Project Execution Model (PEM)

From apppm
(Difference between revisions)
Jump to: navigation, search
 
(53 intermediate revisions by one user not shown)
Line 1: Line 1:
[[File:Image001.png|600px|thumb|right|Figure 1: The Project execution model five-stage gate process ]]
+
''Developed by Christian Klibo Buur''
The sale in Novo Nordisk was steady increasing, which resulted that Novo Nordisk was forces to continuously hire new employees to keep up the increasing demand. The consequence was, that the company experienced, that the diversity of the way project managers handled project was huge. Therefore did the management of the area Product Supply in Novo Nordisk in 2001 decide to initiated a project which purpose was to make a global standardized way to handling projects based on best practice. The idea was based on Novo Nordisk has working with projects in many years and obtained a lot of know how about how to handling projects to secure the best output, but also obtained a lot of know how, of what NOT to do. All the knowledge should be used to develop one global model. One year later in October 2002, the first version of Novo Nordisk Project Execution Model(PEM) was established (source). Afterward Novo Nordisk obtained more know how, and today the 5th version of the Project Execution Model is developed as the newest model, that project managers use. 
+
PEM is a stage-gate project model that consist of five phases, which guiding project managers to successful completion of each project phase. The five phases are: idea-, initiate-, analyse-, execute and realisephase. Figure 1 shows the 5 phases in the model. The main focus of PEM is investment projects, but can easily be adopted for non-investment projects as well.
+
The procedure establishes a framework to ensure that projects are identified, captured, scoped, planned, executed and closed in a standardized and efficient manner according to the model.
+
  
  
Each phase in the PEM model has a gate, where line management, portfolio manager, project owner, steering group and project sponsor evaluate and review the project by either approve or reject the project to continue to next phase. In the following, each phase will be described:
+
[[File:Image001.png|600px|thumb|right|Figure 1: The Project execution model five-stage gate process <ref name=CB1>''Internal Novo Nordisk SOP 049797 about Global procedure of project execution, 5. edition'' effective from 29 Juli 2013</ref> ]]
 +
In 90s the sale in [https://en.wikipedia.org/wiki/Novo_Nordisk ''Novo Nordisk''] was steady increasing, which resulted that the company was forces to continuously hire new employees to continuously meet the increasing demand. The consequence of the increasing of numbers of new employees was, that the company experienced a huge diversity in the way project managers handled project. Therefore in 2001 the executive management in Novo Nordisk decided to initiated a project with the purpose of making a global standardized way to handling projects. Novo Nordisk has working with projects in many years and obtained a lot of know how about good way of handling projects to secure the best output, but also obtained a lot of know how, about what NOT to do and therefore avoid all the pitfalls. The idea was, to use all that knowledge to develop one global model based on best practice. About one year later in October 2002, the first version of Novo Nordisk Project Execution Model(PEM) was established.<ref>''Internal Novo Nordisk SOP 055061 about Global procedure of project execution, 1. edition'' effective from 15 October 2002</ref> Afterward Novo Nordisk obtained more know how to continuously improve the model and today the project managers work after the 5th version of the Project Execution Model.<ref name=CB1>''Internal Novo Nordisk SOP 049797 about Global procedure of project execution, 5. edition'' effective from 29 Juli 2013</ref>
 +
Overall the PEM is a stage-gate project model that consist of five phases. Each phase guiding the project manager to successfully completion of each project phase. The five phases are: idea-, initiate-, analyse-, execute and realize phase. Figure 1 shows the five phases in the model. The main focus of PEM is investment projects, but can easily be adopted to non-investment projects as well.
 +
The procedure establishes a framework to ensure that projects are identified, captured, scoped, planned, executed and closed in a standardized and efficient manner according to the model.
  
=='''PEM - a five gate model'''==
+
Each phase in the PEM model has a gate, where line management, portfolio manager, project owner, steering group and project sponsor (all described in ''roles & responsibilities'') evaluate and review the project by either approve or reject it to continue to next phase. This article aims to describe, each phase. Beside the phases, the roles & responsibilities plus an reflection of Novo Nordisk's PEM and how it works in other industries will be presented:
  
==='''Phase 1'''===
+
== PEM - a five gate model ==
  
The first phase is characteristic of the idea phase. When the idea for a project is identified, the project manager need to find an owner project owner in which the idea is funded. The idea is described in collaboration with Line of Business(LoB) with the project objectives in a brief – this is to secure ownership from the beginning.  
+
=== Phase 1 ===
 +
 
 +
The first phase is characteristic of the idea phase. When the idea for a project is identified, the project manager need to find an project owner in which the idea is funded. The idea is described in collaboration with Line of Business(LoB) with the project objectives in a brief, to secure ownership from the beginning.  
 
In phase 1 the project manager should also create a one-pager which describes:
 
In phase 1 the project manager should also create a one-pager which describes:
  
 
* Background for starting the project and top level objectives
 
* Background for starting the project and top level objectives
 
* Scope of the project.
 
* Scope of the project.
* Level 0 time plan just a rough time plan that don’t need to be too detailed. Only top 10 milestones of the project which include gate approval dates
+
* Level 0 time plan: just a rough time plan that don’t need to be too detailed. Only top 10 milestones of the project which include gate approval dates
* A rough estimate of manning needs, quality strategy, risk list, environment health and safty screening (safty first is essential in Novo Nordisk project)
+
* A rough estimate of manning needs
 +
* Quality strategy
 +
* Risk list
 +
* Environment health and safety screening (safety first is essential in Novo Nordisk project)
 
* Cost estimate: The project manager should make a pre-estimate of the cost budget. There is only a expectation of about 20 % contingency of the estimate.
 
* Cost estimate: The project manager should make a pre-estimate of the cost budget. There is only a expectation of about 20 % contingency of the estimate.
  
As mentioned in the beginning the idea are either an investment or a non-investment project. It is required to make a preliminary stakeholder analysis together with top-level project requirements. The stakeholder analysis involves a 5 step-process, which are described bellow:
+
At least it is required to make a preliminary stakeholder analysis together with top-level project requirements. The communication to the stakeholders is more than just passing information. It is about making a message understandable, about listening to the reactions from the stakeholders the project manager communicate with and engage in a dialogue. The stakeholder analysis involves a 4 step-process, which are described bellow<ref name=CB2>''Internal Novo Nordisk SOP 056035 about Handling stakeholders, 3. edition'' effective from 12 April 2011</ref>:
  
'''1. Identify stakeholder:'''
+
[[File:Stakeholder grid.png|200px|thumb|right|Figure 2: Stakeholder grid <ref name=CB2>''Internal Novo Nordisk SOP 056035 about Handling stakeholders, 3. edition'' effective from 12 April 2011</ref>]]
  
The process of identifying all people or organizations who are impacted by the project and documenting relevant information regarding their interest involvement and impact on project success. Bellow there is a grid to get a overview of how important the difference stakeholders are to the project
 
  
[[File:Stakeholder grid.png]]
+
'''''1. Identify stakeholder:'''''
  
'''2. Plan communications with stakeholders:'''
+
The process of identifying all people or organizations who are impacted by the project and documenting relevant information regarding their interest involvement and impact on project success. Figure 2 shows the grid that should be used to get a overview of importance of the difference stakeholders to the project
  
The process of determining the project stakeholder information need and defining a communication approach. Here the project manager make a plan of who are the important stakeholders and related to, how often communication to the different stakeholders is made. There is a standard to use make the communication plan to the stakeholders:
 
  
[[File:Stakeholder communication.PNG]]
+
'''''2. Scope the communication task:'''''
 +
The Project Manager need to know the size of the communication task, and make it clear what the different stakeholders expect from the project manager. Before the Project Manager plan anything, the following questions need to be answered of each stakeholder to get a better idea of how to plan the communication:
  
''Lav en beskrivelse i de første felter og derefter en eksempel og til sidst bare [tekst]
+
* ''What to communicate?''
 +
* ''To whom? (more specific contact person)''
 +
* ''Why is it necessary and relevant to communicate?''
 +
* ''When to communicate?''
 +
* ''What to achieve?''
 +
* ''By which channel, which media?''
 +
* ''How to communicate?''  
  
'''3. Distribute information to stakeholders:'''
+
Knowing the needs is crucial to planning successful communication and to get there the Project Manager must ask the right question about the stakeholders.
  
The process of making relevant information available to project stakeholders as planned. A key part of this involves planning and manage both current and new project information arriving. Here the project it is also important to consider how to communicate to stakeholder – by email, or a fixed meeting time every week/month.
+
[[File:Communication_plan222.PNG|400px|thumb|right|Figure 3: Stakeholder communication plan<ref name=CB2>''Internal Novo Nordisk SOP 056035 about Handling stakeholders, 3. edition'' effective from 12 April 2011</ref>]]
  
'''4. Manage stakeholders expectations:'''
 
  
The process of communication and working with stakeholders to meet their need and addressing issues as they occur.
 
  
'''5. Report performance:'''
+
'''''3. Do the plan for communication with stakeholder'''''
  
The process of collecting and distributing performance information, including status report, progress measurement.
+
Step 3 is the process of making relevant information available to project stakeholders as planned. A key part of this involves planning and manage both current and new project information arriving. Here the project it is also important to plan how to communicate to stakeholder. When the questions from step 2 is answered, the project manager need to make a plan of Who, When and What to communicate. This is a on-going process, which can change through the project. A example of the final result of a communication plan is showed in figure 3.  
  
Overall this phase is just to give a estimated overview of the project, to get an idea of the project. Normally there are only a contingency of 20% in this phase. Prior to gate the gate 1 approval, the idea is subjected to minimum the Corporate Vice President portfolio review. If the idea is also approved during Line of Business and if prioritizations and deliverables that are required at gate 1 are fulfilled, it enters the project portfolio as an accepted project, and go to phase 2.
 
  
==='''Phase 2'''===
+
'''''4. Measure the impact:'''''
 +
 
 +
As the project manager roll out the planned communication, the project manager should start measuring the impact it has and to what extend the communication objectives have been achieved. Til will help the PM to optimize the communication and evaluate the impact of the communication later on.
 +
 
 +
 
 +
Overall this phase is just to give a estimated overview of the project, to get an idea of the project. Normally there are only a correctness of 20% in this phase. Prior to gate the gate 1 approval, the idea is subjected to minimum the Corporate Vice President portfolio review. If the idea is also approved during Line of Business and if prioritization and deliverable's that are required at gate 1 are fulfilled, it enters the project portfolio as an accepted project, and go to phase 2.
 +
 
 +
=== Phase 2 ===
  
 
Phase 2 is the Initiate phase. During the immediate start of phase 2, the project manager and project owner must establish a steering group. The role of the steering group during this phase is to help the project manager elaborate all business objectives and to evaluate and give direction on the project scope and scope alternatives.  
 
Phase 2 is the Initiate phase. During the immediate start of phase 2, the project manager and project owner must establish a steering group. The role of the steering group during this phase is to help the project manager elaborate all business objectives and to evaluate and give direction on the project scope and scope alternatives.  
  
The main deliverables in phase 2 for the project manager are:
+
The main deliverable's in phase 2 for the project manager are:
  
* Ressource allocation: When starting phase 2 work, key Novo Nordisk project manning must be available and prioritized by LoB resource managers. Here it is recommended to make a brief organizational diagram with manning requirement and any increased headcount.
+
* Resource allocation: When starting phase 2, key project manning must be available and prioritized by LoB resource managers. Here it is recommended to make a brief organizational diagram with manning requirement and any increased headcount.
* Level 1 schedule: a more detailed project plan with 30-50 lines with deliverables and activity duration including milestones for 3rd phase.  
+
* Level 1 schedule: a more detailed project plan with 30-50 lines with deliverable's and activity duration including milestones for 3rd phase.  
 
* Environment, health and safety (EHS) assessment
 
* Environment, health and safety (EHS) assessment
* Cost estimate: The project manager should make a more detailed estimate of the cost. It is expected that the cost estimate have a contingency of 80% - which means that changes in the budget is not expected.
+
* Cost estimate: The project manager should make a more detailed estimate of the cost. It is expected that the cost estimate have a correctness of 80% - which means that major changes in the budget is not expected.
* The main deliverable for phase 2 is a clear scope recommendation for the project based on main scope and alternative scope.
+
* Ensure stakeholder commitment, maybe the needs for communication have changed – it is needed to consider this in this phase.
 +
* Clear scope recommendation for the project based on main scope and alternative scope.
  
A last key deliverable is the risk management. Here the top 10 risk are identified in a grid. The risk management process consist of a 6 step process which help to ensure that the risks of the project are identified and a response and monitoring are performed.
+
A last key deliverable is the risk management. Here the top 10 risk are identified in a grid. The risk management process consist of a 6 step process which help to ensure that the risks of the project are identified and a response and monitoring are performed <ref name=CB3>''Internal Novo Nordisk SOP 076243 about Handling Risk, 8. edition'' effective from 23 January 2015</ref>. The template to the risk process is shown in figure 4.
  
[[File:Risk Grid.png]]
+
[[File:Risk Grid.png|400px|thumb|right|Figure 4: Risk grid <ref name=CB3>''Internal Novo Nordisk SOP 076243 about Handling Risk, 8. edition'' effective from 23 January 2015</ref>]]
  
'''1. Plan risk management:'''
+
'''''1. Plan risk management:'''''
  
 
This is act of actively deciding and documenting in the project how risks shall be addressed. The risk management plan may state to what extent the project is willing to accept risks and plan how the continuing risk management shall be performed.  
 
This is act of actively deciding and documenting in the project how risks shall be addressed. The risk management plan may state to what extent the project is willing to accept risks and plan how the continuing risk management shall be performed.  
  
'''2. Identify risk:'''
+
'''''2. Identify risk:'''''
  
First step in documenting risks in the project is to produce a list of identified risks for the project.
+
Next step in documenting risks in the project is to produce a list of identified risks for the project.
  
'''3. Perform qualitative risk analysis:'''
+
'''''3. Perform qualitative risk analysis:'''''
  
 
Categories each risk into a grid with business impact and likelihood.  
 
Categories each risk into a grid with business impact and likelihood.  
  
'''4. Perform quantitative risk analysis:'''
+
'''''4. Perform quantitative risk analysis:'''''
  
 
Calculate the resulting risk costs, cost of mitigating and presumed costs of all known risks.
 
Calculate the resulting risk costs, cost of mitigating and presumed costs of all known risks.
  
'''5. Plan risk response:'''
+
'''''5. Plan risk response:'''''
  
 
Decide on the appropriate response type for the top 10 risks and plan the actual work needed to bed one to mitigate transfer or avoid the risks.  
 
Decide on the appropriate response type for the top 10 risks and plan the actual work needed to bed one to mitigate transfer or avoid the risks.  
  
'''6. Monitor and control risks:'''
+
'''''6. Monitor and control risks:'''''
  
 
Typical monthly review on known risks and bi annual reviews to identify new risks. Reporting status of key risks to steering group.
 
Typical monthly review on known risks and bi annual reviews to identify new risks. Reporting status of key risks to steering group.
  
The steering group decide if the project manager have secure that all of above are in place. It that is the case and the project manager gets the approval the project can continue to phase 3.
 
  
==='''Phase 3'''===
+
The steering group decide if the project manager have secure that all of above are in place. If that is the case and the project manager gets the approval to continue to phase 3.
 +
 
 +
=== Phase 3 ===
  
 
Phase 3 of the project is known as the analyse phase. Before upstart of phase 3, it is essential that the key project manning for phases 3 and 4 is in place and approved by the project owner and project sponsor. If key manning is not in place, upstart of phase 3 should be postponed.  
 
Phase 3 of the project is known as the analyse phase. Before upstart of phase 3, it is essential that the key project manning for phases 3 and 4 is in place and approved by the project owner and project sponsor. If key manning is not in place, upstart of phase 3 should be postponed.  
In this phase of the project are the main planning of the project done by the project manager and key project team are in place based on the scope from phase 2. The main purpose of this phase is to analyse and describe a detailed solution. Furthermore includes the content of phase 3:
+
In phase 3 of the project the main planning of the project are done by the project manager. Also the key project team are in place based on the scope from phase 2. The main purpose of this phase is to analyse and describe a detailed solution. Furthermore the main deliverbles for phase 3 includes:
  
* A Work breakdown structure (WBS) (make a link to wikiarticle)
+
* [https://en.wikipedia.org/wiki/Work_breakdown_structure ''A Work breakdown structure (WBS)'']
 
* If necessary small adjustments to the project plan
 
* If necessary small adjustments to the project plan
* Ensure stakeholder commitment, maybe the needs for communication have changed – it is needed to consider this in this phase.
+
* Continuously ensure stakeholder commitment, and consider changes in communication if needed.
 
* Risk analysis is further developed along with mitigating actions.
 
* Risk analysis is further developed along with mitigating actions.
 
* Make a first draft of the training needs in LoB
 
* Make a first draft of the training needs in LoB
 
* Final cost budget
 
* Final cost budget
  
At gate 3, the agreement and supporting document are subject to review and approval by steering group. Prior the final approval, the project manager must also seek local IT approval for the automations and IT solutions.  
+
At gate 3, the agreement and supporting document are subject to review and approval by steering group. Prior the final approval, the project manager must also seek local IT approval for the automation and IT solutions.  
  
==='''Phase 4'''===
+
=== Phase 4 ===
  
 
Phase 4 is the executing phase. In this phase, most of the project work is carried out, constructed or purchased. The project manager manages the project and project team within the limits defined in the agreement. The purpose of this phase is to develop, implement and roll-out the solution and secure a smooth transition from project phase to daily operation. The project manager is responsible for the following tasks:
 
Phase 4 is the executing phase. In this phase, most of the project work is carried out, constructed or purchased. The project manager manages the project and project team within the limits defined in the agreement. The purpose of this phase is to develop, implement and roll-out the solution and secure a smooth transition from project phase to daily operation. The project manager is responsible for the following tasks:
Line 113: Line 129:
 
* Distribute information
 
* Distribute information
 
* Manage stakeholder’s expectations
 
* Manage stakeholder’s expectations
* Conduct procurement – Need to close all purchase orders and contracts, and report supplier performance.
+
* Conduct procurement: need to close all purchase orders and contracts, and report supplier performance.
 
* Ensure good EHS practice
 
* Ensure good EHS practice
  
In the implantation of the new business processes in the LoB, the organizational set up and competencies are updated, if needed. Also necessary training and organizational change management activtites are performed. The project manager also work on a package report with project learnings to steering group.  
+
In the implantation of the new business processes, the organizational set up and competencies are updated, if needed. Also necessary training and organizational change management activities are performed. At last the project manager also work on a report package with project learning's to the steering group.  
  
In order to pass gate 4, a project completion review are prepared by the project manager. The main purpose of the review is to gain final acceptance of the project deliverables and to collect learning point from the project planning and execution phase.  
+
In order to pass gate 4, a project completion review are prepared by the project manager. The main purpose of the review is to gain final acceptance of the project deliverable's and to collect learning point from the project planning and execution phase.  
  
When all above is approved by the steering group, the project manager formally hands over the project deliverables to the project owner who then has the responsibility of realizing the benefits of the project.  
+
When all above is approved by the steering group, the project manager formally hands over the project deliverable's to the project owner who then has the responsibility of realizing the benefits of the project.  
  
==='''Phase 5'''===
+
=== Phase 5 ===
  
During phase 5, the project owner realizes the project benefits. The project owner typically maximize realization of benefits by tracking KPIs. This is to ensure the solution is anchored in the organization. During this period, LoB is responsible for following up on supplier guarantees on equipment or buildings in due time before any guarantees expire, e.g. one year review on equipment or five year review on building parts.  
+
During phase 5, the project owner realizes the project benefits. The project owner typically maximize realization of benefits by tracking [https://en.wikipedia.org/wiki/Performance_indicator ''KPIs'']. This is to ensure the solution is anchored in the organization. During this period, LoB is responsible for following up on supplier guarantees on equipment or buildings in due time before any guarantees expire, e.g. one year review on equipment or five year review on building parts.  
  
 
After 6-24 month when benefits of the project have been shown a benefit review is prepared by the project owner for the project sponsor approval. The benefit review is mandatory for all projects.
 
After 6-24 month when benefits of the project have been shown a benefit review is prepared by the project owner for the project sponsor approval. The benefit review is mandatory for all projects.
Line 133: Line 149:
  
 
{| class="wikitable sortable"
 
{| class="wikitable sortable"
|+Overview of roles and responsibilities of people who are involved (Source)
+
|+Overview of roles and responsibilities of people who are involved<ref>'' Novo Nordisk SOP 080119 about project roles and responsibilities,  2. edition'' effective from 14 November 2014</ref>
 
|-
 
|-
 
!Role
 
!Role
Line 141: Line 157:
 
On small projects the project sponsor is the same person as the project owner         
 
On small projects the project sponsor is the same person as the project owner         
 
|  
 
|  
* Own the project deliverables and benefits
+
* Own the project deliverable's and benefits
 
* Ensure that the project follow the PEM methodology
 
* Ensure that the project follow the PEM methodology
 
* Appoint the project manager
 
* Appoint the project manager
Line 149: Line 165:
 
* Make and present the gate 5 benefits to the project sponsor
 
* Make and present the gate 5 benefits to the project sponsor
 
|-
 
|-
| Project manager
+
| [https://en.wikipedia.org/wiki/Project_manager ''Project manager'']
 
|  
 
|  
 
* Plan and direct project execution in all phases - which means that the project manager have the operational responsibility for leading the project
 
* Plan and direct project execution in all phases - which means that the project manager have the operational responsibility for leading the project
Line 159: Line 175:
 
* Report and communicate project performance to the steering group and relevant stakeholders
 
* Report and communicate project performance to the steering group and relevant stakeholders
 
* Archive all key project data, e.g. minutes from steering group meetings and relevant project data
 
* Archive all key project data, e.g. minutes from steering group meetings and relevant project data
* Organizing the prioritization deliverables, evaluating team member contributions and making adjustments when needed
+
* Organizing the prioritization deliverable's, evaluating team member contributions and making adjustments when needed
 
* Ensure compliance with the PEM system. including approval of mandatory outputs
 
* Ensure compliance with the PEM system. including approval of mandatory outputs
 
* Close and evaluate the project at gate 4
 
* Close and evaluate the project at gate 4
 
|-
 
|-
| Steering group (StG)
+
| [https://en.wikipedia.org/wiki/Committee#Steering_committees ''Steering group (StG)'']
 +
A steering committee makes strategic decisions concerning future realization of a specific project
 
|
 
|
 
* Scope the project objectives during phase 2 and 3
 
* Scope the project objectives during phase 2 and 3
 
* Help resolve project project risks outside authorization limits of the project manager and the agreement
 
* Help resolve project project risks outside authorization limits of the project manager and the agreement
 
* Make decisions on key issues, including prioritization to meet deadlines and/ or budgets
 
* Make decisions on key issues, including prioritization to meet deadlines and/ or budgets
* Approve the project gate 1, 2, 3, 4 documents
+
* Approve the project gate 2, 3, 4 documents
 
* Review project status on scope schedule, cost, risk and quality
 
* Review project status on scope schedule, cost, risk and quality
 
* Approve or reject scope changes that have impact benefits or described scope or affecting the schedule, cost or quality
 
* Approve or reject scope changes that have impact benefits or described scope or affecting the schedule, cost or quality
Line 180: Line 197:
 
* Head the steering group or delegate this task to the project owner
 
* Head the steering group or delegate this task to the project owner
 
|-
 
|-
|Project team
+
| [https://en.wikipedia.org/wiki/Project_team ''Project team'']
 
|
 
|
 
* Plan the project in details within their area of expertise
 
* Plan the project in details within their area of expertise
* Identify and describe all deliverables
+
* Identify and describe all deliverable's
 
* Participate in risk evaluation
 
* Participate in risk evaluation
 
* Identify constraints and assumptions
 
* Identify constraints and assumptions
Line 191: Line 208:
 
|-
 
|-
 
|Line of Business (LoB)
 
|Line of Business (LoB)
 +
An internal cooperate business unit
 
|  
 
|  
 
* Negotiate with the project manager on how to meet manning needs
 
* Negotiate with the project manager on how to meet manning needs
Line 200: Line 218:
 
|}
 
|}
  
Maybe describe what the different are - maybe it can be confusing what a steering group are?
+
== Reflections of PEM in Novo Nordisk and implementation in other industries ==
 
+
Novo Nordisk Project Execution Model is a complex model, with many stages and processes, that the project manager need to take under consideration. PEM follow the full project lifecycle from definition and justification of the project, through to delivering demonstrable benefits for the business. One of the things that can challenge other industries to use PEM, is the huge requirement of resources. This is to secure successful completion of the project goal and objectives, but can in some cases be a process where the purpose of for example a steering group meeting is to please the StG instead of secure progress of the project (not say that a StG is not useful, which is definitely not the case).
=='''Discussion of Novo Nordisk's Project Execution Model compared to other project models'''==
+
Why the model is useful in Novo Nordisk, is because of the most importance of [https://en.wikipedia.org/wiki/Regulatory_compliance ''quality compliance''] in the company - Novo Nordisk never compromise on quality, which often affect the cost and delivery. And therefore Novo Nordisk experienced, that the need of having more people involved to secure that quality is always fulfilled is important. Poor quality can in worst case be a matter of life and death. The importance of of quality control measures is essential. But to maintain the competitive advantages there is a need of some project progress. These two competing priorities - quality and time to execution - must be well managed through careful process in order to reduce risks inherent on this industry, which can result in more focus and inspection from [https://en.wikipedia.org/wiki/Food_and_Drug_Administration ''FDA''] than necessary. This extremely focus on quality is not necessary in other industries, which mean that some of the requirement in PEM would not be necessary. Therefore PEM is not a fit-to-all project model, but differently a model, that can be adjusted in relation to the industry. However are there still a lot of benefits that can be realized by this model. PEM helps to coordinating the various processes from the different phases, to secure that the project manager are meeting timelines and dealing with complex quality issues. PEM help project managers to assign the appropriate amount of time and resource to each phase of the project, to ensure the project can progress forward in a logical and controlled way. Also the PEM helps to manage the risks while also focusing on the quality. This should hopefully secure no rework <ref> ''[http://projectmgmt.brandeis.edu/downloads/BRU_MSMPP_WP_Feb2012_Pharma.pdf] By Brandeis University By Leanne Bateman'' effective from February 2012</ref>
 
+
 
+
=='''Conclusion'''==
+
  
Pros and cons
+
== Additional reading ==
  
Skriv nogle linjer om refferancerne.
+
- [https://en.wikipedia.org/wiki/Standard_operating_procedure ''Standard operating procedure''] - To get a better understanding of what a SOP is to know what kind references that are used.
  
Skriv noget om hvor i project management life cycle dette befinder sig
+
== References ==
 +
<references/>

Latest revision as of 16:48, 18 December 2018

Developed by Christian Klibo Buur


Figure 1: The Project execution model five-stage gate process [1]

In 90s the sale in Novo Nordisk was steady increasing, which resulted that the company was forces to continuously hire new employees to continuously meet the increasing demand. The consequence of the increasing of numbers of new employees was, that the company experienced a huge diversity in the way project managers handled project. Therefore in 2001 the executive management in Novo Nordisk decided to initiated a project with the purpose of making a global standardized way to handling projects. Novo Nordisk has working with projects in many years and obtained a lot of know how about good way of handling projects to secure the best output, but also obtained a lot of know how, about what NOT to do and therefore avoid all the pitfalls. The idea was, to use all that knowledge to develop one global model based on best practice. About one year later in October 2002, the first version of Novo Nordisk Project Execution Model(PEM) was established.[2] Afterward Novo Nordisk obtained more know how to continuously improve the model and today the project managers work after the 5th version of the Project Execution Model.[1] Overall the PEM is a stage-gate project model that consist of five phases. Each phase guiding the project manager to successfully completion of each project phase. The five phases are: idea-, initiate-, analyse-, execute and realize phase. Figure 1 shows the five phases in the model. The main focus of PEM is investment projects, but can easily be adopted to non-investment projects as well. The procedure establishes a framework to ensure that projects are identified, captured, scoped, planned, executed and closed in a standardized and efficient manner according to the model.

Each phase in the PEM model has a gate, where line management, portfolio manager, project owner, steering group and project sponsor (all described in roles & responsibilities) evaluate and review the project by either approve or reject it to continue to next phase. This article aims to describe, each phase. Beside the phases, the roles & responsibilities plus an reflection of Novo Nordisk's PEM and how it works in other industries will be presented:

Contents

[edit] PEM - a five gate model

[edit] Phase 1

The first phase is characteristic of the idea phase. When the idea for a project is identified, the project manager need to find an project owner in which the idea is funded. The idea is described in collaboration with Line of Business(LoB) with the project objectives in a brief, to secure ownership from the beginning. In phase 1 the project manager should also create a one-pager which describes:

  • Background for starting the project and top level objectives
  • Scope of the project.
  • Level 0 time plan: just a rough time plan that don’t need to be too detailed. Only top 10 milestones of the project which include gate approval dates
  • A rough estimate of manning needs
  • Quality strategy
  • Risk list
  • Environment health and safety screening (safety first is essential in Novo Nordisk project)
  • Cost estimate: The project manager should make a pre-estimate of the cost budget. There is only a expectation of about 20 % contingency of the estimate.

At least it is required to make a preliminary stakeholder analysis together with top-level project requirements. The communication to the stakeholders is more than just passing information. It is about making a message understandable, about listening to the reactions from the stakeholders the project manager communicate with and engage in a dialogue. The stakeholder analysis involves a 4 step-process, which are described bellow[3]:

Figure 2: Stakeholder grid [3]


1. Identify stakeholder:

The process of identifying all people or organizations who are impacted by the project and documenting relevant information regarding their interest involvement and impact on project success. Figure 2 shows the grid that should be used to get a overview of importance of the difference stakeholders to the project


2. Scope the communication task: The Project Manager need to know the size of the communication task, and make it clear what the different stakeholders expect from the project manager. Before the Project Manager plan anything, the following questions need to be answered of each stakeholder to get a better idea of how to plan the communication:

  • What to communicate?
  • To whom? (more specific contact person)
  • Why is it necessary and relevant to communicate?
  • When to communicate?
  • What to achieve?
  • By which channel, which media?
  • How to communicate?

Knowing the needs is crucial to planning successful communication and to get there the Project Manager must ask the right question about the stakeholders.

Figure 3: Stakeholder communication plan[3]


3. Do the plan for communication with stakeholder

Step 3 is the process of making relevant information available to project stakeholders as planned. A key part of this involves planning and manage both current and new project information arriving. Here the project it is also important to plan how to communicate to stakeholder. When the questions from step 2 is answered, the project manager need to make a plan of Who, When and What to communicate. This is a on-going process, which can change through the project. A example of the final result of a communication plan is showed in figure 3.


4. Measure the impact:

As the project manager roll out the planned communication, the project manager should start measuring the impact it has and to what extend the communication objectives have been achieved. Til will help the PM to optimize the communication and evaluate the impact of the communication later on.


Overall this phase is just to give a estimated overview of the project, to get an idea of the project. Normally there are only a correctness of 20% in this phase. Prior to gate the gate 1 approval, the idea is subjected to minimum the Corporate Vice President portfolio review. If the idea is also approved during Line of Business and if prioritization and deliverable's that are required at gate 1 are fulfilled, it enters the project portfolio as an accepted project, and go to phase 2.

[edit] Phase 2

Phase 2 is the Initiate phase. During the immediate start of phase 2, the project manager and project owner must establish a steering group. The role of the steering group during this phase is to help the project manager elaborate all business objectives and to evaluate and give direction on the project scope and scope alternatives.

The main deliverable's in phase 2 for the project manager are:

  • Resource allocation: When starting phase 2, key project manning must be available and prioritized by LoB resource managers. Here it is recommended to make a brief organizational diagram with manning requirement and any increased headcount.
  • Level 1 schedule: a more detailed project plan with 30-50 lines with deliverable's and activity duration including milestones for 3rd phase.
  • Environment, health and safety (EHS) assessment
  • Cost estimate: The project manager should make a more detailed estimate of the cost. It is expected that the cost estimate have a correctness of 80% - which means that major changes in the budget is not expected.
  • Ensure stakeholder commitment, maybe the needs for communication have changed – it is needed to consider this in this phase.
  • Clear scope recommendation for the project based on main scope and alternative scope.

A last key deliverable is the risk management. Here the top 10 risk are identified in a grid. The risk management process consist of a 6 step process which help to ensure that the risks of the project are identified and a response and monitoring are performed [4]. The template to the risk process is shown in figure 4.

Figure 4: Risk grid [4]

1. Plan risk management:

This is act of actively deciding and documenting in the project how risks shall be addressed. The risk management plan may state to what extent the project is willing to accept risks and plan how the continuing risk management shall be performed.

2. Identify risk:

Next step in documenting risks in the project is to produce a list of identified risks for the project.

3. Perform qualitative risk analysis:

Categories each risk into a grid with business impact and likelihood.

4. Perform quantitative risk analysis:

Calculate the resulting risk costs, cost of mitigating and presumed costs of all known risks.

5. Plan risk response:

Decide on the appropriate response type for the top 10 risks and plan the actual work needed to bed one to mitigate transfer or avoid the risks.

6. Monitor and control risks:

Typical monthly review on known risks and bi annual reviews to identify new risks. Reporting status of key risks to steering group.


The steering group decide if the project manager have secure that all of above are in place. If that is the case and the project manager gets the approval to continue to phase 3.

[edit] Phase 3

Phase 3 of the project is known as the analyse phase. Before upstart of phase 3, it is essential that the key project manning for phases 3 and 4 is in place and approved by the project owner and project sponsor. If key manning is not in place, upstart of phase 3 should be postponed. In phase 3 of the project the main planning of the project are done by the project manager. Also the key project team are in place based on the scope from phase 2. The main purpose of this phase is to analyse and describe a detailed solution. Furthermore the main deliverbles for phase 3 includes:

  • A Work breakdown structure (WBS)
  • If necessary small adjustments to the project plan
  • Continuously ensure stakeholder commitment, and consider changes in communication if needed.
  • Risk analysis is further developed along with mitigating actions.
  • Make a first draft of the training needs in LoB
  • Final cost budget

At gate 3, the agreement and supporting document are subject to review and approval by steering group. Prior the final approval, the project manager must also seek local IT approval for the automation and IT solutions.

[edit] Phase 4

Phase 4 is the executing phase. In this phase, most of the project work is carried out, constructed or purchased. The project manager manages the project and project team within the limits defined in the agreement. The purpose of this phase is to develop, implement and roll-out the solution and secure a smooth transition from project phase to daily operation. The project manager is responsible for the following tasks:

  • Direct and manage project
  • Distribute information
  • Manage stakeholder’s expectations
  • Conduct procurement: need to close all purchase orders and contracts, and report supplier performance.
  • Ensure good EHS practice

In the implantation of the new business processes, the organizational set up and competencies are updated, if needed. Also necessary training and organizational change management activities are performed. At last the project manager also work on a report package with project learning's to the steering group.

In order to pass gate 4, a project completion review are prepared by the project manager. The main purpose of the review is to gain final acceptance of the project deliverable's and to collect learning point from the project planning and execution phase.

When all above is approved by the steering group, the project manager formally hands over the project deliverable's to the project owner who then has the responsibility of realizing the benefits of the project.

[edit] Phase 5

During phase 5, the project owner realizes the project benefits. The project owner typically maximize realization of benefits by tracking KPIs. This is to ensure the solution is anchored in the organization. During this period, LoB is responsible for following up on supplier guarantees on equipment or buildings in due time before any guarantees expire, e.g. one year review on equipment or five year review on building parts.

After 6-24 month when benefits of the project have been shown a benefit review is prepared by the project owner for the project sponsor approval. The benefit review is mandatory for all projects.

[edit] Roles and responsibilities

In the following the roles and their responsibilities of the persons that are involved in the project, will be described.

Overview of roles and responsibilities of people who are involved[5]
Role Responsibilities
Project owner

On small projects the project sponsor is the same person as the project owner

  • Own the project deliverable's and benefits
  • Ensure that the project follow the PEM methodology
  • Appoint the project manager
  • Define business needs in the Idea phase
  • Provide LoB internal manning resources to the project manager and cost funding for the project, include manning agreement with all relevant departments
  • Establish and run the steering group with the project manager
  • Make and present the gate 5 benefits to the project sponsor
Project manager
  • Plan and direct project execution in all phases - which means that the project manager have the operational responsibility for leading the project
  • Prepare project brief and project charter including e.g. project risk evaluation
  • Negotiate project resources with project owner and manage these resources during project execution
  • Establish the project organisation
  • Involve all relevant internal and external stakeholders, and continuously be aware of stakeholder expectations during the project
  • Perform integrated scope control on the report
  • Report and communicate project performance to the steering group and relevant stakeholders
  • Archive all key project data, e.g. minutes from steering group meetings and relevant project data
  • Organizing the prioritization deliverable's, evaluating team member contributions and making adjustments when needed
  • Ensure compliance with the PEM system. including approval of mandatory outputs
  • Close and evaluate the project at gate 4
Steering group (StG)

A steering committee makes strategic decisions concerning future realization of a specific project

  • Scope the project objectives during phase 2 and 3
  • Help resolve project project risks outside authorization limits of the project manager and the agreement
  • Make decisions on key issues, including prioritization to meet deadlines and/ or budgets
  • Approve the project gate 2, 3, 4 documents
  • Review project status on scope schedule, cost, risk and quality
  • Approve or reject scope changes that have impact benefits or described scope or affecting the schedule, cost or quality
  • StG is ultimately responsible for project success
Project sponsor

On small projects, the project sponsor is the same person as the project owner

  • Act as final approver and founder of the project
  • Approve the total investment cost
  • Head the steering group or delegate this task to the project owner
Project team
  • Plan the project in details within their area of expertise
  • Identify and describe all deliverable's
  • Participate in risk evaluation
  • Identify constraints and assumptions
  • Create detailed work breakdown structure (WBS)
  • Provide realistic time, manning and cost estimates
  • Execute the project plan to accomplish project scope
Line of Business (LoB)

An internal cooperate business unit

  • Negotiate with the project manager on how to meet manning needs
  • Approve project investment application
  • Ensure that present and future operational budgets are made or updated as an result of project activities.
  • Ensure implementation of their individual areas
  • Allocate resources for project activities and participate in Risk evaluation

[edit] Reflections of PEM in Novo Nordisk and implementation in other industries

Novo Nordisk Project Execution Model is a complex model, with many stages and processes, that the project manager need to take under consideration. PEM follow the full project lifecycle from definition and justification of the project, through to delivering demonstrable benefits for the business. One of the things that can challenge other industries to use PEM, is the huge requirement of resources. This is to secure successful completion of the project goal and objectives, but can in some cases be a process where the purpose of for example a steering group meeting is to please the StG instead of secure progress of the project (not say that a StG is not useful, which is definitely not the case). Why the model is useful in Novo Nordisk, is because of the most importance of quality compliance in the company - Novo Nordisk never compromise on quality, which often affect the cost and delivery. And therefore Novo Nordisk experienced, that the need of having more people involved to secure that quality is always fulfilled is important. Poor quality can in worst case be a matter of life and death. The importance of of quality control measures is essential. But to maintain the competitive advantages there is a need of some project progress. These two competing priorities - quality and time to execution - must be well managed through careful process in order to reduce risks inherent on this industry, which can result in more focus and inspection from FDA than necessary. This extremely focus on quality is not necessary in other industries, which mean that some of the requirement in PEM would not be necessary. Therefore PEM is not a fit-to-all project model, but differently a model, that can be adjusted in relation to the industry. However are there still a lot of benefits that can be realized by this model. PEM helps to coordinating the various processes from the different phases, to secure that the project manager are meeting timelines and dealing with complex quality issues. PEM help project managers to assign the appropriate amount of time and resource to each phase of the project, to ensure the project can progress forward in a logical and controlled way. Also the PEM helps to manage the risks while also focusing on the quality. This should hopefully secure no rework [6]

[edit] Additional reading

- Standard operating procedure - To get a better understanding of what a SOP is to know what kind references that are used.

[edit] References

  1. 1.0 1.1 Internal Novo Nordisk SOP 049797 about Global procedure of project execution, 5. edition effective from 29 Juli 2013
  2. Internal Novo Nordisk SOP 055061 about Global procedure of project execution, 1. edition effective from 15 October 2002
  3. 3.0 3.1 3.2 Internal Novo Nordisk SOP 056035 about Handling stakeholders, 3. edition effective from 12 April 2011
  4. 4.0 4.1 Internal Novo Nordisk SOP 076243 about Handling Risk, 8. edition effective from 23 January 2015
  5. Novo Nordisk SOP 080119 about project roles and responsibilities, 2. edition effective from 14 November 2014
  6. [1] By Brandeis University By Leanne Bateman effective from February 2012
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox