Iron triangle

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 1: Line 1:
The Iron Triangle for Project Management also called The Magic Triangle, or The Project Triangle is a tool illustrating the three ground pillars when carrying out a project; Cost, Time and Quality. When aiming for a successful project it would be optimal if there were no restrictions to especially the period and economical aspect, to deliver the highest quality when ending the project. However, all projects operate within constraints set to fulfill the overall given task.  
+
The Iron Triangle for project management, also called The Magic Triangle or The Project Triangle, is a tool illustrating the ground pillars when carrying out a project; time, cost and quality (TCQ). Traditionally, a project has been perceived as a success, when being able to deliver within time, cost and quality. The definition and formulation of the model and its ground pillars change according to sources. In some models, a fourth pillar is included, the Scope [2] [4]. This will be discussed in the article.
The Iron Triangle demonstrates the independence of the ground pillars, as they are independent resources with a pin-point approximation of the focus of the project. When adjusting one of the of the pillars it will affect the other two. If the time is short, the budget raise and can result in an unsuccessful project with an undesirable quality.
+
When aiming for a successful project it would be optimal if there were no restrictions to especially the period and economical aspect, to deliver the highest quality when ending the project. However, all projects operate within constraints set to fulfil the overall given task.  
The triangle is an overall simple model to positioning the project between different variables all important to consider when aiming for a good final result. However, many projects do not success within the constraints set for time, budget and quality, and often the limits are exceeded <ref name="Flyvbjerg"> Flybjerg, B. (2011): ''Over Budget, Over Time, Over and Over Again'', From Peter W. G., Morris, Jeffery K. Pinto, and Jones Söderlund (2011): The Oxford Handbook of Project Management (Oxford University Press.), pp. 321-344/</ref>. All projects are unique and complex and must be managed individual <ref name="PMI"> P.M.I. (2017): ''A Guide to the Project Management Body of Knowledge'', 6th edition, Project Management Institute </ref>. Thus, the model has limitations as a project’s success cannot be managed by only three boundaries, but the Iron Triangle can be used as guideline concerning project management <ref name="Atkinson"> Atkinson, R. (1999): ''Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria'', International Journal of Project Management, DOI:10.1016/S0263-7863(98)00069-6 </ref>
+
The Iron Triangle demonstrates the dependence of the ground pillars, as they are dependent resources with a pin-point approximation of the focus of the project. The triangle is an overall simple model to positioning the project between the three different variables all important to consider when aiming for a good final result.  
.
+
The usage of the Iron Triangle can be defined as the quote express; “''The goal of the model is to maintain the focus of the triple constraint power structure on the project higher purpose.''” [6]. The model is used in project management to plan and deliver a project.
 +
 
 +
However, many projects do not success within the constraints set for time, budget and quality. Thus, the limits are often exceeded [1]. All projects are unique and complex and must be managed individually [2]. Thus, the model has limitations as a project’s success cannot be managed by only three boundaries, but the Iron Triangle can be used as guideline concerning project management [3].
 +
 
 +
This article will present the definition of the three ground pillars, their dependence and the application of the model in project management. As a conclusion on the article, the limitations of the model will be presented.  
  
This article will present the definition of the three ground pillars, their independence and the application of the model in project management. As a conclusion on the article, the limitations and criticism of the model will be presented.
 
  
 
__TOC__
 
__TOC__
  
==The Iron Triangle’s three pillars==
+
==Big idea==
'''Independence of the three pillars'''
+
The Iron Triangle is a model based on three constraints, time, cost and quality, which create a frame for project management and a path towards a successful result.
 +
In project management time and cost are highly dependent and linked directly to handling and planning a project. The quality aspect of the model is more discussed, and over time the third factor has been replaced by Scope, Performance, or Requirements. However, the model often returns to its original form as TCQ. The links between time, cost and quality has been identified as strong and decidedly connected contrary Scope, Performance, or Requirements. The three constraints have been commonly acknowledged as a success criteria and tool in project management. However, a large amount of literature [5] specify that there are many factors affecting the conclusion of success of a project whilst other elements affect the success of the management. This will be discussed further down.
 +
 
 +
The Iron Triangle is usually illustrated with the three ground pillars at each vertices of the triangle, as illustrated in the figure below. Some editions of the model have positioned Scope in the middle as illustrated in the second figure. The three ground pillars all contribute to the boundaries of the tasks towards the scope.
  
 
'''Cost'''  
 
'''Cost'''  
Line 18: Line 24:
  
  
[[File:TCQ1.png|400px|thumb|right|The poor listener only knows elements on the surface. The good listener registers elements below the surface and has better options to predict risks and exploit opportunities. Source: Drawing by Anna Fredgaard]]
+
[[File:TCQ1.png|400px|thumb|right|The Iron Triangle with the three ground pillars. Drawing: Emilie Winther Schmidt]]
  
  

Revision as of 17:56, 21 February 2021

The Iron Triangle for project management, also called The Magic Triangle or The Project Triangle, is a tool illustrating the ground pillars when carrying out a project; time, cost and quality (TCQ). Traditionally, a project has been perceived as a success, when being able to deliver within time, cost and quality. The definition and formulation of the model and its ground pillars change according to sources. In some models, a fourth pillar is included, the Scope [2] [4]. This will be discussed in the article. When aiming for a successful project it would be optimal if there were no restrictions to especially the period and economical aspect, to deliver the highest quality when ending the project. However, all projects operate within constraints set to fulfil the overall given task. The Iron Triangle demonstrates the dependence of the ground pillars, as they are dependent resources with a pin-point approximation of the focus of the project. The triangle is an overall simple model to positioning the project between the three different variables all important to consider when aiming for a good final result. The usage of the Iron Triangle can be defined as the quote express; “The goal of the model is to maintain the focus of the triple constraint power structure on the project higher purpose.” [6]. The model is used in project management to plan and deliver a project.

However, many projects do not success within the constraints set for time, budget and quality. Thus, the limits are often exceeded [1]. All projects are unique and complex and must be managed individually [2]. Thus, the model has limitations as a project’s success cannot be managed by only three boundaries, but the Iron Triangle can be used as guideline concerning project management [3].

This article will present the definition of the three ground pillars, their dependence and the application of the model in project management. As a conclusion on the article, the limitations of the model will be presented.


Contents


Big idea

The Iron Triangle is a model based on three constraints, time, cost and quality, which create a frame for project management and a path towards a successful result. In project management time and cost are highly dependent and linked directly to handling and planning a project. The quality aspect of the model is more discussed, and over time the third factor has been replaced by Scope, Performance, or Requirements. However, the model often returns to its original form as TCQ. The links between time, cost and quality has been identified as strong and decidedly connected contrary Scope, Performance, or Requirements. The three constraints have been commonly acknowledged as a success criteria and tool in project management. However, a large amount of literature [5] specify that there are many factors affecting the conclusion of success of a project whilst other elements affect the success of the management. This will be discussed further down.

The Iron Triangle is usually illustrated with the three ground pillars at each vertices of the triangle, as illustrated in the figure below. Some editions of the model have positioned Scope in the middle as illustrated in the second figure. The three ground pillars all contribute to the boundaries of the tasks towards the scope.

Cost

Time

Quality


The Iron Triangle with the three ground pillars. Drawing: Emilie Winther Schmidt


Application

The Iron Triangle is used for project management, when a project has a defined start and end. Project Management is utilising a gathering of models, tools and techniques to move a unique project forward within the variables time, cost and quality [1] .

Limitations

Thus, the Iron Triangle is an incomplete model [1] , as there are many factors affecting and controlling a project. The success of a project cannot be controlled by three factors but must contain aspects of e.g. benefits for the customer and end-user [2].


Annotated bibliography

Maylor, H. (2010): Project management, Chapter 4, 4.2


References

  1. 1.0 1.1 Atkinson, R. (1999): Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria, International Journal of Project Management, DOI:10.1016/S0263-7863(98)00069-6
  2. P.M.I. (2017): A Guide to the Project Management Body of Knowledge, 6th edition, Project Management Institute