Earned Value Analysis
(→Requirements) |
|||
Line 11: | Line 11: | ||
== Requirements == | == Requirements == | ||
+ | In order to successfully execute an Earned Value Analysis, the following systematic preconditions and requirements must be fulfilled. | ||
+ | |||
+ | '''Time-based schedule''' | ||
+ | The measurement of progress is made on the basis of a work schedule, which must be defined and agreed, including a clear timeline and an estimation of | ||
+ | |||
+ | '''Work Breakdown Structure''' | ||
+ | All tasks and their specific scope must be defined seperately in the form of a work breakdown structure. This is necessary to control the progress of individual activities, as well as for an exact allocation of cost. | ||
+ | |||
+ | '''Cost Assessment''' | ||
+ | A cost collection system including an appropriate association of cost estimates, which can then be cumulated in order to obtain the the actual cost, as well as the cost for given time periods, e.g. per week/month | ||
+ | |||
+ | '''Progress measurement''' | ||
+ | An objective, consistent, quantitative method of assessing progress | ||
+ | |||
+ | '''Responsibility/ authority matrix''' | ||
+ | |||
+ | '''Monitoring and review process of all variables''' | ||
+ | in order to identify changes | ||
+ | |||
+ | ‘Implementing Best Practice in Hospital Project Management Utilising EVPM methodology’, Raf Dua (1999): | ||
== Areas of application == | == Areas of application == |
Revision as of 15:46, 10 September 2016
Abstract
In order to measure performance in terms of cost, time and work progress, the Earned Value Analysis (EVA) is introduced as a suitable method, offering quantitative analysis techniques as well as objective performance indicators. Besides giving an overview of the method itself and the steps, which must be followed in order to carry out an EVA, the requirements on both structural and methodological level are presented and the key benefits are outlined. In addition to its’ primary area of application as a tool within project controlling, the extended usability of the method in other key functions of a company is shown. All technical contents are being demonstrated based on illustrative examples.
Contents |
Definition
Requirements
In order to successfully execute an Earned Value Analysis, the following systematic preconditions and requirements must be fulfilled.
Time-based schedule The measurement of progress is made on the basis of a work schedule, which must be defined and agreed, including a clear timeline and an estimation of
Work Breakdown Structure All tasks and their specific scope must be defined seperately in the form of a work breakdown structure. This is necessary to control the progress of individual activities, as well as for an exact allocation of cost.
Cost Assessment A cost collection system including an appropriate association of cost estimates, which can then be cumulated in order to obtain the the actual cost, as well as the cost for given time periods, e.g. per week/month
Progress measurement An objective, consistent, quantitative method of assessing progress
Responsibility/ authority matrix
Monitoring and review process of all variables in order to identify changes
‘Implementing Best Practice in Hospital Project Management Utilising EVPM methodology’, Raf Dua (1999):