Milestone Planning
Line 97: | Line 97: | ||
*For this article it is important to use the literature Standard for Program Management. This standard clearly provides terms and definitions that explain precisely information regarding program and its uncertainties. … | *For this article it is important to use the literature Standard for Program Management. This standard clearly provides terms and definitions that explain precisely information regarding program and its uncertainties. … | ||
+ | |||
+ | Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute Retrived form https://www.pmi.org/learning/library/milestone-different-planning-approach-7635. | ||
+ | *The article: Milestone Planning - a different planning approach, critically discuss different approaches referring it all to a milestone plan. Besides, a reflective and constructive explanation for what a milestone is and when can a time schedule be planned etc. those subjects and other aspects are described with convincing details and references. Furthermore, the author is capable of navigating between different topics and create concrete statements. This is some of my reason to recommend reading this article to everyone that is interested in milestone planning. This article by expand your knowledge upon the topic. | ||
=='''Reference'''== | =='''Reference'''== | ||
<references/> | <references/> |
Revision as of 20:21, 21 February 2021
The characteristics for a successful plan are to provide a path that lead towards a specific goal within a projects scope. The path to create a decent plan can be divided by various activities, uncertainties, phases, and decisions. The similarly between those unknown variables are that they are a part of a milestone plan which is an essential project, program and portfolio management tool. Managing or using a milestone plan allows management on different detail levels. The tool can navigate between important phases and its decision points. [1]
A milestone plan is constructed by milestones instead of focusing on activities. When using a milestone plan in a project planning it gives a goal- and result orientated planning. [2] In a beginning of a project a milestone plan can give assistance to clarify some of the deliverables for the project within the present knowledge. It is important to know the project goal(s). Some project goals are not concrete and therefore alternated although the planning. Changes though the planning is necessary to reach a common goal that satisfies all stakeholders. The goal can be redirected by new knowledge and that is why it is important to have milestones which create a decision point on “Are we going in the right direction, or do we need to alternate our future planning?” or “Have we achieve the deliverables for this milestone?”.
This article will explore a few scenarios where a milestone plan is either used in a program plan or a contribution by creation a monitoring platform that allows a regular review of the project-, program, or portfolio achievements with in an organization´s strategic plan. Furthermore, the concept will be reflected critically with a practical approach and guidance. [3]
Contents |
Context
- Project has a life cycles and contain various elements such as activities, objectives, focus, benefits etc.
- Program is defined by multiple projects which are grouped together. With subsidiary projects it is possible to track the interdependencies and which intended benefits are achieved. This may not be possible by managing each project individually.
- Portfolio is an effective managing of multiple programs and projects. Portfolio is a process with subsidiary programs and projects that are grouped to gain strategic objectives. [5]
Planning is an essential part of every aspect for managing a project, program, or portfolio. A milestone plan can be used and executed in all detail levels but are used for different purposes. One reason could be that a project and a program both include elements of time. Time regarding a project or a program indicate that it is temporary. Even if a program takes years or decades to fulfill its panned achievements. In contrary, a portfolio does not need a specific end date.
A portfolio encompasses various elements of initiatives and work is not related to each other, to attain the planned benefits. The beginning of initiatives is related to an organization’s strategic plan. The organization’s strategic plan can control the start, or the end of a specific investment. This means the owner(s) of the portfolio are grouping resources dependent on the different subjects such as geographical area, work that must be delivered to the same client, etc. In these scenarios it can be complexed to use a milestone plan.
A plan consisted of milestones for a portfolio could be use, but it cannot obtain concrete monitoring, because portfolios and its activities are not necessary linked together. To get an overview of the relationship between projects, programs and portfolio can figure 1 be used. This figure 1 illustrates a strategy regarding an organization as an example. As mention earlier, a portfolio can contain other portfolios and programs. Portfolio management can include stand-alone projects or have multiple programs before it reaches the portfolio level. The objective of these variations is to gain the planned benefits or subgoals. Furthermore, it is important to notice that the relation between a project, program, or portfolio share resources and stakeholders.
This information is critical, because there is a limit to the resources and which project it is allocated to. The variation for a portfolios structure is important regarding resources. You can ask yourself; “does a portfolio have 3 programs, 5 projects that need resources?” or “does a portfolio consist of 1 program with 10 projects?” This difference changes the allocation of resources and the strategy to group resources for every part. [6]
Explanation and its purpose
A project is typically divided into parts of purpose, people, complexity, and uncertainty. These categories will not be fully explained in this paper. All parts are important and provide methods, knowledges, and management tools to deal with every aspect of handling a project, or other activities. General a plan requires a schedule. When making a schedule it is the activities that gives the schedule a period that is depended on time. This is possible when all activities are clear and known. In many cases it is not the case. When working on a case many questions and uncertainties will rise. Most uncertainties are linked to the missing knowledge on the topic. Is it a common project with high knowledge or is it a unique project with low knowledge? This can increase the complexity drastically and to control complexities, it can be divided into subcategories. A quick view of possible complexities in a project.
- Technical and task complexity
- Time complexity
- Goal complexity
- Social complexity
- Organizational complexity
- Legal complexity
Then a project, program, or portfolio can be complex. Every subcategory relies on methods, concepts, or tools that helps solving the equation for complexity. For planning a project, it is within the time complexity. This include various elements such as milestones, Critical Path Analysis, Gantt chart, etc. Also, in the time complexity questions can be; “How much time does it take to complete an activity or task?” or “When can an activity begin then it will achieve the planned result?” and “How many resources does an activity need and does it require help from individual expertise?”
By diving into the complexities of a project is it vital to know the project scope. Goals for a project is usually set to a predate based on the initial knowledge. In other word, the main task for complexity is to create structure. There are many ways to create structure for a project. The main objective for this paper is to use a milestone plan to create structure. The layout for explaining and discuss a milestone plan is inspired by the literature “Power i projekter og portefølje”.The literature inspired a practical approach concerning a milestone plan.
First step toward a structure is to separate the projects purpose into deliverables. Then when all deliverables are fulfilled the projects purpose is achieved and that is illustrated in the right-side of figure 2. As it is visible, the purpose is divided into deliverables. To achieve every delivery there is created work packages. These work packages are main activities that later leads to a delivery. A work package contain multiple activities and they can be either goal- or result orientated. Several projects are using Work-Breakdown-Structure, shortened WBS. This method provides a hierarchy that break a project into phases, deliverables, and work packages. When a delivery is concrete will it become possible to manage. As an example, a construction of a house is divided by several deliverables which involved contractors. With a separation of the contractors, they will experience to be limited to a specific amount of time. Also, they may do critical work before another contractor begins. So, a contractor is responsible to work within a certain time and trust other to deliver their work on time. If one contractor is delayed it can delay many activities. If this occurs and it pushes other activities, then the critical path is located. Another example would be for an organizational project of change The deliverables for a case like this could be by separation into subjects as organizational structure, work patterns, implementation of a new IT systems, provide guidance for employees, etc.[ref ppp] The common question for both examples are the knowledge high or low? A carpenter has built a wall numerous times and knows how to estimate the time to finish one wall. Nearly all participants involved in the construction of the house knows the required time for doing their work. A project of change in an organizational has other factors than estimate the work and delivery of physical products. To change an organization, it also demands a change of people and their individual work routines. They must learn how to adapts and execute a new implement of for example. As mention earlier, this could be by learning a new IT system or a radical change in their everyday work life. Also, people tent to disagree changes because it affects them. [7]
Second step is to establish milestones regarding to the work packages and they are illustrated by diamond shaped geometry in figure 3. A milestone is a sub-delivery that leads to certain deliverables. Milestones can depend on another milestone. As discussed earlier in the first step, there are two ways to achieve a schedule. One way is typically a project that has been standardize which mean the activities are known. This structure tents to focus on activities before using milestones. The other way is when activities are unclear, then it is important to keep track on the deliverables. This structure uses milestone before focusing on activities. If activities are unknown, would it be best to establish milestones. A reason to use milestones before activities is that a milestone does not alternate throughout a project. There are many possibilities or rather activities that lead to a milestone. A quick example could be that you are bicycling home to your parents, and you know three different roads to get home. The distance and time for the three roads are important, but the main objective are they all lead you home. The roads symbolize activities and your parents’ home as a milestone. This is three different ways to reach your sub-delivery and it is to get home. [8]
Third step is to understand and organize milestones into logical ties or dependencies between milestones. They may be time depended. For doing so, the logical order is just as important as every milestone achieving its goals. To illustrate these milestones are added to figure 4. The milestones after the marked milestone are altered by the result form the marked milestone. Other aspects for the marked milestone are that it has several resources attached. This mean there could be more area of responsibilities within it and they are all depending on the result. If the deadline for a marked milestone are changed it is important to include all parts concerning the specific delivery for that milestone. If there are two work packages that shares several milestones it will be recommendable to combine them into one, because they properly have the same deadlines. [9]
Fourth step happens after all milestones are established and dependencies between milestone is determined. The separation into phases can be created and this is shown in figure 5. The figure shows the deliverables and work packages separated into phases. The purpose of phases is to divide the project into main subjects. In other words, it happens when a project changes character and the initial knowledge has increase and uncertainties has decrease. With every phase the knowledge increases and the uncertainties decrease. The critical purpose for a phase is to finish a main subject that provide a clear perspective for the next phase. The first phases are for early analysis or design phases where it is used to create clear problem statements. When a proper problem statement is done then the beginning of work packages can be distributed. When performing the implementation phase the manager can provide guidance and coordination for all deliverables. All milestones do not have the same deadline at the same time. [10]
Fifth step is to include decision making or decision point near a new phase. In figure 6 there is now added a decision point to every phase. These decision points are useful to monitoring and plan the next move for a new phase. It is important to discuss the criteria for starting a new phase. The stakeholders must approve going further with the project and focus on the next phase. Aspects must be discussed, such as “Has the uncertainties decreased enough to continue with next phase and do we reach our expected result at this point?” or “Do we have to rethink our anticipated budget or risk management and is this project relevant anymore? Those question are an essential to estimate a qualified guess for the future. Do not make the mistake to forget including decision points, because has the phase achieved its goal? Practical it is advisable to mark the deadlines for each decision points then a project manager or other stakeholders can prepare for them. [11]
Sixth step it about defining the activities that fulfills the needs for every milestone. The activities are not clear for every milestone. That is one of the reasons it is good to start dividing into the main activities when the knowledge is high enough. It is not necessary to know all details in the start. That is why it is better to have an overview for the whole project with a milestone plan. To complete the activities questions stating “how, when, and where” is needed to accomplish. Besides knowing the activities, it is important to secure that the activities does not clash into one another. This occurs when activity A is depending on activity B and cannot start before activity A finish. This phenomenon is called the Critical Path Analysis which is illustrated by figure 7. Furthermore, it is about which path can delay the entire project if something is delayed. Several activities can be ongoing but if they are not linked together or are near a milestone they are not as critical. This is also illustrated by figure 7 where the deadlines for each activity is different but activity A, is the critical one. [12]
Guidance with a practical approach
To give an example for a milestone plan this section will focus on a project that has to build a house. To describe this milestone plan will figure 6 be used and filed with information as seen in figure 8.
The purpose is to build a house and that has been done numerous times. That means the knowledge level is high, and uncertainties are low, because there are standards for, how to build a house. It is common to use a milestone plan that is created by knowing the activities. Along the way, activities are used to determine milestones and then a deadline is fixed. The approach for this case will mainly follow the previous section: Explanation and its purpose.
When building a house there are several contractors involved which include their corporation and knowledge. That is important for the project. When you want to build a house and you are paying, you become the Builder or owner of the house. It means that you are in charge, but you do not need knowledges regarding buildings So, the deliverables are divided into category as contractors, payments, documentation, quality check, etc. These deliverables are not completed at the same time, but they are all depending on one another. Those deliverables are shown in figure 8. An example, you need to install the plumbing and electrical installations before closing the flooring. If the floor is closed before they are done, then it is impossible to finish their work. This example does illustrate a need for a milestone because the floor cannot be finish before the pluming nor electrical installations are finished. The activities for building a house is known. An estimation for a deadline is possible when corporation with the contractors.
Using milestones for planning decide the delivery date of the house, but those milestones can even be used for ongoing payments to the contractors. As an owner, you are not obligated to pay all the expenses to the contractors or other involved in the beginning of a project. This depend on the agreement between the owner and contractors. This will not be discussed into further details.
In a case like this, it would be practical to get an overview for the phases depended on the initial knowledge level upon building a house. There are known phases which is commonly used when building a house and those phases are Design phase, Project design, Implementation phase, and Operation and Maintenance. In other cases where standard is not available it would be advisable to find similar projects or literature that can provide guidance. Concerning the decision point, it is used to monitoring the project and its deadlines These dates are important tool to control and check the contractors if they are following the schedule or not. Typically, a schedule for a plan is created with a Gantt chart. A Gantt chart is a scheduling tool that can illustrate and monitor a project into the desired detail level. Often are this done digitally, and the schedule follows the milestone plan. By combining a milestone plan with a Gant chart, it creates a practical way to motoring without a daily visit to the constructions site. On a construction site is it recommendable to use a management method called Lean management. In short terms it provides for example a weekly meeting on the site where all contractors are together to discuss the present challenges that has occurred. On these meetings the opportunity to discuss and deal with the known critical part of the project or which elements that can influence the project in the future if they are delayed.
Limitations
There are many aspects to a milestone plan that need attention and clear meaning of it. First, a milestone plans application depends strongly on the project strategy. Up until now a milestone plan is mostly explained by an implementation strategy. This type of strategy tent to focus more on detail levels rather than the principles on how a project reach its goals that is planned by the base organization. This mean that an organization can describe how a project should reach it goals and this can compromise several activities. In the previous sections, milestones are described to be dated as deadlines or events which often is correct but mixes two components together. A milestone consists of what we want to achieve and when we are there that is the deadline or event of a milestone. Now, we know want to achieve and when its deadline is, so how does a project manager or stakeholder determine we have reached our goal? Is the delivery a physical product, or is it an abstract quality? Those two questions are world apart, because they are not comparable. It is great to make a milestone plan, but if a delivery, or a goal does not have a verification tools or description it is hard to tell whenever a delivery reaches the expectations for a specific milestone. This is a huge point, because if the goal for a delivery is not clear the when are the delivery good enough to proceed to the next milestone? [13]
Another reflective thought on milestone plans and its application is how detailed it can or should be? As mention earlier. A milestone plan is a logical path toward the purpose of a project. Milestones are not supposed to be changed even if there are radically changes to the activities. A milestone is a robust structure that stand its ground throughout a project lifecycle. Furthermore, a milestone plan does not need to be in great details, because every achievement is descried and how it is going to be evaluated. The activities within a milestone can changes due to gained knowledge or decision making from stakeholders etc. Again, this does not change the intention for a milestone. This does not incite that detailed planning is unimportant, because it is not! It is important to plan in detail when it is necessary and not just, because you have do make a detailed plan. An early detailed plan can lead to unnecessary discussions because a milestone can reach its goals in different ways. Every milestone needs separate activities and therefore a detailed plan could be made for each milestone. The start of a milestone is something that is determine by a project manager. When activities for a milestone is known is it possible to create a schedule, because an estimation of time can be done by knowing the activities. For scheduling into further details a digital Gannt chart are usually used. [14]
In context to project, program, and portfolio management it was discussed that a milestone is most suitable for a project, or program. This may be true upon a common understanding of a milestone plan being used for concrete projects or program. As discussed earlier, what define a milestones success and are the delivered deliveries enough? This may be clearer within a project, or program, because the purpose, or scope can be measurable. In contrary to a portfolio however can we determine whenever a milestone is achieved or not? Of cause, there must be a description of what a milestone should reach, but when it is good enough? This is not impossible to obtain, but due to the uncertainties and its complexity it becomes easy to lose track for the scope in the process. Especially, when a portfolio can take years and even decades to achieve. Furthermore, addressing the milestones in a way that allows non-experts to understand the scope of the project is good practices for programs and especially portfolios.
In general, a milestone plan can be used whenever you are a project manager in a project, program, portfolio management. The important aspect it to use navigate between the initial knowledge and which goals that is set for the scope. This discussion based on subjects form the annotated bibliography and a critical article which discuss milestone planning in different approaches. [15]
Annotated bibliography
Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- This reference discuss the concepts of various management tools including milestone plan. It establishes the basis for at great planning within a practical approach. Beside the basis knowledge, it successfully connects specific parts to a project, program, or portfolio management. When planning a project independently the path to achieve it may be different considered to several reasons. Some of the reasons could be the present knowledge and which effect it has on stakeholders and the steering committee. This balance of information on the concrete management tools and how to implement them on a project, program, or portfolio is why this reference is annotated.
Project Management Institute, Inc.. (2017). Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th Edition). Project Management Institute, Inc. (PMI).
- This is a standard regarding project management and knowledge. It provides knowledge on the relationship for project, program, and portfolio management. The relationship is illustrated by an organizational approach toward an understanding that embrace the differences. …
The Standard for Program Management – Fourth Edition (2017).
- For this article it is important to use the literature Standard for Program Management. This standard clearly provides terms and definitions that explain precisely information regarding program and its uncertainties. …
Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute Retrived form https://www.pmi.org/learning/library/milestone-different-planning-approach-7635.
- The article: Milestone Planning - a different planning approach, critically discuss different approaches referring it all to a milestone plan. Besides, a reflective and constructive explanation for what a milestone is and when can a time schedule be planned etc. those subjects and other aspects are described with convincing details and references. Furthermore, the author is capable of navigating between different topics and create concrete statements. This is some of my reason to recommend reading this article to everyone that is interested in milestone planning. This article by expand your knowledge upon the topic.
Reference
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, Chapter 5, DJØF Publishing (2008), ISBN: 978-87-574-1665-7
- ↑ Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute. Retrieved from https://www.pmi.org/learning/library/milestone-different-planning-approach-7635
- ↑ The Standard for Program Management — fourth edition. ProQuest Ebook Central https://ebookcentral-proquest-com.proxy.findit.dtu.dk
- ↑ Project Management Institute, Inc.. (2017). Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th Edition). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/toc/id:kpGPMBKP02/guide-project-management/guide-project-management, Figure 1-3, page 12.
- ↑ Project Management Institute, Inc.. (2017). Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th Edition). Project Management Institute, Inc. (PMI). Retrieved from https://app.knovel.com/hotlink/toc/id:kpGPMBKP02/guide-project-management/guide-project-management.
- ↑ — fourth edition.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 149-155, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 156, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 157, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 158, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 158-160, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Attrup, M. L. and Olsson, J.R. , Power i projekter og portefølje, page 161, DJØF Publishing (2008), ISBN: 978-87-574-1665-7.
- ↑ Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute Retrived form https://www.pmi.org/learning/library/milestone-different-planning-approach-7635
- ↑ Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute Retrived form https://www.pmi.org/learning/library/milestone-different-planning-approach-7635
- ↑ Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute Retrived form https://www.pmi.org/learning/library/milestone-different-planning-approach-7635