Theory of Constrains Manufacturing Systems
Line 22: | Line 22: | ||
Nearly every manufacturing system initially has a bottleneck and consequently, the system can only be as fast as its weakest link. It is critical to be able to determine the procedure in the production line which is the limiting factor. Generally the station which has accumulated the largest amount of WIP can be considered the Bottleneck, however other engineering management techniques can be applied to determine the bottle neck. | Nearly every manufacturing system initially has a bottleneck and consequently, the system can only be as fast as its weakest link. It is critical to be able to determine the procedure in the production line which is the limiting factor. Generally the station which has accumulated the largest amount of WIP can be considered the Bottleneck, however other engineering management techniques can be applied to determine the bottle neck. | ||
− | Any work station which is not operating at 100% capacity is having a negative effect on the entire manufacturing system. This negative effect can have negative costly impacts, environmental impacts or even staff impacts if not identified and improved<ref>http://www.lean-manufacturing-japan.com/scm-terminology/bottleneck-constraint. | + | Any work station which is not operating at 100% capacity is having a negative effect on the entire manufacturing system. This negative effect can have negative costly impacts, environmental impacts or even staff impacts if not identified and improved<ref>Imaoka, Z., (2008). Bottleneck (Constraint). Retrieved from: http://www.lean-manufacturing-japan.com/scm-terminology/bottleneck-constraint.</ref>. Often too much time is investing into reducing running costs of a production line as this is identified as having a negative impact on production, however reducing costs consequently reduces [[cash flow]] through the system, not dealing with the bigger impact, the bottleneck. |
== Application == | == Application == | ||
Line 30: | Line 30: | ||
=== Five Focusing Steps === | === Five Focusing Steps === | ||
[[File:Five focusing steps.png|thumb|Five Focusing Steps Cycle]] | [[File:Five focusing steps.png|thumb|Five Focusing Steps Cycle]] | ||
− | The five focusing steps of TOC is an ideal approach to identifying the bottleneck and the correct procedure to reduce the impact keeping in mind the 'goal.' The five focusing steps are<ref>https://www.tocinstitute.org/five-focusing-steps.html | + | The five focusing steps of TOC is an ideal approach to identifying the bottleneck and the correct procedure to reduce the impact keeping in mind the 'goal.' The five focusing steps are<ref>Theory of Constrains Institute., (2017). Five Focusing Steps. Retrieved from: https://www.tocinstitute.org/five-focusing-steps.html.</ref>: |
#Identify the Constraint | #Identify the Constraint | ||
#Exploit the Constraint | #Exploit the Constraint | ||
Line 67: | Line 67: | ||
=== Thinking Process === | === Thinking Process === | ||
− | The [[thinking process]] in TOC, are tools used to determine, and fixing a problem in a system. In streamline processing it is a fundamental approach to always be striving to improve processes, eliminate bottlenecks and reduce manufacturing time. A common approach is to answer the following questions:<ref>http://www.dbrmfg.co.nz/Thinking%20Process.htm | + | The [[thinking process]] in TOC, are tools used to determine, and fixing a problem in a system. In streamline processing it is a fundamental approach to always be striving to improve processes, eliminate bottlenecks and reduce manufacturing time. A common approach is to answer the following questions:<ref>Dr. Youngman. K., (2010). A Guide to Implementing the Theory of Constraints. Retrieved from: http://www.dbrmfg.co.nz/Thinking%20Process.htm. </ref> |
*What should I change? | *What should I change? | ||
*What should It change to? | *What should It change to? |
Revision as of 17:41, 27 September 2017
Theory of constraints (TOC) is an engineering management technique used to evaluate a manageable procedure, identifying the largest constraint (bottleneck) and strategizing to reduce task time and maximise profit. It assists in determining what to change, when to change it, and how to cause the change[1]. The theory was established by Dr. Eliyahu Goldratt through his 1984 bestselling novel The Goal. Since this time, TOC has continued to develop and evolve and is a primary management tool in the engineering industry. When Applying TOC, powerful tools are used to determine the constraint and reduce its effect on the procedure, including:
- The Five Focusing Steps
- The Thinking Process
- Throughput Accounting
- Drum-Buffer-Rope
While it is a dominant engineering management and manufacturing tool, TOC can also widely used in throughput accounting, software engineering and other project, program, and portfolio engineering fields. Although the theory is limited by varying factors, time factors and human identification, TOC is the ideal engineering solution to increasing profit and reducing idle time in a manufacturing systems through its ability to elimination 'the weak link.'
Contents |
History
Theory of Constraints is a method to determine a procedure in a sequence of procedures which has the greatest negative effect on the production line. The theory was first derived by Dr Eliyahu Goldratt through his 1984 bestselling novel, 'The Goal.' Dr Goldratt was a well-regarded educator in the construction industry, being sought-after by many large companies. In the mid 1990's, Goldratt in 2000, established Goldratt's Marketing Group to further enhance the TOC knowledge to those interested. Goldratt's Marketing Group was established to further enhance the knowledge of businesses in product production, suppliers and distributors, project managers and retail workers, further develop the quality of decision-making, improving communication and stimulating new solutions.[2]
The theory operates with the assumption that every process has at least one influencing constraint, of which must be improved for the process to become more economic. Time spent trying to maximise processes which are not considered the bottleneck will not provide any benefits to the system. Attempting to reduce the influencing factor the bottleneck has on the entire system, will further the 'goal.' The procedure of reducing the influencing factor the bottleneck has on the system, continues as one bottleneck is minimised the attention turns to the new largest hindering procedure.
Bottleneck
In streamline manufacturing, the bottleneck is the station of a production line where greatest limiting process occurs. It is generally the station with the greatest amount of work in progress(WIP) at the work station[3]. Bottlenecks often results in slow production times, surplus of raw material and low employee morale.
Nearly every manufacturing system initially has a bottleneck and consequently, the system can only be as fast as its weakest link. It is critical to be able to determine the procedure in the production line which is the limiting factor. Generally the station which has accumulated the largest amount of WIP can be considered the Bottleneck, however other engineering management techniques can be applied to determine the bottle neck.
Any work station which is not operating at 100% capacity is having a negative effect on the entire manufacturing system. This negative effect can have negative costly impacts, environmental impacts or even staff impacts if not identified and improved[4]. Often too much time is investing into reducing running costs of a production line as this is identified as having a negative impact on production, however reducing costs consequently reduces cash flow through the system, not dealing with the bigger impact, the bottleneck.
Application
There are several practiced techniques applied to streamline manufacturing to reduce and or eliminate the constraining factor in the system. The methods applied to the systems all are designed to isolate the constraint, break it down into its components and find a suitable solution to reducing the negative impact the station has on the entire system. The thinking processes as well as the identification of the bottleneck is conducted in different manners. The four most common practiced techniques include; Five Focusing Steps, Thinking Process, Throughput Accounting and the Drum-Buffer-Effect.
Five Focusing Steps
The five focusing steps of TOC is an ideal approach to identifying the bottleneck and the correct procedure to reduce the impact keeping in mind the 'goal.' The five focusing steps are[5]:
- Identify the Constraint
- Exploit the Constraint
- Subordinate the Constraint
- Elevate the Constraint
- Repeat the Process
Identify the Constraint
The first step is to determine which process in the system is constraining the systems total throughput. This is the most important step as it will either further limit or increase the rate of manufacturing in the system. Indicators of the bottleneck in the system will have accumulated a large amount of WIP and will have a higher average cycle time. This process may also have the highest cost to manufacture in the system and that may be the bottleneck. However the bottleneck is determined, it is important to decipher which station is having the largest negative impact on cash flow in the system
Exploit the Constraint
Exploiting the constraint is the procedure of quickly improving the current bottleneck with minimal disruption to the production line. Common rapid relief techniques include:
- Inventory buffers
- Quality check
- Continuous operation
- Schedule around bottleneck
- Offload constraint work
Improvements in these fields will have a quick solution to improvement of the constraint which will result in improved throughput
Subordinate to the Constraint
This step focuses on techniques to mitigate impact from upstream or downstream processes which may further delay the operations of the bottleneck. Techniques include:
- Drum-Buffer-Rope
- Subordinate maintenance
- Added sprint capacity
- Operations pace
Elevate the Constraint
In this step, actions are taken to break the constraints by the implementation of larger changes to improve the bottleneck. These changes usually include a large investment of time and or money. Techniques used include:
- Use of performance data
- Single-Minute Exchange of Die (SMED) program
- Design improvements
- Purchase additional equipment/staff
Repeat the Process
Once the initial steps of the Five Focusing Steps have been executed, the bottleneck of focus should no longer be the hindering process of the system. The implementation of the Five Focusing Steps is not used for one off improvement but for continuous improvements to the process. If the bottleneck has been broken, the next step is to repeat the focusing steps for the new bottleneck. If the bottleneck has not been broken, a new approach needs to be taken, including verifying that the investigated constraint has correctly been identified as the bottleneck.
Thinking Process
The thinking process in TOC, are tools used to determine, and fixing a problem in a system. In streamline processing it is a fundamental approach to always be striving to improve processes, eliminate bottlenecks and reduce manufacturing time. A common approach is to answer the following questions:[6]
- What should I change?
- What should It change to?
- How to cause the change?
Asking these questions when faced with a problem in a production line, will offer a range of solutions simultaneously to improve the current situation. The thinking process allows a smooth transition through the layers of the process to be able to adapt a more suitable method to improve the manufacturing system.
Throughput Accounting
Throughput accounting (TA) is a simple management accounting technique providing managers with information support to make profitable decisions for their system. It is an alternative method to traditional cost accounting, in which limiting factors in a system are identified and simple solutions are adapted to move towards reaching the businesses goal. The actions of throughput accounting maximize the net profit from a system in the shortest amount of time, with limited resources and limited expenditures.
Throughput accounting uses through methods in dealing with income and expenses in a system[7]
Throughput (T) is the rate at which a system can produce a unit. For profit orientated systems, throughput is considered net sales (S) minus totally variable cost (TVC).
Investment (I) is the monetary value of the system. The value of inventory, buildings, machines and other assets are considered investments.
Operating expenses (OE) is the cost of the supply chain operating to produce the unit. For a system manufacturing a physical item, the operating expense is the investment cost minus the cost of raw materials but including the cost of maintenance, rent and taxes.
Drum-Buffer-Rope
The Drum-Buffer-Rope concept is applied to a manufacturing system to synchronize various work stations so they are no faster than the bottleneck (reference article). Like a band marches to the beat of the drum, so does the production line to the beat of the slowest station. Once the bottleneck is ready to move on, the adjacent stations, controlled by the speed of the bottleneck, may move onto the next unit. The rope theory was introduced with the intention to explain that once the rope stretches to its maximum, being the speed of the bottleneck to produce units, those stations attached cannot work any further.
This concept was first applied by Ford Motors Cor., Ltd[8]. Who used conveyor belts as transporters of material for their automobile construction. From the introduction of this concept, Mr. Taiichi Ohno of Toyota Motors corporation introduced the concept Kanban[9]. Kanban is Japanese for 'visual signal.' Kanban was introduced after Toyota engineers observed a supermarkets technique of product ordering. Products were not ordered to demand, but when stock was low. Toyota used this to model their manufacturing systems whereby a workstation once it has completed its task, would demand the next task be bough to the station. Common Kanban techniques include the demand for something being interpreted through visual representation, colors. Colors are generally used to identify when a station is busy or when they are ready for a delivery of WIP.
There are four steps to ensuring a Kanban approach to streamline manufacturing is executed effectively[10]:
- Visualize work
- Limit work in progress
- Focus on flow
- continuous improvement
Applying TOC to Manufacturing Systems
Constraints and Limitations
A key process in TOC is the identification of the limiting factor in a production system to ultimately improve the production of units. A major limitation in the theory is that of identifying the station which is in fact the limiting procedure][11] .
Identification
It is not uncommon that when applying TOC the wrong work station is being examined as the limiting station when, however this station may only be the bottleneck due to another constraining factor not being focused on. This limitation theory, may encourage the waste of resources and times on a station which may in fact not require optimizing.
Variation
Another limitation of the theory is the lack of consideration towards varying factors. Factors such as demand for a product are not directly examined when TOC is applied. If the market demand for a product is varying, the use of resources to improve the situation may be better used expanding production capacity.
Time
Time is an influential constraint when applying TOC. The theory does not consider the current time frame for the production system and the duration of the demand for the product. The theory limits itself to short-term effects on the system rather than forecasting for the future. Overcoming this constraint means examining the long-term effects of work done to improve the constraint. If findings in a short-term analysis seem to repeat they can be considered as long-term effects, therefore implementing changes may be appropriate.
References
- ↑ Vorne Industries Inc.,. (2016). What is the Theory of Constrains?. Retrieved from: http://www.leanproduction.com/theory-of-constraints.html.
- ↑ Goldratt's Marketing Group,. (2011). Biography of Dr. Eliyahu M. Goldratt. Retrieved from: https://www.toc-goldratt.com/tocweekly/biography-of-dr-eliyahu-m-goldratt.,
- ↑ Investopedia., (2017). Bottleneck. Retrieved from: http://www.investopedia.com/terms/b/bottleneck.asp.
- ↑ Imaoka, Z., (2008). Bottleneck (Constraint). Retrieved from: http://www.lean-manufacturing-japan.com/scm-terminology/bottleneck-constraint.
- ↑ Theory of Constrains Institute., (2017). Five Focusing Steps. Retrieved from: https://www.tocinstitute.org/five-focusing-steps.html.
- ↑ Dr. Youngman. K., (2010). A Guide to Implementing the Theory of Constraints. Retrieved from: http://www.dbrmfg.co.nz/Thinking%20Process.htm.
- ↑ http://www.goldratt.co.uk/articles/newsletter/back_to_basics_1.html/ Goldratt, Knowledge that Delivers],
- ↑ http://www.lean-manufacturing-japan.com/scm-terminology/dbr-drum-buffer-rope-theory.html/DBR Theory
- ↑ https://leankit.com/learn/kanban/what-is-kanban// What is Kanban?
- ↑ http://kanbantool.com/kanban-presentation/ Kanban Presentation
- ↑ http://yourbusiness.azcentral.com/limitations-theory-constraints-16352.html/ Limitations of the Theory of Constrains,