Kanban in Project Management

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 1: Line 1:
 
Kanban|看板 directly translates to signboard from Japanese. The Kanban system was originally a inventory-control system developed by developed by Taiichi Ohno, an industrial engineer at Toyota to reduce the waste (muda) in the production line and by that improve the manufacturing efficiency.  
 
Kanban|看板 directly translates to signboard from Japanese. The Kanban system was originally a inventory-control system developed by developed by Taiichi Ohno, an industrial engineer at Toyota to reduce the waste (muda) in the production line and by that improve the manufacturing efficiency.  
 
The Kanban system is with some alterations applied as an agile project management tool. The basis of this concept is to have a board with cards attached. Different parts on the board represent several stages of the development that all tasks go through. The cards represent the different tasks in the project, and move from left to right on the board. The board can be set-up and divided however the user like, nonetheless the main concept is always the same and can be summarized by these six points
 
The Kanban system is with some alterations applied as an agile project management tool. The basis of this concept is to have a board with cards attached. Different parts on the board represent several stages of the development that all tasks go through. The cards represent the different tasks in the project, and move from left to right on the board. The board can be set-up and divided however the user like, nonetheless the main concept is always the same and can be summarized by these six points
Limit WIP (work in process): The board is divided in parts, and each part can only have a set number of tasks, thus this don't need to be the same for every part. This is true for all parts except the “start” and “finished” part, which is always unlimited
+
#Limit WIP (work in process): The board is divided in parts, and each part can only have a set number of tasks, thus this don't need to be the same for every part. This is true for all parts except the “start” and “finished” part, which is always unlimited
Cards : Each task is represented by a card (post-it note or similar)
+
#Cards : Each task is represented by a card (post-it note or similar)
Flow: The tasks on the board are moved from left to right between the different parts. The person performing the task is moving the post-it
+
#Flow: The tasks on the board are moved from left to right between the different parts. The person performing the task is moving the post-it
Team: The team working with the tasks agree on some rules for when a task can be set as finished.
+
#Team: The team working with the tasks agree on some rules for when a task can be set as finished.
Kaizen (constant improvement) 1: The team working with the Kanban board have to get together on a regular basis to analyze the flow. Focusing on tasks that are stuck on the board
+
#Kaizen (constant improvement) 1: The team working with the Kanban board have to get together on a regular basis to analyze the flow. Focusing on tasks that are stuck on the board
Kaizen (constant improvement) 2: There is no Kanban police - and if you need to alter your board or break your rules that's ok, but let the rest of your team know.
+
#Kaizen (constant improvement) 2: There is no Kanban police - and if you need to alter your board or break your rules that's ok, but let the rest of your team know.
 
+
== The board ==
+
 
+
The Kanban boards for project management most often consists of three main parts “To Do”, “DOING” and “Done”. Each of these is divided in two or more sub sections. There are many reasons for doing this, the main one being to visualize when the task is ready to go to the next main part.
+
 
+
 
+
To Do
+
 
+
In this section all tasks that are in your “backlog” is placed. This part of the board have no rules for a upper limit. The number of tasks here is most often limited by your lack of knowledge of the future, as you don't know all the “To Do” tasks yet.
+
 
+
To enhance the flow of your board you can make a “Breakdown” part subsequent to the “To Do”. This Breakdown part is managed by a rule. This can forexaple be that all task must be limited to take approximately two working days. If the task initially is longer/larger than this, it is divided into several smaller tasks before moving on to the next part of your board. When the tasks are placed here, thay are ready for the next main part “Doing”
+
 
+
Doing
+
 
+
In this part of the board all task that are worked on are located. This part of the board is almost always divided into several smaller parts. An example of this can be Plan, Develop, Test and Deploy.
+
 
+
Plan
+
 
+
In this section the work is planned, this can be allocation of resources or finding a possible solution
+
 
+
Develop
+
 
+
Here is where the task go from an ide to a product. This section is also often divided to the sub sections In Process and Done. The reason for having a Done part, is to make it visual when the tasks is ready to be transferred to the next stage, testing.
+
Testing
+

Revision as of 07:47, 8 September 2016

Kanban|看板 directly translates to signboard from Japanese. The Kanban system was originally a inventory-control system developed by developed by Taiichi Ohno, an industrial engineer at Toyota to reduce the waste (muda) in the production line and by that improve the manufacturing efficiency. The Kanban system is with some alterations applied as an agile project management tool. The basis of this concept is to have a board with cards attached. Different parts on the board represent several stages of the development that all tasks go through. The cards represent the different tasks in the project, and move from left to right on the board. The board can be set-up and divided however the user like, nonetheless the main concept is always the same and can be summarized by these six points

  1. Limit WIP (work in process): The board is divided in parts, and each part can only have a set number of tasks, thus this don't need to be the same for every part. This is true for all parts except the “start” and “finished” part, which is always unlimited
  2. Cards : Each task is represented by a card (post-it note or similar)
  3. Flow: The tasks on the board are moved from left to right between the different parts. The person performing the task is moving the post-it
  4. Team: The team working with the tasks agree on some rules for when a task can be set as finished.
  5. Kaizen (constant improvement) 1: The team working with the Kanban board have to get together on a regular basis to analyze the flow. Focusing on tasks that are stuck on the board
  6. Kaizen (constant improvement) 2: There is no Kanban police - and if you need to alter your board or break your rules that's ok, but let the rest of your team know.
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox