''Knowledge and Awareness'' figure & ''Rumsfeld Matrix''<ref name=Krogerus> Krogerus, Mikael. ''"The decision book: fifty models for strategic thinking"'', 2012. </ref>.
  
ref PMI:
+
== Overview of The Risk Management Process ==
<ref name=PMI> Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/pdf/id:kt012LZJB1/guide-project-management/opportunities </ref>
+
  
 +
The risk management process is a seven-step iterative process, which can be seen in figure 1. The process is described below in proper order. This section describes an overview of the risk management process. It will not be in-depth, but can be used to create an understanding of the entire process. For a more detailed review of the seven steps, an elaboration can be found in ''"DS/ISO 31000:2018, Risk management - Guidelines"'' <ref name=ISO31000_2018/>.
  
Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). Retrieved from
+
# '''Communication & Consultation''' <br
https://app.knovel.com/hotlink/pdf/id:kt012LZJB1/guide-project-management/opportunities
+
/> The purpose of communication and consultation is to share relevant information with identified and relevant stakeholders. There must be close coordination between the stakeholders to ensure a shared understanding of the project's scope and criteria. The purpose of this phase is to bring stakeholders together with different expertise and ensure that there is enough information to facilitate sufficient risk overview and decision-making. However, it is also important to ensure that the different points of view are appropriately considered when defining risk criteria and when evaluating risks <ref name=ISO31000_2018/>. Communication and consultation will result in a focus on the project's scope, context and criteria.  <br
 +
/> <br
 +
/>
 +
# '''Scope, Context and Criteria''' <br
 +
/> In this step, the goal is to establish the objects, scope, context and criteria. The scope is used by the organization to define its risk management activities. The process is applied at several levels such as strategic, operational, programme, project and other activities. This implies considerations about appropriate risk assessment tools and techniques, objectives and decitions need to be made, expected outcomes from the steps taken in the process, resources, etc <ref name=ISO31000_2018/>. An elaboration can be found in ''"DS/ISO 31000:2018, Risk management - Guidelines"'' <ref name=ISO31000_2018/>. The context is used to describe the environment for the project both externally and internally. The organization will seek to define and achieve its objectives. The criteria define the type of risk that affects the objects. The risks must be evaluated in relation to their significance and support the decision-making process. <br
 +
/> <br
 +
/>
 +
# '''Risk identification''' <br
 +
/> The purpose of the risk identification process is to identify, describe and recognize risks that can have a positive or negative impact on the organization in achieving its objectives. Risk identification is an iterative process which is connected to the risk analysis and the risk evaluation. These three steps combined are named ''"risk assessment"'' and is illustrated in figure 1. <br
 +
/> <br
 +
/>
 +
# '''Risk Analysis''' <br
 +
/> Risk analysis is used to understand the risk and its characteristics. A risk analysis involves considerations about scenarios, uncertainties, consequences, risk sources, complexity, probability, control and its effectiveness <ref name=ISO31000_2018/>. The risk analysis is used to determine its level of risk and can vary according to the purpose of the analysis. Tools for determining a risk analysis could be, for example, a SWOT Analysis, Root Cause Analysis, Risk Register or a Probability Impact Matrix, which is described in this article (see figure 5). By making a risk analysis, a better understanding of which risk treatment is required is created. <br
 +
/> <br
 +
/>
 +
# '''Risk Evaluation''' <br
 +
/> The purpose of risk evaluation is to support decisions taken in the project. The evaluation involves a comparison of results obtained in the risk analysis with the established risk criteria to assess where additional action is required <ref name=ISO31000_2018/>. The risk evaluation can lead to consideration of treatment options, further analysis or reconsideration of objectives. <br
 +
/> <br
 +
/>
 +
# '''Risk Treatment''' <br
 +
/> The importance of risk treatment can determine whether a project will be a success or not. The purpose of risk treatment is to implement options that address the risks. ''"DS/ISO 31000:2018, Risk management - Guidelines"'' describes risk treatment as a process of <ref name=ISO31000_2018/>: <br
 +
/> - ''formulating and selecting risk treatment options;'' <br
 +
/> - ''planning and implementing risk treatment;'' <br
 +
/> - ''assessing the effectiveness of risk treatment;'' <br
 +
/> - ''deciding whether the remaining risk is acceptable;'' <br
 +
/> - ''if not acceptable, taking further treatment.'' <br
 +
/> Further elaboration of risk treatment will be described in the following section. <br
 +
/> <br
 +
/>
 +
# '''Monitoring & Review''' <br
 +
/> The purpose of monitoring and review is to consider the previous steps and assess the quality and effectiveness of the process design, implementation and outcomes. By doing this, an iterative process of the entire risk management process has been created and it is possible as a project manager to assess errors and shortcomings that will strengthen future similar projects. This is done by recording and reporting during the process and creating additional treatment plans (analysis) for new identified risks to improve risk management activities. Furthermore, it is important to communicate risk management activities and results across the organization, as well as having good interaction with stakeholders, including those responsible for some of the risk management activities <ref name=ISO31000_2018/>. <br
 +
/> <br
 +
/>
  
=== Donald Rumfeld's Matrix ===
+
== Risk Treatment ==
  
abc
+
The importance of risk treatment lies in the fact that risks are decisive for whether a project will be a success or not. By not managing the risks, the consequence can be fatal. Barry Boehm states the consequence as ''"If you don’t actively attack the risks, they will actively attack you"'' <ref name=ROM> Forsberg, K., & Mooz, H. RISK AND OPPORTUNITY MANAGEMENT. (1996). INCOSE International Symposium, pp. 586–598. Retrieved from https://doi.org/10.1002/j.2334-5837.1996.tb02057.x </ref>. Risks can be both threats and opportunities as they can have either a positive or negative impact on the project. This section will describe the response strategies to threats and opportunities.
  
<ref name=Hillson> Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management".'' Marcel Dekker Inc. </ref>
+
=== Threats ===
 +
Threats are uncertainties and unexpected events that can effect the project negative and threaten the project scope. When reacting to threats as an approach to the Risk Management Process, it becomes possible to reduce the impact to zero by either avoiding, reducing or transferring the risks. Threats can be divided into five categories; Avoid, Transfer, Mitigate/Reduce, Accept, Escalate.
  
Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management".'' Marcel Dekker Inc.
+
'''Avoid'''  
  
 +
Threat avoidance is when the project team seeks to eliminate the uncertainties by making it impossible for the risk to occur or protects the project from its impact by executing the project differently so that the objectives are achieved but avoids the risk so that it has no impact on the project <ref name=RiskResponse> Hillson, D. (2002). ''Extending the risk process to manage opportunities. International Journal of Project Management'', (pp. 235–240). Retrieved from https://doi.org/10.1016/S0263-7863(01)00074-6 </ref>.
  
 +
'''Transfer'''
  
== Risk Management Process ==
+
By transferring the risk, another stakeholder is identified who is better at managing the risk and is responsible for the right action being taken. They are therefore responsible for bearing the risk if it occur <ref name=PMI/>. This can be done when the project manager acknowledge his lack in expertise and wants a third party to manage the risk.
  
abc
 
  
Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management".'' Marcel Dekker Inc.
+
'''Mitigate'''
  
== Risk Treatment ==
+
When mitigating the risk, action is taken to reduce the impact of a threat or reducing the probability of occurrence. Reducing the size of the risk in early stages will make it more acceptable to the project. ''"Early mitigation action is often more effective than trying to repair the
 +
damage after the threat has occurred"'' <ref name=PMI/>.
  
The importance of risk treatment lies in the fact that risks are decisive for whether a project will be a success or not. By not managing the risks, the consequence can be fatal. Barry Boehm states the consequence as ''"If you
+
The goal of the threat is to acknowledge its existence and deal with it so that it does the least damage to the project. For this, an Impact matrix can be used for the threat, and can be used to take proactive precautions against the threat. The probability impact matrix can be seen in figure 5.
don’t actively attack the risks, they will actively attack you".''
+
  
  
 +
'''Accept'''
  
 +
The acceptance of a threat is when one acknowledges the threat's existence without taking any action against it. By actively accepting a risk, a contingency plan can be made which is triggered when an event occurs. Threat acceptance can also include passive acceptance, which means doing nothing <ref name=PMI/>.
  
Risk management is driven by the desire to succeed.
+
'''Escalate'''
  
 +
Escalation is used when a project team agrees that the threat is outside the scope of the project or when the action exceeds the project manager's authority <ref name=PMI/>. This could, for example, be change in laws that could have an effect on the project but the project team are not able to do any actions against it.
  
 +
=== Opportunities ===
 +
Opportunities are uncertainties and unexpected events that can effect the project positive and aid the project scope. Opportunities can be divided into five categories; Exploit, Share, Enhance, Accept/Ignore, Escalate.
  
=== Extra? ===
+
'''Exploit'''
 +
The exploit strategy acts to ensure the identified opportunity occur (increase the probability to 100%). ''"Aggressive measures are taken which seek to ensure that the benefits from this opportunity are realised by the project"'' <ref name=RiskResponse/>. This strategy corresponds to the "avoid" response.
  
abc
+
'''Share'''
may be to blame for lower success
+
  
== NOTES: ==
+
The sharing strategy involves sharing the risk with a stakeholder who is better at securing the benefit of the risk opportunity <ref name=PMI/>. This is done when the project manager acknowledge a higher value when sharing the opportunity to another stakeholder.
  
When reacting to threats, ARTA (Avoid, Reduce, Transfer, Accept) can be used as an approach to the Risk Management Process. The goal is to reduce the impact to zero by either avoiding, reducing or transferring the risks.
+
'''Enhance'''
  
Some of the response strategies to threats and Opportunities will also be highlighted in this article
+
The enhancing strategy seeks to increase the probability of the risk to occur. The opportunity of the risk also aims to increase the impact of the risk in order to maximize the benefit to the project <ref name=RiskResponse/>. ''"Early enhancement action is often more effective than trying to improve the opportunity after it has occurred"'' <ref name=PMI/>.
  
By using risk management, it is possible to ensure that the project team achieves the goals they are solving
+
'''Accept/Ignore'''
  
Risk management is a five-step monitoring process that establishes context, identifies, analyzes, evaluates and addresses potential risks over the life of a project.
+
Accepting or ignoring the opportunities is done when the risk has a minor impact on the project. The existence of the opportunity is acknowledged but no proactive action is planned <ref name=PMI/>.
  
 +
[[File:Priority_of_The_Response_Strategy_for_Threats_and_Opportunities.png|right|thumb|350px|Figure 4: Priority of The Response Strategy for Threats and Opportunities <ref name=Hillson/> ]]
  
Risk can be either threats or opportunities...
+
'''Escalate'''
  
Risk treatment is a way to manage and act on the identified risks.
+
Escalation is used when a project team agrees that the threat is outside the scope of the project or when the action exceeds the project manager's authority <ref name=PMI/>. This could, for example, be change in laws that could have an effect on the project but the project team are not able to do any actions against it.
  
 +
Some project management theories exclude the Escalate strategy since in every project you cannot any take actions against them besides identify the risks and recognize that they are outside the scope of the project. This applies to both threats and opportunities.
  
 +
== Priority of Opportunities and Threats ==
 +
When managing threats and opportunities it is important to prioritize the response strategy of the identified risks. In the previous section, the strategies are prioritized so that the strategies described first are the most important. It can also be seen in figure 4, which shows the priority order of the responses <ref name=Hillson/>. When this approach is used, one will initially look at '''"Avoid"''' and '''"Exploit"''', as they have the greatest potential and impact on the project. The second priority is '''"Transfer"''' and '''"Share"''', here the search is for another stakeholder who can either manage the risk to maximize a opportunity or minimize a threat in order to control the impact of the risk. The third priority is '''"Mitigate"''' and '''"Enhance"''', which are used when it is not possible to avoid/exploit or transfer/share the risk. The last response strategy '''Accept/Ignore''' is used when the other response strategies have been considered and the risk is identified as being of minor importance/impact.
  
(CONTENT)
+
One way to do a qualitative risk analysis is by using a ''"Double Probability Impact Matrix"'' which is used to set up the identified risks and determine their likelihood and potential effect on the project objectives, allowing risks to be prioritised for further attention <ref name=RiskResponse/>. The "Double Probability Impact Matrix" will be described in the following section.
  
This is a page will be elaborated on the following topics:
+
== Probability Impact Matrix for Opportunities and Threats ==
 +
[[File:Double_Probability_Impact_Matrix.png|right|thumb|350px|Figure 5: The "Double Probability Impact Matrix" for threats and opportunities <ref name=RiskResponse/> ]]
  
* Managing threats and opportunities in risk treatment introduction (known knowns?, risk management, risk treatment)
+
The goal for risk treatment is to minimize the identified risks that have a negative impact, and to maximize the risks that have a positive impact. By using qualitative risk analyses, it is possible to determine their likelihood and potential effects on the current project objectives. The primary technique used is the Probability Impact Matrix, which makes it possible to prioritize the risks for further attention <ref name=RiskResponse/>. Each risk is assessed against some criteria and placed on a two-dimensional grid. The location of the risk on the matrix describes the significance of the risk, allowing the risk to be ranked. The ''"Probability Impact Matrix"'' is illustrated in figure 5, showing the areas of attention for threats and opportunities.
  
* Risk management process (the 5 stages in the risk management process)
+
This approach is used to visualize both threats and opportunities in relation to their impact on the project. It may well be difficult to list the risks on the matrix, but by using this matrix the project manager can quickly get an overview of the identified risks he has to deal with. As can be seen in the figure, there is an "arrow of attention", which is the identified risks with the most positive/negative impact on the project. Hillson describe this area as ''"high-probability/high-impact risks are prioritised, since these are either'' '''''"show-stopper threats"''''' ''which must be avoided if possible or'' '''''"golden opportunities"''''' ''which must be exploited if possible"'' <ref name=RiskResponse/>.
  
* Responses to threats and opportunities
+
It should be noted, this matrix is ​​not a "fixed" model as some organizations find it more advantageous to divide the matrix into two models, one for threats and one for opportunities. Other organizations also have the opportunity side mirrored. However, this results in you not having the possibility to create an "arrow of attention" for the risks in the model. However, it is important to note that the risk management process is an iterative process and it is therefore necessary to revisit the model several times.
  
* Discussion and conclusion
+
== Discussion/conclusion ==
 +
This paper aimed to highlight the importance of the risk management process and more specifically delve into risk treatment process. In this section, the limitations and advantages of using risk treatment will be described, as it describes the theory, there are parts of the method which does not process cultural differences or the way of working in the company.
  
* References
+
=== Limitations ===
 +
When dealing with risk management, it is important to consider the work approach and the type of project being worked on. It is important to ensure that you have relevant project managers with experience in that area. Some of the limitations when prioritizing the risks can be when you do not have much experience or work with projects in other countries and cultures, and thus there is a probability that you prioritize the risks incorrectly.
  
 +
This can result in using too much time on risks that are not relevant and are more likely not to occur. In addition, there is chance that resources are not used on risks that are subsequently discovered to have a large impact on the project.
  
NOTES FOR ABSTRACT:
+
However, risk treatment is a good approach for creating an overview of the risks and ensuring that the right precautions have been taken. It is important to use tools that give the manager the best overview, as the manager would be able to act prioritized and correctly.  
 
+
The goal is to take procortions for the uncertainties and reduce the impact it can we on the project. This can be done by...
+
 
+
In project management there is a lot of uncertainties we need to prepare and take procortions for. By doing this it will be possible to prevent unknown factors that can occure. mannaging thorugout the whole projct.
+
 
+
The 5 steps in risk management
+
 
+
responding to threats - ARTA
+
 
+
Responding to opportunities
+
  
 +
Some of the recognized tools would be a SWOT Analysis, Root Cause Analysis, Risk Register or a Probability Impact Matrix. Depending on the project, some tools may be more advantageous to use and it is the project manager's responsibility to ensure that he use the tools that make the most sense for him.
  
 
== Annotated Bibliography ==
 
== Annotated Bibliography ==
 
'''Articles'''
 
'''Articles'''
# Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). <ref name=PMI/>
+
# Project Management Institute, Inc. (PMI). (2021). ''A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management''. (pp. 114-125). Project Management Institute, Inc. (PMI). <ref name=PMI/>
#* DESCRIPTION
+
#* Elaborates on the theory and terms behind uncertainties, risks and the prioritization of threats and opportunities. Use this article to learn more about the process behind risk treatment. 
 +
# Danish Standards Association (2018), DS/ISO 31000:2018, ''Risk management - Guidelines''. <ref name=ISO31000_2018/>
 +
#* Provides a good description of the risk management process, as well as benefits and important points in the seven steps.
 +
# ''There are unknown unknowns''. Retrieved February 10, 2023. <ref name=unknown/>
 +
#* Gives a description of unknown unknowns.
 +
# Hillson, D. (2002). ''Extending the risk process to manage opportunities. International Journal of Project Management'', (pp. 235–240). <ref name=RiskResponse/>
 +
#* Provides a detailed description of responses to threats and opportunities.
  
# Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines. <ref name=ISO31000_2018/>
+
'''Books'''
#* DESCRIPTION
+
# Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management"''. <ref name=Hillson/>
 +
#* Provides a detailed description of the Knowledge and awareness matrix and the relationship between risk and uncertainty.
 +
#  Krogerus, Mikael. ''"The decision book: fifty models for strategic thinking"'', 2012. <ref name=Krogerus/>
 +
#* Uses and describes the Rumsfeld Matrix.
  
 
+
'''Transcript'''
'''Books'''
+
Rumsfeld, Donald. ''"Defense.gov News Transcript: DoD News Briefing – Secretary Rumsfeld and Gen. Myers, United States Department of Defense (defense.gov)"''. February 12, 2002. <ref name=Rumsfeld/>
Hillson, David. ''"Effective Opportunity Management for Projects - Exploiting Positive Risk"'', 2003. Ch. 1. ''"The case for opportunity management"'' <ref name=Hillson/>
+
#* A transcript of Donald Rumsfeld gave to a question at a U.S. Department of Defense (DoD) news briefing on February 12, 2002.
#* Description
+
  
 
== References ==
 
== References ==

Latest revision as of 15:48, 2 April 2023

Developed by Theis Rosenkvist Sørensen

Risk treatment is the final stage in the risk management process. It is used to control and monitor the uncertainties during the project. When managing a project, uncertainties are one of the most important factors to control in order to achieve a successful project. Uncertainties occur when certain events in a project are unpredictable and it will only be possible to guess about a future event. Risk management is used to identify risks in the project that help maintain stability and used to prevent unforeseen events that can be cost, resource or time consuming. By using risk management, it is possible to ensure that the project team achieves the goals they are solving by not encountering many unpredictable obstacles during the project.

The risk management process is a seven-step iterative process: Communication & Consultation, Establish Context/Scope/Criteria, Identify Risks, Analyze Risks, Evaluate Risk, Risk treatment and Monitoring & Review [1]. This is done throughout the projects lifetime. By managing the project using responses to threats and opportunities, it becomes possible to minimize the impact of the risk. If it can be done in a successful way, better risk management is achieved and it will thus be possible to reduce the impact of the uncertainties in the project. By using Rumsfeld matrix, it becomes possible to reduce the risk by establishing precautions that can prevent or reduce the uncertainties from arising.

When working with risk treatment, there are some limitations. One of the crucial limitations is the lack of knowledge sharing. The lack of knowledge sharing leads to a greater amount of uncertainties that could have been prevented. However, not all uncertainties can be prevented and even perfectly planned projects have their limitations. By having a greater amount of expertise, a higher level of risk treatment can be performed and will minimize the risk by identifying crucial uncertainties in the project.

This paper aims to highlight the importance of the risk management process and more specifically delve into risk treatment process.

Contents

[edit] Introduction

[edit] The Risk Management Process

Figure 1: The Risk Management Process [1]

Risk management is a process that works to manage risks to ensure that it cause the least impact in the project. Risk management is based on assumptions and experience from previous projects. However, many assumptions are uncertain which can have an effect on the project's original scope. The Project Management Institute (PMI), describes risks as "An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives" [2]. By successfully navigating the uncertainty, risk can be managed in a way that is most beneficial to the project scope.

The process involves a "systematic application of policies, procedures and practices to the activities of communicating and consulting, establishing the context and assessing, treating, monitoring, reviewing, recording and reporting risk" [1]. It should be noted that there can be many different applications of the risk management process, as it can be adapted to a particular project to achieve specific goals within the organization.

When operating the risk management process, take into account that the process is an iterative approach and it is important to go back and assess whether there have been changes in the previous stages that could create new potential risks that the project manager needs to adapt in their risk assessment. The stages are illustrated in Figure 1 [1].

[edit] Knowledge and awareness

Figure 2: Knowledge and Awareness [3]

David Hillson describes the difference between risk and uncertainties. He states that "risk" has a set of possible outcomes that are known, but that the precise outcome is not known in advance. In contrast, uncertainties relates to a lack of knowledge about the possible outcomes and are thus an unknown event from an unknown number of possible outcomes [3].

Based on these descriptions, the relationship between risk and uncertainty can be described as:

"Risk is measurable uncertainty"; "Uncertainty is unmeasurable risk" [3].

Another way to distinguish the relationship between risk and uncertainty is by looking at the relationship between knowledge and awareness. Figure 2 illustrates four quadrants where knowledge and awareness are either present or absent. The figure is a similar concept to the Johari Window, which describes self-awareness and perception by others [3]. The top right corner of the quadrant certainty is illustrated, where both awareness and knowledge are present. An example could be a known number of square meters on which a building must be built or the appearance of the building so that it fits a certain cityscape. The top left corner illustrate caution, which describe the things that are uncertain. This could be, for example, the weather conditions next week. Under certainty we have amnesia which describes the lack of awareness or a blind spot regarding the knowledge we have. An example of this could be, bad planning, poor communication or acting on intuition and biases. The project manager can practice self-awareness to identify them. The last quadrant is Ignorance, where "we don't know what we don't know". An example of this could be the beginning of a war or an unpredictable natural disaster.

[edit] Donald Rumfeld's Unknown-unknowns

Figure 3: The Connection Between Hillson's Knowledge and Awareness figure[3] & Rumsfeld Matrix[4]

The knowledge and awareness figure created by Hillson and the Johari Window is a comparison to the known description used by the former U.S. Secretary of Defense Donald Rumsfeld at a press conference in 2002. He described the types of uncertainties as:

"Reports that say that something hasn't happened are always interesting to me, because as we know, there are known knowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But there are also unknown unknowns – the ones we don't know we don't know" [5].

This statement became known as Rumsfeld matrix when the author Mikael Krogerus refers to it in his book "The decision book : fifty models for strategic thinking" [6]. Figure 3 illustrates the connection between Hillson's Knowledge and Awareness figure & Rumsfeld Matrix[4].

[edit] Overview of The Risk Management Process

The risk management process is a seven-step iterative process, which can be seen in figure 1. The process is described below in proper order. This section describes an overview of the risk management process. It will not be in-depth, but can be used to create an understanding of the entire process. For a more detailed review of the seven steps, an elaboration can be found in "DS/ISO 31000:2018, Risk management - Guidelines" [1].

  1. Communication & Consultation
    The purpose of communication and consultation is to share relevant information with identified and relevant stakeholders. There must be close coordination between the stakeholders to ensure a shared understanding of the project's scope and criteria. The purpose of this phase is to bring stakeholders together with different expertise and ensure that there is enough information to facilitate sufficient risk overview and decision-making. However, it is also important to ensure that the different points of view are appropriately considered when defining risk criteria and when evaluating risks [1]. Communication and consultation will result in a focus on the project's scope, context and criteria.

  2. Scope, Context and Criteria
    In this step, the goal is to establish the objects, scope, context and criteria. The scope is used by the organization to define its risk management activities. The process is applied at several levels such as strategic, operational, programme, project and other activities. This implies considerations about appropriate risk assessment tools and techniques, objectives and decitions need to be made, expected outcomes from the steps taken in the process, resources, etc [1]. An elaboration can be found in "DS/ISO 31000:2018, Risk management - Guidelines" [1]. The context is used to describe the environment for the project both externally and internally. The organization will seek to define and achieve its objectives. The criteria define the type of risk that affects the objects. The risks must be evaluated in relation to their significance and support the decision-making process.

  3. Risk identification
    The purpose of the risk identification process is to identify, describe and recognize risks that can have a positive or negative impact on the organization in achieving its objectives. Risk identification is an iterative process which is connected to the risk analysis and the risk evaluation. These three steps combined are named "risk assessment" and is illustrated in figure 1.

  4. Risk Analysis
    Risk analysis is used to understand the risk and its characteristics. A risk analysis involves considerations about scenarios, uncertainties, consequences, risk sources, complexity, probability, control and its effectiveness [1]. The risk analysis is used to determine its level of risk and can vary according to the purpose of the analysis. Tools for determining a risk analysis could be, for example, a SWOT Analysis, Root Cause Analysis, Risk Register or a Probability Impact Matrix, which is described in this article (see figure 5). By making a risk analysis, a better understanding of which risk treatment is required is created.

  5. Risk Evaluation
    The purpose of risk evaluation is to support decisions taken in the project. The evaluation involves a comparison of results obtained in the risk analysis with the established risk criteria to assess where additional action is required [1]. The risk evaluation can lead to consideration of treatment options, further analysis or reconsideration of objectives.

  6. Risk Treatment
    The importance of risk treatment can determine whether a project will be a success or not. The purpose of risk treatment is to implement options that address the risks. "DS/ISO 31000:2018, Risk management - Guidelines" describes risk treatment as a process of [1]:
    - formulating and selecting risk treatment options;
    - planning and implementing risk treatment;
    - assessing the effectiveness of risk treatment;
    - deciding whether the remaining risk is acceptable;
    - if not acceptable, taking further treatment.
    Further elaboration of risk treatment will be described in the following section.

  7. Monitoring & Review
    The purpose of monitoring and review is to consider the previous steps and assess the quality and effectiveness of the process design, implementation and outcomes. By doing this, an iterative process of the entire risk management process has been created and it is possible as a project manager to assess errors and shortcomings that will strengthen future similar projects. This is done by recording and reporting during the process and creating additional treatment plans (analysis) for new identified risks to improve risk management activities. Furthermore, it is important to communicate risk management activities and results across the organization, as well as having good interaction with stakeholders, including those responsible for some of the risk management activities [1].

[edit] Risk Treatment

The importance of risk treatment lies in the fact that risks are decisive for whether a project will be a success or not. By not managing the risks, the consequence can be fatal. Barry Boehm states the consequence as "If you don’t actively attack the risks, they will actively attack you" [7]. Risks can be both threats and opportunities as they can have either a positive or negative impact on the project. This section will describe the response strategies to threats and opportunities.

[edit] Threats

Threats are uncertainties and unexpected events that can effect the project negative and threaten the project scope. When reacting to threats as an approach to the Risk Management Process, it becomes possible to reduce the impact to zero by either avoiding, reducing or transferring the risks. Threats can be divided into five categories; Avoid, Transfer, Mitigate/Reduce, Accept, Escalate.

Avoid

Threat avoidance is when the project team seeks to eliminate the uncertainties by making it impossible for the risk to occur or protects the project from its impact by executing the project differently so that the objectives are achieved but avoids the risk so that it has no impact on the project [8].

Transfer

By transferring the risk, another stakeholder is identified who is better at managing the risk and is responsible for the right action being taken. They are therefore responsible for bearing the risk if it occur [2]. This can be done when the project manager acknowledge his lack in expertise and wants a third party to manage the risk.


Mitigate

When mitigating the risk, action is taken to reduce the impact of a threat or reducing the probability of occurrence. Reducing the size of the risk in early stages will make it more acceptable to the project. "Early mitigation action is often more effective than trying to repair the damage after the threat has occurred" [2].

The goal of the threat is to acknowledge its existence and deal with it so that it does the least damage to the project. For this, an Impact matrix can be used for the threat, and can be used to take proactive precautions against the threat. The probability impact matrix can be seen in figure 5.


Accept

The acceptance of a threat is when one acknowledges the threat's existence without taking any action against it. By actively accepting a risk, a contingency plan can be made which is triggered when an event occurs. Threat acceptance can also include passive acceptance, which means doing nothing [2].

Escalate

Escalation is used when a project team agrees that the threat is outside the scope of the project or when the action exceeds the project manager's authority [2]. This could, for example, be change in laws that could have an effect on the project but the project team are not able to do any actions against it.

[edit] Opportunities

Opportunities are uncertainties and unexpected events that can effect the project positive and aid the project scope. Opportunities can be divided into five categories; Exploit, Share, Enhance, Accept/Ignore, Escalate.

Exploit The exploit strategy acts to ensure the identified opportunity occur (increase the probability to 100%). "Aggressive measures are taken which seek to ensure that the benefits from this opportunity are realised by the project" [8]. This strategy corresponds to the "avoid" response.

Share

The sharing strategy involves sharing the risk with a stakeholder who is better at securing the benefit of the risk opportunity [2]. This is done when the project manager acknowledge a higher value when sharing the opportunity to another stakeholder.

Enhance

The enhancing strategy seeks to increase the probability of the risk to occur. The opportunity of the risk also aims to increase the impact of the risk in order to maximize the benefit to the project [8]. "Early enhancement action is often more effective than trying to improve the opportunity after it has occurred" [2].

Accept/Ignore

Accepting or ignoring the opportunities is done when the risk has a minor impact on the project. The existence of the opportunity is acknowledged but no proactive action is planned [2].

Figure 4: Priority of The Response Strategy for Threats and Opportunities [3]

Escalate

Escalation is used when a project team agrees that the threat is outside the scope of the project or when the action exceeds the project manager's authority [2]. This could, for example, be change in laws that could have an effect on the project but the project team are not able to do any actions against it.

Some project management theories exclude the Escalate strategy since in every project you cannot any take actions against them besides identify the risks and recognize that they are outside the scope of the project. This applies to both threats and opportunities.

[edit] Priority of Opportunities and Threats

When managing threats and opportunities it is important to prioritize the response strategy of the identified risks. In the previous section, the strategies are prioritized so that the strategies described first are the most important. It can also be seen in figure 4, which shows the priority order of the responses [3]. When this approach is used, one will initially look at "Avoid" and "Exploit", as they have the greatest potential and impact on the project. The second priority is "Transfer" and "Share", here the search is for another stakeholder who can either manage the risk to maximize a opportunity or minimize a threat in order to control the impact of the risk. The third priority is "Mitigate" and "Enhance", which are used when it is not possible to avoid/exploit or transfer/share the risk. The last response strategy Accept/Ignore is used when the other response strategies have been considered and the risk is identified as being of minor importance/impact.

One way to do a qualitative risk analysis is by using a "Double Probability Impact Matrix" which is used to set up the identified risks and determine their likelihood and potential effect on the project objectives, allowing risks to be prioritised for further attention [8]. The "Double Probability Impact Matrix" will be described in the following section.

[edit] Probability Impact Matrix for Opportunities and Threats

Figure 5: The "Double Probability Impact Matrix" for threats and opportunities [8]

The goal for risk treatment is to minimize the identified risks that have a negative impact, and to maximize the risks that have a positive impact. By using qualitative risk analyses, it is possible to determine their likelihood and potential effects on the current project objectives. The primary technique used is the Probability Impact Matrix, which makes it possible to prioritize the risks for further attention [8]. Each risk is assessed against some criteria and placed on a two-dimensional grid. The location of the risk on the matrix describes the significance of the risk, allowing the risk to be ranked. The "Probability Impact Matrix" is illustrated in figure 5, showing the areas of attention for threats and opportunities.

This approach is used to visualize both threats and opportunities in relation to their impact on the project. It may well be difficult to list the risks on the matrix, but by using this matrix the project manager can quickly get an overview of the identified risks he has to deal with. As can be seen in the figure, there is an "arrow of attention", which is the identified risks with the most positive/negative impact on the project. Hillson describe this area as "high-probability/high-impact risks are prioritised, since these are either "show-stopper threats" which must be avoided if possible or "golden opportunities" which must be exploited if possible" [8].

It should be noted, this matrix is ​​not a "fixed" model as some organizations find it more advantageous to divide the matrix into two models, one for threats and one for opportunities. Other organizations also have the opportunity side mirrored. However, this results in you not having the possibility to create an "arrow of attention" for the risks in the model. However, it is important to note that the risk management process is an iterative process and it is therefore necessary to revisit the model several times.

[edit] Discussion/conclusion

This paper aimed to highlight the importance of the risk management process and more specifically delve into risk treatment process. In this section, the limitations and advantages of using risk treatment will be described, as it describes the theory, there are parts of the method which does not process cultural differences or the way of working in the company.

[edit] Limitations

When dealing with risk management, it is important to consider the work approach and the type of project being worked on. It is important to ensure that you have relevant project managers with experience in that area. Some of the limitations when prioritizing the risks can be when you do not have much experience or work with projects in other countries and cultures, and thus there is a probability that you prioritize the risks incorrectly.

This can result in using too much time on risks that are not relevant and are more likely not to occur. In addition, there is chance that resources are not used on risks that are subsequently discovered to have a large impact on the project.

However, risk treatment is a good approach for creating an overview of the risks and ensuring that the right precautions have been taken. It is important to use tools that give the manager the best overview, as the manager would be able to act prioritized and correctly.

Some of the recognized tools would be a SWOT Analysis, Root Cause Analysis, Risk Register or a Probability Impact Matrix. Depending on the project, some tools may be more advantageous to use and it is the project manager's responsibility to ensure that he use the tools that make the most sense for him.

[edit] Annotated Bibliography

Articles

  1. Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). [2]
    • Elaborates on the theory and terms behind uncertainties, risks and the prioritization of threats and opportunities. Use this article to learn more about the process behind risk treatment.
  2. Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines. [1]
    • Provides a good description of the risk management process, as well as benefits and important points in the seven steps.
  3. There are unknown unknowns. Retrieved February 10, 2023. [6]
    • Gives a description of unknown unknowns.
  4. Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, (pp. 235–240). [8]
    • Provides a detailed description of responses to threats and opportunities.

Books

  1. Hillson, David. "Effective Opportunity Management for Projects - Exploiting Positive Risk", 2003. Ch. 1. "The case for opportunity management". [3]
    • Provides a detailed description of the Knowledge and awareness matrix and the relationship between risk and uncertainty.
  2. Krogerus, Mikael. "The decision book: fifty models for strategic thinking", 2012. [4]
    • Uses and describes the Rumsfeld Matrix.

Transcript

  1. Rumsfeld, Donald. "Defense.gov News Transcript: DoD News Briefing – Secretary Rumsfeld and Gen. Myers, United States Department of Defense (defense.gov)". February 12, 2002. [5]
    • A transcript of Donald Rumsfeld gave to a question at a U.S. Department of Defense (DoD) news briefing on February 12, 2002.

[edit] References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 Danish Standards Association (2018), DS/ISO 31000:2018, Risk management - Guidelines, Retrieved from https://sd.ds.dk/Viewer/Standard?ProjectNr=M296412&Status=60.60&VariantID=41&Page=0
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 Project Management Institute, Inc. (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) – 7th Edition and The Standard for Project Management. (pp. 114-125). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/pdf/id:kt012LZJB1/guide-project-management/opportunities
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Hillson, David. "Effective Opportunity Management for Projects - Exploiting Positive Risk", 2003. Ch. 1. "The case for opportunity management". Marcel Dekker Inc.
  4. 4.0 4.1 4.2 Krogerus, Mikael. "The decision book: fifty models for strategic thinking", 2012.
  5. 5.0 5.1 Rumsfeld, Donald. "Defense.gov News Transcript: DoD News Briefing - Secretary Rumsfeld and Gen. Myers, United States Department of Defense (defense.gov)". February 12, 2002. Retrieved from https://archive.ph/20180320091111/http://archive.defense.gov/Transcripts/Transcript.aspx?TranscriptID=2636#selection-1053.10-1053.342
  6. 6.0 6.1 There are unknown unknowns. Retrieved February 10, 2023. Retrieved from https://en.wikipedia.org/wiki/There_are_unknown_unknowns
  7. Forsberg, K., & Mooz, H. RISK AND OPPORTUNITY MANAGEMENT. (1996). INCOSE International Symposium, pp. 586–598. Retrieved from https://doi.org/10.1002/j.2334-5837.1996.tb02057.x
  8. 8.0 8.1 8.2 8.3 8.4 8.5 8.6 8.7 Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, (pp. 235–240). Retrieved from https://doi.org/10.1016/S0263-7863(01)00074-6



Made by Theis Sørensen (s195768)

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox