Critical Path Method (CPM)

From apppm
(Difference between revisions)
Jump to: navigation, search
(Example of Critical Path Method)
(Example of Critical Path Method)
Line 121: Line 121:
  
 
== Example of Critical Path Method ==
 
== Example of Critical Path Method ==
 
Example
 
  
 
Based on the below network diagram, identify the total paths, critical path, and float for each path.
 
Based on the below network diagram, identify the total paths, critical path, and float for each path.
 +
 
[[File:A1.png]]
 
[[File:A1.png]]
 +
 
The above network diagram has five paths; the paths and their duration are as follows:
 
The above network diagram has five paths; the paths and their duration are as follows:
  
Start -> A -> B -> C-> End, duration: 31 days.
+
1. Start -> A -> B -> C-> End, duration: 31 days.
Start ->D -> E ->F -> End, duration: 18 days.
+
2. Start ->D -> E ->F -> End, duration: 18 days.
Start -> D -> B -> C -> End, duration: 26 days.
+
3. Start -> D -> B -> C -> End, duration: 26 days.
Start -> G ->H ->I -> End, duration: 13 days.
+
4. Start -> G ->H ->I -> End, duration: 13 days.
Start -> G -> E ->F -> End, duration: 16 days.
+
5. Start -> G -> E ->F -> End, duration: 16 days.
  
 
Since the duration of the first path is the longest, it is the critical path. The float on the critical path is zero.
 
Since the duration of the first path is the longest, it is the critical path. The float on the critical path is zero.
Line 147: Line 147:
 
Float for the fifth path = 31 – 16 = 15 days.
 
Float for the fifth path = 31 – 16 = 15 days.
  
Calculate Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF)
+
'''Calculate Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF)'''
  
 
We have identified the critical path, and the duration of the other paths, it’s time to move on to more advanced calculations, Early Start, Early Finish, Late Start and Late Finish.
 
We have identified the critical path, and the duration of the other paths, it’s time to move on to more advanced calculations, Early Start, Early Finish, Late Start and Late Finish.
  
Calculating Early Start (ES) and Early Finish (EF)
+
'''Calculating Early Start (ES) and Early Finish (EF)'''
  
 
To calculate the Early Start and Early Finish dates, we use forward pass; we will start from the beginning and proceed to the end.
 
To calculate the Early Start and Early Finish dates, we use forward pass; we will start from the beginning and proceed to the end.
Line 161: Line 161:
 
Early Start of the activity = Early Finish of predecessor activity + 1
 
Early Start of the activity = Early Finish of predecessor activity + 1
 
Early Finish of the activity = Activity duration + Early Start of activity – 1
 
Early Finish of the activity = Activity duration + Early Start of activity – 1
Early Start and Early Finish Dates for the path Start -> A -> B -> C -> End
 
  
 +
'''Early Start and Early Finish Dates for the path Start -> A -> B -> C -> End'''
 +
 +
[[File:AA2.png]]
  
 
Early Start of activity A = 1 (Since this is the first activity of the path)
 
Early Start of activity A = 1 (Since this is the first activity of the path)
 +
 
Early Finish of activity A = ES of activity A + activity duration – 1
 
Early Finish of activity A = ES of activity A + activity duration – 1
 
= 1 + 10 – 1 = 10
 
= 1 + 10 – 1 = 10
 +
 
Early Start of activity B = EF of predecessor activity + 1
 
Early Start of activity B = EF of predecessor activity + 1
 
= 10 +1 = 11
 
= 10 +1 = 11
 +
 
Early Finish of activity B = ES of activity B + activity duration – 1
 
Early Finish of activity B = ES of activity B + activity duration – 1
 
= 11 + 12 – 1 = 22
 
= 11 + 12 – 1 = 22
 +
 
Early Start of activity C = EF of predecessor activity + 1
 
Early Start of activity C = EF of predecessor activity + 1
 
= 22 +1 = 23
 
= 22 +1 = 23
 +
 
Early Finish of activity C = ES of activity C + activity duration – 1
 
Early Finish of activity C = ES of activity C + activity duration – 1
 
= 23 + 9 – 1 = 31
 
= 23 + 9 – 1 = 31
Early Start and Early Finish Dates for the path Start -> D -> E -> F -> End
 
  
 +
'''Early Start and Early Finish Dates for the path Start -> D -> E -> F -> End'''
 +
 +
[[File:A3.png]]
  
 
Early Start of activity D = 1 (Since this is the first activity of the path)
 
Early Start of activity D = 1 (Since this is the first activity of the path)
 +
 
Early Finish of activity D = 1 + 5 – 1 = 5
 
Early Finish of activity D = 1 + 5 – 1 = 5
 +
 
Early Start of activity E = EF of predecessor activity + 1
 
Early Start of activity E = EF of predecessor activity + 1
  
Line 188: Line 199:
 
Early Start of activity E = EF of predecessor activity + 1
 
Early Start of activity E = EF of predecessor activity + 1
 
= 5 + 1 = 6
 
= 5 + 1 = 6
 +
 
Early Finish of activity E = 6 + 7 – 1 = 12
 
Early Finish of activity E = 6 + 7 – 1 = 12
 +
 
Early Start of activity F = 12 + 1 = 13
 
Early Start of activity F = 12 + 1 = 13
 +
 
Early Finish of activity F = 13 + 6 -1 = 18
 
Early Finish of activity F = 13 + 6 -1 = 18
Early Start and Early Finish Dates for the path Start -> G -> H -> I -> End
 
  
 +
'''Early Start and Early Finish Dates for the path Start -> G -> H -> I -> End'''
 +
 +
[[File:A4.png]]
  
 
Early Start of activity G = 1 (Since this is the first activity of the path)
 
Early Start of activity G = 1 (Since this is the first activity of the path)
 
Early Finish of activity G = 1 + 3 – 1 = 3
 
Early Finish of activity G = 1 + 3 – 1 = 3
 +
 
Early Start of activity H = 3 + 1 = 4
 
Early Start of activity H = 3 + 1 = 4
 
Early Finish of activity H = 4 + 4 – 1 = 7
 
Early Finish of activity H = 4 + 4 – 1 = 7
 +
 
Early Start of activity I = 7 +1 = 8
 
Early Start of activity I = 7 +1 = 8
 
Early Finish of activity I = 8 + 6 – 1 = 13
 
Early Finish of activity I = 8 + 6 – 1 = 13
  
Calculating Late Start (LS) and Late Finish (LF)
+
'''Calculating Late Start (LS) and Late Finish (LF)'''
  
 
We have calculated Early Start and Early Finish dates of all activities. Now it is time to calculate the Late Start and Late Finish dates.
 
We have calculated Early Start and Early Finish dates of all activities. Now it is time to calculate the Late Start and Late Finish dates.
Line 212: Line 230:
  
 
To calculate the Late Start and Late Finish, we use backward pass; i.e. we will start from the last activity and move back towards the first activity.
 
To calculate the Late Start and Late Finish, we use backward pass; i.e. we will start from the last activity and move back towards the first activity.
Late Start and Late Finish Dates for the path Start -> A -> B -> C -> End
+
 
 +
'''Late Start and Late Finish Dates for the path Start -> A -> B -> C -> End'''
 +
 
 +
[[File:A5.png]]
  
 
On a critical path, Early Start, and Early Finish dates will be the same as Late Start and Late Finish dates.
 
On a critical path, Early Start, and Early Finish dates will be the same as Late Start and Late Finish dates.
Late Start and Late Finish Dates for the path Start -> D -> E -> F -> End
 
  
 +
'''Late Start and Late Finish Dates for the path Start -> D -> E -> F -> End'''
 +
 +
[[File:A6.png]]
  
 
Late Finish of activity F = 31 (because you cannot allow any activity to cross the project completion date)
 
Late Finish of activity F = 31 (because you cannot allow any activity to cross the project completion date)
 +
 
Late Start of activity F = LF of activity F – activity duration + 1
 
Late Start of activity F = LF of activity F – activity duration + 1
 
= 31 – 6 +1 = 26
 
= 31 – 6 +1 = 26
Line 224: Line 248:
 
= LS of activity F – 1
 
= LS of activity F – 1
 
= 26 – 1 = 25
 
= 26 – 1 = 25
 +
 
Late Start of Activity E = LF of activity E – activity duration + 1
 
Late Start of Activity E = LF of activity E – activity duration + 1
 
= 25 – 7 + 1 = 19
 
= 25 – 7 + 1 = 19
  
 
Late Finish of activity D = LS of successor activity – 1
 
Late Finish of activity D = LS of successor activity – 1
 +
 
If you look at the network diagram, you will notice that activity D has two successor activities, B and E. So, which activity will you select?
 
If you look at the network diagram, you will notice that activity D has two successor activities, B and E. So, which activity will you select?
 +
 
You will select the activity with the earlier(least) Late Start date. Here, Late Start of activity B is 11, and Late Start of activity E is 19.
 
You will select the activity with the earlier(least) Late Start date. Here, Late Start of activity B is 11, and Late Start of activity E is 19.
  
 
Therefore, you will select activity B which has the earlier Late Start date.
 
Therefore, you will select activity B which has the earlier Late Start date.
 +
 
Hence,
 
Hence,
 
Late Finish of activity D = LS of activity B – 1
 
Late Finish of activity D = LS of activity B – 1
 
= 11 – 1 = 10
 
= 11 – 1 = 10
 +
 
Late Start of Activity D = LF of activity D – activity duration + 1
 
Late Start of Activity D = LF of activity D – activity duration + 1
 
= 10 – 5 + 1 = 6
 
= 10 – 5 + 1 = 6
Late Start and Late Finish Dates for the path Start -> G -> H -> I -> End
+
 
 +
'''Late Start and Late Finish Dates for the path Start -> G -> H -> I -> End'''
 +
 
 +
[[File:A7.png]]
  
  
 
Late Finish of activity I = 31 (because you cannot allow any activity to cross the project completion date)
 
Late Finish of activity I = 31 (because you cannot allow any activity to cross the project completion date)
 
Late Start of activity I = 31 – 6 + 1 = 26
 
Late Start of activity I = 31 – 6 + 1 = 26
 +
 
Late Finish of activity H = 26 – 1 = 25
 
Late Finish of activity H = 26 – 1 = 25
 
Late Start of activity H = 25 – 4 + 1 = 22
 
Late Start of activity H = 25 – 4 + 1 = 22
 +
 
Late Finish of Activity G = 19 – 1= 18 (we will choose the late start of activity E, not activity H, because the Late Start of activity E is earlier than the Late Start of activity H)
 
Late Finish of Activity G = 19 – 1= 18 (we will choose the late start of activity E, not activity H, because the Late Start of activity E is earlier than the Late Start of activity H)
 
Late Start of activity G = 18 – 3 + 1
 
Late Start of activity G = 18 – 3 + 1
 
= 16
 
= 16

Revision as of 14:58, 22 September 2017

Critical Path Method or CPM, is a tool used in the planning and management of different types of projects such as construction, software development, research programs, product development, sales promotion and etc. It is essentially a mathematically based algorithm of network diagrams that depicts the sequence and interrelation of all the component parts of a project and is well suited for the construction industry. In comparison to the conventional methods of planning and scheduling of construction works - bar charts and progress diagrams - Critical Path Method proves to be more useful and precise as it allows the quick evaluation and comparison of alternative work programs, construction methods, types of equipment and etc.

The time-cost problem in the construction sector is forever debatable and has an infinite number of solutions. Today, the Critical Path Methods provides a systematic procedure of correlating cost and time of each activity involved in the construction project, to provide an optimum solution. It is a crucial tool used in construction management as it provides varying degree of involvement by the management to suit the needs and objectives of the project.

Contents

Historical Background

The critical path technique had its origin from 1956 to 1958 in two parallel but different problems of planning and control in projects in the United States.

In the first case, the US Navy was concerned with the control of contracts for its Polaris Missile program. As the contracts comprised of research, development and manufacture work of newly developed parts, the probability of completion dates for each contract was determined. This procedure was referred to as Program Evaluation and Review Technique, abbreviated to PERT. PERT did not originally include cost estimates, but subsequent inclusion of cost data in the system is called PERTCO, that is PERT with costs. It is therefore important to understand that PERT systems involve a probability approach and are better suited for projects where big uncertainties exist.

In the second case, the EI du Pont de Nemours Company was constructing huge chemical plants in America. These projects required that both time and cost be estimated accurately. This method of planning and control that was developed was initially called Project Planning and Scheduling (PPS), which covered the design, construction and maintenance of large and complex projects using realistic estimates of time and cost. This method has since been developed into Critical Path Method (CPM).

Critical Path Method Terminology

Planning

Planning is the process of choosing the one method and order of work to be adopted for a project from all the various ways and sequences in which the optimum result can be achieved. This is schematically shown on the CPM network diagram.

Scheduling

Scheduling is the determination of the timing of the operations comprising the project and their assembly for the overall completion time. This can only be done after the project plan has been defined and modelled as a network diagram.

Network Diagram, Activity and Event

A network is a flow diagram constituting of activities and events that are connected logically and sequentially.

Well defined jobs or tasks are called activities. These are represented by arrows in a network diagram.

The beginning or end of each activity constitutes an event of the project.In a network diagram, events are represented by nodes. These can be circular, square, rectangular or oval in shape.

Dummy

A dummy is a type of operation in the network which neither requires any time nor any resources, but is merely a device to identify a dependence among operations. A dummy is represented by a dashed arrow.

Characteristics of Critical Path Method Projects

The following are the primary characteristics of any network diagram used in a CPM project:

1. The project to be planned should consist of clearly recognisable activities.

2. These activities must have definite commencement and completion dates.

3. The events must occur in a definite pattern and must have a technological sequence.

Steps in Critical Path Method

The process of using critical path method in project planning phase has six steps.

Step 1: Activity specification

You can use the Work Breakdown Structure (WBS) to identify the activities involved in the project. This is the main input for the critical path method.

In activity specification, only the higher-level activities are selected for critical path method.

When detailed activities are used, the critical path method may become too complex to manage and maintain.

Step 2: Activity sequence establishment

In this step, the correct activity sequence is established. For that, you need to ask three questions for each task of your list.

1. Which tasks should take place before this task happens.

2. Which tasks should be completed at the same time as this task.

3. Which tasks should happen immediately after this task.

Step 3: Network diagram

Once the activity sequence is correctly identified, the network diagram can be drawn (refer to the sample diagram above).

Although the early diagrams were drawn on paper, there are a number of computer softwares, such as Primavera, for this purpose nowadays.

Step 4: Estimates for each activity

This could be a direct input from the WBS based estimation sheet. Most of the companies use 3-point estimation method or COCOMO based (function points based) estimation methods for tasks estimation.

You can use such estimation information for this step of the process.

Step 5: Identification of the critical path

For this, you need to determine four parameters of each activity of the network.

Earliest start time (ES) - The earliest time an activity can start once the previous dependent activities are over.

Earliest finish time (EF) - ES + activity duration.

Latest finish time (LF) - The latest time an activity can finish without delaying the project.

Latest start time (LS) - LF - activity duration.

The float time for an activity is the time between the earliest (ES) and the latest (LS) start time or between the earliest (EF) and latest (LF) finish times.

During the float time, an activity can be delayed without delaying the project finish date.

The critical path is the longest path of the network diagram. The activities in the critical path have an effect on the deadline of the project. If an activity of this path is delayed, the project will be delayed.

In case if the project management needs to accelerate the project, the times for critical path activities should be reduced.

Step 6: Critical path diagram to show project progresses

Critical path diagram is a live artefact. Therefore, this diagram should be updated with actual values once the task is completed.

This gives more realistic figure for the deadline and the project management can know whether they are on track regarding the deliverable.

Advantages of Critical Path Method

1. It shows the graphical view of the project.

2. It discovers and makes dependencies visible.

3. It helps in project planning, scheduling, and controlling.

4.It helps in contingency planning.

5.It shows the critical path, and identifies critical activities requiring special attention.

6.It helps you assign the float to activities and flexibility to float activities.

7.It shows you where you need to take action to bring project back on track.

Example of Critical Path Method

Based on the below network diagram, identify the total paths, critical path, and float for each path.

A1.png

The above network diagram has five paths; the paths and their duration are as follows:

1. Start -> A -> B -> C-> End, duration: 31 days. 2. Start ->D -> E ->F -> End, duration: 18 days. 3. Start -> D -> B -> C -> End, duration: 26 days. 4. Start -> G ->H ->I -> End, duration: 13 days. 5. Start -> G -> E ->F -> End, duration: 16 days.

Since the duration of the first path is the longest, it is the critical path. The float on the critical path is zero.

The float for the second path “Start ->D -> E ->F -> End” = duration of the critical path – duration of the path “Start ->D -> E ->F -> End” = 31 – 18 = 13

Hence, the float for the second path is 13 days.

Using the same process, we can calculate the float for other paths as well.

Float for the third path = 31 – 26 = 5 days. Float for the fourth path = 31 – 13 = 18 days. Float for the fifth path = 31 – 16 = 15 days.

Calculate Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF)

We have identified the critical path, and the duration of the other paths, it’s time to move on to more advanced calculations, Early Start, Early Finish, Late Start and Late Finish.

Calculating Early Start (ES) and Early Finish (EF)

To calculate the Early Start and Early Finish dates, we use forward pass; we will start from the beginning and proceed to the end.

Early Start (ES) for the first activity on any path will be 1, because no activity can be started before the first day. The start point for any activity or step along the path is the end point of the predecessor activity on the path plus one.

The formula used for calculating Early Start and Early Finish dates.

Early Start of the activity = Early Finish of predecessor activity + 1 Early Finish of the activity = Activity duration + Early Start of activity – 1

Early Start and Early Finish Dates for the path Start -> A -> B -> C -> End

File:AA2.png

Early Start of activity A = 1 (Since this is the first activity of the path)

Early Finish of activity A = ES of activity A + activity duration – 1 = 1 + 10 – 1 = 10

Early Start of activity B = EF of predecessor activity + 1 = 10 +1 = 11

Early Finish of activity B = ES of activity B + activity duration – 1 = 11 + 12 – 1 = 22

Early Start of activity C = EF of predecessor activity + 1 = 22 +1 = 23

Early Finish of activity C = ES of activity C + activity duration – 1 = 23 + 9 – 1 = 31

Early Start and Early Finish Dates for the path Start -> D -> E -> F -> End

A3.png

Early Start of activity D = 1 (Since this is the first activity of the path)

Early Finish of activity D = 1 + 5 – 1 = 5

Early Start of activity E = EF of predecessor activity + 1

Since the Activity E has two predecessor activities, which one will you select? You will select the activity with the greater Early Finish date. Early Finish of activity D is 5, and Early Finish of activity G is 3 (we will calculate it later).

Therefore, we will select the Early Finish of activity D to find the Early Start of activity E.

Early Start of activity E = EF of predecessor activity + 1 = 5 + 1 = 6

Early Finish of activity E = 6 + 7 – 1 = 12

Early Start of activity F = 12 + 1 = 13

Early Finish of activity F = 13 + 6 -1 = 18

Early Start and Early Finish Dates for the path Start -> G -> H -> I -> End

A4.png

Early Start of activity G = 1 (Since this is the first activity of the path) Early Finish of activity G = 1 + 3 – 1 = 3

Early Start of activity H = 3 + 1 = 4 Early Finish of activity H = 4 + 4 – 1 = 7

Early Start of activity I = 7 +1 = 8 Early Finish of activity I = 8 + 6 – 1 = 13

Calculating Late Start (LS) and Late Finish (LF)

We have calculated Early Start and Early Finish dates of all activities. Now it is time to calculate the Late Start and Late Finish dates.

Late Finish of the last activity in any path will be the same as the Last Finish of the last activity on the critical path, because you cannot continue any activity once the project is completed.

The fula used for Late Start and Late Finish dates: Late Start of Activity = Late Finish of activity – activity duration + 1 Late Finish of Activity = Late Start of successor activity – 1

To calculate the Late Start and Late Finish, we use backward pass; i.e. we will start from the last activity and move back towards the first activity.

Late Start and Late Finish Dates for the path Start -> A -> B -> C -> End

A5.png

On a critical path, Early Start, and Early Finish dates will be the same as Late Start and Late Finish dates.

Late Start and Late Finish Dates for the path Start -> D -> E -> F -> End

A6.png

Late Finish of activity F = 31 (because you cannot allow any activity to cross the project completion date)

Late Start of activity F = LF of activity F – activity duration + 1 = 31 – 6 +1 = 26 Late Finish of activity E = LS of successor activity – 1 = LS of activity F – 1 = 26 – 1 = 25

Late Start of Activity E = LF of activity E – activity duration + 1 = 25 – 7 + 1 = 19

Late Finish of activity D = LS of successor activity – 1

If you look at the network diagram, you will notice that activity D has two successor activities, B and E. So, which activity will you select?

You will select the activity with the earlier(least) Late Start date. Here, Late Start of activity B is 11, and Late Start of activity E is 19.

Therefore, you will select activity B which has the earlier Late Start date.

Hence, Late Finish of activity D = LS of activity B – 1 = 11 – 1 = 10

Late Start of Activity D = LF of activity D – activity duration + 1 = 10 – 5 + 1 = 6

Late Start and Late Finish Dates for the path Start -> G -> H -> I -> End

A7.png


Late Finish of activity I = 31 (because you cannot allow any activity to cross the project completion date) Late Start of activity I = 31 – 6 + 1 = 26

Late Finish of activity H = 26 – 1 = 25 Late Start of activity H = 25 – 4 + 1 = 22

Late Finish of Activity G = 19 – 1= 18 (we will choose the late start of activity E, not activity H, because the Late Start of activity E is earlier than the Late Start of activity H) Late Start of activity G = 18 – 3 + 1 = 16

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox