Work Breakdown Structure (WBS) in Project Management

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 13: Line 13:
  
 
According to the PMBOK, the total of the work is distributed from the lowest to the higher levels, in order to ensure that nothing is left out and prevent any extra work to be performed. It is also worth pointing out that the 100% rule is not only applied in the work packages of the project, but also in the activity level. More specifically the activities which are represented in each work package should sum up to 100% <ref name="link"/>. However, the use of the 100% Rule should be followed with the clear distinction between the elements of the WBS, since it can cause inadequate communication between the project team, double work and confusion from a financial point of view. Hence, it is suggested to use WBS dictionary to avoid this kind of ambiguities in order to eliminate risks regarding the final project outcome <ref name="link"/>.
 
According to the PMBOK, the total of the work is distributed from the lowest to the higher levels, in order to ensure that nothing is left out and prevent any extra work to be performed. It is also worth pointing out that the 100% rule is not only applied in the work packages of the project, but also in the activity level. More specifically the activities which are represented in each work package should sum up to 100% <ref name="link"/>. However, the use of the 100% Rule should be followed with the clear distinction between the elements of the WBS, since it can cause inadequate communication between the project team, double work and confusion from a financial point of view. Hence, it is suggested to use WBS dictionary to avoid this kind of ambiguities in order to eliminate risks regarding the final project outcome <ref name="link"/>.
 +
 +
==The 100% Rule Example==
  
 
The 100% Rule provides the project manager with all the necessary information regarding the specific tasks should be performed in each area in order to complete the project and the responsible people for each task. In that way the project manager is aware of the project’s progress and ensures that everything is aligned and everything is related in the WBS elements. The WBS consists one of the first steps of the planning process, since it allows that all outcomes are specified before the schedule planning. Another critical aspect of the 100% Rule, is that assists the project manager to ensure that project costs are aligned with the work and every activity is related with the project in order to be completed and finally achieve the desired outcome.
 
The 100% Rule provides the project manager with all the necessary information regarding the specific tasks should be performed in each area in order to complete the project and the responsible people for each task. In that way the project manager is aware of the project’s progress and ensures that everything is aligned and everything is related in the WBS elements. The WBS consists one of the first steps of the planning process, since it allows that all outcomes are specified before the schedule planning. Another critical aspect of the 100% Rule, is that assists the project manager to ensure that project costs are aligned with the work and every activity is related with the project in order to be completed and finally achieve the desired outcome.
  
 +
In the following figure is clearly illustrated how the 100% rule can be applied in the WBS of a project. Specifically, the project consists of a deliverable which is defined in the top level of the WBS regarding the construction of a house. In the second level
 +
The 100% rule is clearly illustrated in the following figure which represents the WBS of a project according with the 100% rule’s principles. The project has a deliverable which is defined in the top level of the WBS and The main deliverable which consists the level 1 of the WBS is the construction of the house.
 +
 +
[[File:WBSexample.png|1300px|thumb|center|Figure 1: Work Breakdown Structure of a House Construction, inspired by www.workbreakdownstructures.com.]]
 
==References==
 
==References==
  

Revision as of 00:42, 19 May 2019

Contents

History

The Work Break Down Structure (WBS) was developed during 1960s by the U.S. Department of Defense (DoD) and the National Aeronautics and Space Administration (NASA) under the two main pillars of ‘’planning’’ and ‘’controlling’’ the large projects they were responsible for, in order to provide the best quality. Specifically, on June 1962, NASA and DoD published a document regarding PERT/COST which was the first approach to the Work Breakdown Structure. It is worth pointing out, that this guide was adopted in all services as a military standard across DoD [1].

In 1987, this approach of WBS was documented from the Project Management Institute (PMI) in order to provide a generic concept of these techniques for non-defense organizations. Ergo, the Project Management Body of Knowledge (PMBOK) Guide provides an overview of WBS approach for general application through the organizations.

Definition of Work Breakdown Structure

The Work Breakdown Structure (WBS) is a widely applied tool in the field of project management which is defined as the hierarchical decomposition framework for presenting the work that needs to be executed by the team, in order to achieve the project objectives. (ISO 21500 Standard, p. 18). Specifically, it creates the backbone of the project and provides a clear visual overview of the work to be completed. WBS is a tool that gives the ability to the project team to develop the project schedule and the resource requirements, to estimate and control the cost, while at the same time to minimize the number of unexpected situations. Therefore, the main purpose of WBS is to organize the team’s work into manageable sections and define the total scope of the project.

The 100% Rule

The 100% Rule is one of the most vital principles of WBS, which has been established from the Project Management Institute (PMI), in order to achieve a highly effective WBS and evaluate its decomposition. This rule is defined as: “The next decomposition of a WBS element (“child” level) must represent 100 percent of the work applicable to the next higher (“parent”) element [2].

According to the PMBOK, the total of the work is distributed from the lowest to the higher levels, in order to ensure that nothing is left out and prevent any extra work to be performed. It is also worth pointing out that the 100% rule is not only applied in the work packages of the project, but also in the activity level. More specifically the activities which are represented in each work package should sum up to 100% [3]. However, the use of the 100% Rule should be followed with the clear distinction between the elements of the WBS, since it can cause inadequate communication between the project team, double work and confusion from a financial point of view. Hence, it is suggested to use WBS dictionary to avoid this kind of ambiguities in order to eliminate risks regarding the final project outcome [3].

The 100% Rule Example

The 100% Rule provides the project manager with all the necessary information regarding the specific tasks should be performed in each area in order to complete the project and the responsible people for each task. In that way the project manager is aware of the project’s progress and ensures that everything is aligned and everything is related in the WBS elements. The WBS consists one of the first steps of the planning process, since it allows that all outcomes are specified before the schedule planning. Another critical aspect of the 100% Rule, is that assists the project manager to ensure that project costs are aligned with the work and every activity is related with the project in order to be completed and finally achieve the desired outcome.

In the following figure is clearly illustrated how the 100% rule can be applied in the WBS of a project. Specifically, the project consists of a deliverable which is defined in the top level of the WBS regarding the construction of a house. In the second level The 100% rule is clearly illustrated in the following figure which represents the WBS of a project according with the 100% rule’s principles. The project has a deliverable which is defined in the top level of the WBS and The main deliverable which consists the level 1 of the WBS is the construction of the house.

Figure 1: Work Breakdown Structure of a House Construction, inspired by www.workbreakdownstructures.com.

References

  1. DOD and NASA Guide, PERT/COST System Design, June 1962
  2. Gregory T. Haugan “Effective Work Breakdown Structures”, 2002, Vienna, VA Management Concept, p.17
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox