Scheduling: Critical path, PERT and Gantt

From apppm
(Difference between revisions)
Jump to: navigation, search
(Indicators to consider)
 
(43 intermediate revisions by one user not shown)
Line 1: Line 1:
''Developed by Frank Almirudis, currently under construction''
+
By Frank Almirudis.
  
''Title to be changed to: '''Choosing critical path, PERT or Gantt as your project scheduling method'''''
+
Migrated to <span class="plainlinks">[http://apppm.man.dtu.dk/index.php/Choosing_between_critical_path,_PERT_or_Gantt_as_your_project_scheduling_method ''' Choosing between critical path, PERT or Gantt as your project scheduling method ''']</span>
  
=Abstract=
+
This page can be deleted if an Admin wishes to do so.
Under the aspect of Complexity in project management, '''Scheduling''' is the development and control of a plan which details when and how the products or services defined in a project scope will be delivered. <ref name=PMI></ref><ref name=PSfS></ref>
+
 
+
The resulting plan is known as a '''project schedule''', which can also be used as a tool for management of stakeholders' expectations, means of communication and/or evaluating performance. Project data like planned dates, activities, resources, constraints, dependencies and activity sequence and duration are all inputs to the project schedule, and should be constantly monitored and updated by the project management team. To properly create and use the project schedule with the aforementioned inputs, the team must select the '''scheduling method''' that best suits the needs of their project.
+
 
+
Three scheduling methods are covered in this article:
+
 
+
* '''Critical path method (CPM)'''
+
* '''Program evaluation and review technique (PERT)'''
+
* '''Gantt'''
+
 
+
The focus of this article is to help the reader:
+
 
+
* Know the definition, theory and purpose behind each scheduling method.
+
* Understand under what circumstances each method is best applied.
+
* Decide which scheduling method fits their case best.
+
* Understand the limitations of their selected method.
+
* Reference the reader to different sources on how to apply their selected method.
+
 
+
=Scheduling methods=
+
 
+
[[File:Pert example.png| 310px | thumb | right |'''Figure 1:''' PERT/CPM diagram example. <ref name=VPO> Made by Visual Paradigm Online.</ref>]]
+
[[File:GC1.JPG|310px|thumb|right|'''Figure 2:''' Gantt chart example. <ref name=JeanetteGJ> Made by Jeanette Garst Johansen September 2016.</ref>]]
+
 
+
'''Critical Path Method (CPM)''' is a technique created to identify the key activities that are critical for the completion of a project, bearing in mind that if any of these were to be delayed, then the whole project delivery would be delayed. The end game of this method is to find and optimal balance between the length of the project and it's associated costs, as well as identifying the costs of the activities are minor according to the optimal time. In order to create a critical path diagram, one must at least consider all the activities that are requied to deliver the project, their duration and their dependencies. As these components are similar to the ones used in PERT, the two methods are often used together and their combination is called PERT/CPM.
+
 
+
'''Program evaluation and review technique (PERT)''' is a scheduling method aimed to create a project's timeline in a graphical manner. This timeline helps the user monitor and control the project's activities while ensuring that the interdependencies between said activities are kept in check and complied to in order to deliver the project. While activities are the central component of PERT, they are not scheduled, this is because the interdependencies dictate when an activity is able to be completed, as all other activities preceding it must be fulfilled before the next activity may be done. PERT diagrams are integrated by 4 key elements: '''Activities, preset date, calendar and contrains.'''
+
 
+
* Activities are sets of errands that are to be done to complete the project, these should have a completion time and a description.
+
* Preset date are set to the activities that may critically affect the delivery, and these dates are aimed to be respected.
+
* Calendar of working and non working days to accurately respresent the time when this project is to be completed.
+
* Constrains to set the interdependencies of the activities, these contratins can be: finish-to-start, finish-to-finish, start-to-start or finish-to-finish.
+
 
+
The timeline using PERT is usually represented by using two methods: '''Activity On Arrow (AOA)''' in which each activity is represented by arrows, while nodes are starting and finishing events of the activities. The other method is '''Activity On Node (AON)''' where activities are repesented as nodes while the arrows are the interdependencies of the activities. Note that an activity may not be started until all preceding connected activites are fulfilled.
+
 
+
'''Gantt chart''' is a visual representation that showcases tasks, ther dependecies and time constrains that allow project managers to identify challenges, control them and come up with different solutions to said challenges, using vertical and horizontal axis to represent a simple timeline for a project. The horizontal axis indicates the time available in a project, while the vertical axis represents the different tasks that need to be performed to do a project in the expected time delivery. Dependencies within each activity can be set as well in this method, however, because of how the visual representation is done in this particular method, adding too many dependencies may generate visual clutter, which can cause confusion to the viewer.
+
 
+
=Indicators to consider=
+
 
+
To properly assess if one should use PERT/CPM or Gantt for scheduling their project, the project management team must consider a number of '''indicators''' regarding the project. These indicators help the team understand where their project stands in a different number of fronts, and by understanding the project's priorities they can decide in a more objective way which method to use.
+
 
+
[[File:IMG 0551 (1).jpg|310px|thumb|right|'''Figure 3:''' Gantt chart used in high complexity projects. <ref name="Google.com">Google.com (2016), ''Google Pictures'',web:http://1.bp.blogspot.com/-_7g6MG6XDYw/T4VTUS5h_LI/AAAAAAAAACM/NfzixKRsXbk/s1600/PanklGanttChart.JPG</ref>]]
+
 
+
'''Complexity'''
+
 
+
The first and most important indicator to take into account is complexity of the project. The number of activities and the level of dependency between said activities will be in most cases the deciding factor in choosing between PERT/CPM and a Gantt chart. While a Gantt chart is a tool which almost anyone can use to generate a project schedule and it's easy to follow, when the activities and their dependencies start to pile up the Gantt chart gets too complex and it's hard to read and follow, losing the most fundamental advantage of the Gantt diagram over PERT/CPM, '''Figure 3''' showcases an example of a Gantt chart used in a situation where the activities and dependencies were too many. An example on complexity can be seen in the Engineering, Procurement and Construction (EPC) process of a thermal power plant. Because of the level of detail that the EPC contractor has to look into in order to deliver a thermal power plant, they are likely to use PERT/CPM to monitor the various dependencies within the project, where as suppliers of specific equipment for the power plant (e.g. a pump manufacturer) will be more inclined to use a Gantt chart, due to the fewer steps in getting a single piece of equipment manufactured. The bottom line is: If the project management team considers that their project is simple enough in terms of activities and dependencies then a Gantt chart should be considered. If the complexity is too high for a Gantt chart, then the reader should consider using PERT/CPM, taking into account the below indicators as well to ensure that they are getting what they want out of their project schedule.
+
 
+
'''Resources available to generate the project schedule'''
+
 
+
Another front that has to be taken into account is the different resources available to generate and update the diagrams. PERT/CPM, while being a more robust scheduling method, takes significantly more resources in order to generate a diagram. It is often done using specialized software and has to be done by a qualified person. Because projects with great complexity generally create more revenue, the money for software and qualified personnel is often not an issure, however, it is important to consider another resource which is time. Time management is also an issue, as it will take longer to develop a PERT/CPM diagram than it will take to generate a Gantt chart. The reader must carefully consider the time available to generate the schedule plan. If the resources are not available, it's adviced to reconsider using Gantt charts.
+
 
+
'''Need for flexibility'''
+
 
+
How much uncertainity exists in the project and how likely is it that activities within the project will change? These are important questions to consider when choosing a scheduling method. This is due to the flexibility of said methods. While PERT/CPM is costly and time consuming to generate, it is also easy to come back and adjust when the project. This is due to the fact that the method not only accounts for the activities that are the most critical to deliver the project, but also the surrounding activities, meaning that if the context of the project was to change, simply adding more nodes of activities or events and updating the corresponding dependencies and dates would be enough to have the project schedule back in track, this makes PERT/CPM an attractive choice when there is risk, since Gantt charts basically have to be generated from scratch each time there is a significant update. Flexibility is one of the strongest points for PERT/CPM.
+
 
+
'''Stakeholders who will need to read the schedule'''
+
 
+
Who can read it
+
Need to use as a communication tool
+
 
+
 
+
'''Dependencies clarity'''
+
 
+
'''Timeframe'''
+
 
+
'''Resource allocation'''
+
 
+
=Limitations=
+
=Application=
+
 
+
 
+
 
+
 
+
=References=
+
 
+
<references>
+
<ref name="PMI"> Project Management Institute, Inc. ''Guide to the Project Management Body of Knowledge (PMBOK® Guide)''. 2017. Chapter 6, page 175. Retrieved from
+
https://app.knovel.com/hotlink/toc/id:kpGPMBKP02/guide-project-management/guide-project-management</ref>
+
<ref name="PSfS"> Practice standard for scheduling</ref>
+

Latest revision as of 14:25, 4 March 2019

By Frank Almirudis.

Migrated to Choosing between critical path, PERT or Gantt as your project scheduling method

This page can be deleted if an Admin wishes to do so.

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox