Femern
From apppm
(Difference between revisions)
Line 7: | Line 7: | ||
==Schedule Management== | ==Schedule Management== | ||
− | ===Estimation of Activity Durations: Three-Point Estimating<ref name="PMBOK 6th Edition">https://app-knovel-com.proxy.findit.dtu.dk/web/view/khtml/show.v/rcid:kpGPMBKP02/cid:kt011DX7BB/viewerType:khtml//root_slug:6-project-schedule-management/url_slug:project-schedule-management?kpromoter=federation&b-toc-cid=kpGPMBKP02&b-toc-root-slug=&b-toc-url-slug=project-schedule-management&b-toc-title=Guide%20to%20the%20Project%20Management%20Body%20of%20Knowledge%20(PMBOK%C2%AE%20Guide)%20(6th%20Edition)&page=1&view=collapsed&zoom=1 | + | ===Estimation of Activity Durations: Three-Point Estimating<ref name="PMBOK 6th Edition">https://app-knovel-com.proxy.findit.dtu.dk/web/view/khtml/show.v/rcid:kpGPMBKP02/cid:kt011DX7BB/viewerType:khtml//root_slug:6-project-schedule-management/url_slug:project-schedule-management?kpromoter=federation&b-toc-cid=kpGPMBKP02&b-toc-root-slug=&b-toc-url-slug=project-schedule-management&b-toc-title=Guide%20to%20the%20Project%20Management%20Body%20of%20Knowledge%20(PMBOK%C2%AE%20Guide)%20(6th%20Edition)&page=1&view=collapsed&zoom=1=== |
Three-point estimating is a tool used to estimate the duration of an activity. It is used primarily when there is insufficient historical data available to produce an estimate. The tool considers a most likely time (tM), optimistic time (tO) and pessimistic time (tP) to produce the best estimate via the following equation: | Three-point estimating is a tool used to estimate the duration of an activity. It is used primarily when there is insufficient historical data available to produce an estimate. The tool considers a most likely time (tM), optimistic time (tO) and pessimistic time (tP) to produce the best estimate via the following equation: | ||
Line 14: | Line 14: | ||
Using this triangular distribution estimation uncertainty and risk can be reduced with respect to single-point estimating. | Using this triangular distribution estimation uncertainty and risk can be reduced with respect to single-point estimating. | ||
− | |||
− |
Revision as of 08:48, 3 March 2020
Collection of tools
Plan Quality Management
Manage Quality
Control Quality
Schedule Management
===Estimation of Activity Durations: Three-Point Estimating[1]
Cite error:
<ref>
tags exist, but no <references/>
tag was found