Parkinson's Law in Project Management

From apppm
(Difference between revisions)
Jump to: navigation, search
(Implications on Project Management)
(Implications on Project Management)
Line 25: Line 25:
  
 
== Implications on Project Management ==
 
== Implications on Project Management ==
The behaviour associated with Parkinson’s Law has a great influence on project performance.<ref name="incencitives"> Chen, B. & Hall, N. G. (June 12, 2020). [https://www.sciencedirect.com/science/article/pii/S0377221720305476 "Incentive schemes for resolving Parkinson’s Law in project management"]. European ''Journal of Operational Research.'' '''288''' (20): 666–682. doi 10.1016/j.ejor.2020.06.006</ref> Along with student syndrome, it is one of the main reasons why deadlines are not met and projects are inefficient.  
+
The behaviour associated with Parkinson’s Law has a great influence on project performance.<ref name="incencitives"> Chen, B. & Hall, N. G. (June 12, 2020). [https://www.sciencedirect.com/science/article/pii/S0377221720305476 "Incentive schemes for resolving Parkinson’s Law in project management"]. European ''Journal of Operational Research.'' '''288''' (20): 666–682. doi=10.1016/j.ejor.2020.06.006</ref> Along with student syndrome, it is one of the main reasons why deadlines are not met and projects are inefficient.  
  
 
Within project '''scheduling''', it is important a project manager is aware of it. According to Parkinson's Law, it is assumed that a task either is completed on time or is delayed. The task is not completed before time. To achieve the most efficient use of resources and time, the time allocated for each task needs to correspond with the time it actually takes to complete it. If the allocated time is too short the task is delayed and if the allocated time is too long unnecessary time is spent on the task. However, it is difficult to accurately estimate the time needed as it depends on a number of factors, such as the estimators knowledge about task, the competencies of the person allocated to the task, and available resources.  
 
Within project '''scheduling''', it is important a project manager is aware of it. According to Parkinson's Law, it is assumed that a task either is completed on time or is delayed. The task is not completed before time. To achieve the most efficient use of resources and time, the time allocated for each task needs to correspond with the time it actually takes to complete it. If the allocated time is too short the task is delayed and if the allocated time is too long unnecessary time is spent on the task. However, it is difficult to accurately estimate the time needed as it depends on a number of factors, such as the estimators knowledge about task, the competencies of the person allocated to the task, and available resources.  

Revision as of 13:55, 28 February 2021

Parkinson's Law states that work expands to fill the time available for its completion.[1] It was formulated by British historian and author Cyril Northcote Parkinson in an essay for The Economist in 1955.[2]

Originally, Parkinson's Law described how a bureaucracy can grow unrelated to its actual workload because people make work for each other by complicating work. The growth of bureaucracy depends on two factors: (1) The Law of Multiplication of Subordinates and (2) The Law of Multiplication of Work. From statistical analyses, Parkinson determined the increase in staff per year to be around 5-7% independent of its workload. Based on this, he formulated a mathematical formula to determine the annual increase in staff in any public administrative department.[1]

The tendency in work behaviour Parkinson's Law describes, is one of the reasons why projects are delayed. Parkinson’s Law explains the behavioural aspect of scheduling. According to Parkinson's Law, a person will spent all the available time to complete a task regardless of the tasks size. This results in inefficient use of time and effort. Project managers can use this to understand employees motivation for completing tasks. In project schedule management, this is valuable knowledge when estimating activity duration. The project manager should account for this tendency when scheduling to enhance productivity. [3]

This article highlights areas in project management where techniques and tools are affected by Parkinson's Law. Tools to minimise the implications of Parkinson's Law are suggested and reflected upon. Parkinson's Law is difficult to manage. It depends on how good the scheduling is, which also depends on how good resources are allocated and then there are risks, which makes scheduling uncertain at times.

Contents

Theory

In Parkinson’s essay from 1955[1], the law refers to the relationship between the bureaucracy and its workload. The law describes how people make work for each other by complicating the work. Therefore, a bureaucracy can grow unrelated to its actual workload. The growth depends on two factors: (1) The Law of Multiplication of Subordinates and (2) The Law of Multiplication of Work. The Law of Multiplication of Subordinates states an overworked person, seeking a promotion, in an organisation has incentives to multiply subordinates instead of creating rivals by sharing their work. The Law of Multiplication of Work states that people will make work for each other by complicating it to occupy everyone. This gives the impression that the staff is overworked and lacking resources, therefore more staff is hired.[1]
Parkinson uses the bureaucracy of the British Civil Service as an example of Parkinson’s Law.[4] He supports his statements with statistical analyses showing that the number of ships and men in the royal navy fell between 1914 and 1928, while the number of employees in administration rose. With these analyses, he determined the rate of staff per year to be around 5-7% independent of the amount of work. He formulated the following mathematical formula to determine the annual increase in staff in any public administrative department:[1]

 x = \frac{2k^m+p}{n}

  • k = number of employees with incentives to multiply subordinates
  • m = number of hours devoted to answering minutes within the department
  • p = difference between the ages of appointment and retirement
  • n = number of effective units being administered
  • x = number of new employees each year[1]

The definition of Parkinson’s Law as known today is the first sentence of the essay, "It is a commonplace observation that work expands so as to fill the time available for its completion" (Parkinson, 1955). Parkinson describes how work is elastic in its demands on time. Work becomes more complex as to fill the time before completion. He uses the example of an elderly lady spending a whole day writing and sending a postcard. A busy man could do it in three minutes, yet the lady spends the day worrying and stressing over sending the postcard.[1]
In project management, this is the definition applied. Parkinson’s Law describes the tendency that people will spent all of the allocated time to complete a task regardless of the time it actually takes to complete it. Likewise, a person will not complete a task before a deadline, resulting in inefficient use of resources and time. For instance, a person has one week to complete a task that takes 8 hours, but instead of completing it on the first day using all of their effort, the person will use less effort and spent a week.

Implications on Project Management

The behaviour associated with Parkinson’s Law has a great influence on project performance.[5] Along with student syndrome, it is one of the main reasons why deadlines are not met and projects are inefficient.

Within project scheduling, it is important a project manager is aware of it. According to Parkinson's Law, it is assumed that a task either is completed on time or is delayed. The task is not completed before time. To achieve the most efficient use of resources and time, the time allocated for each task needs to correspond with the time it actually takes to complete it. If the allocated time is too short the task is delayed and if the allocated time is too long unnecessary time is spent on the task. However, it is difficult to accurately estimate the time needed as it depends on a number of factors, such as the estimators knowledge about task, the competencies of the person allocated to the task, and available resources.

Besides scheduling, resources, risks, and governance are also affected by Parkinson's Law.

Scheduling

In project scheduling, the objective is to make a detailed plan of activity durations and dates to ensure timely completion of a project. The plan is continuously monitored and controlled and used as a tool for communication and managing stakeholder's expectations.[3]
In terms of Parkinson's Law in scheduling, the concern is whether time and resources are used efficiently. Parkinson's Law can affect several aspects of scheduling and result in inefficiency if not properly managed. It is important project managers are aware of the behaviour caused by Parkinson's Law and how they can minimise it with scheduling. Clearly, the quality of a schedule depends on other factors such as the number of available resources and the allocation. However, in the following section the focal point is purely project schedule management.

According to the PMI standard 'Guide to the Project Management Body of Knowledge (PMBOK® Guide)' (2017), project schedule management consists of six processes to properly manage the completion of a project. The processes are: (1) Plan Schedule Management, (2) Define Activities, (3) Sequence Activities, (4) Estimate Activity Durations, (5) Develop Schedule, and (6) Control Schedule. The fourth process, estimate activity durations, has a great influence on whether Parkinson's Law is showing. To minimise the implications of Parkinson’s Law, the estimated activity durations need to correspond to the time it takes to complete the activity with the estimated resources and with maximum effort. This process requires an estimation of the amount of work effort required to complete the activity and the amount of available resources estimated to complete the activity. However, estimation of durations is challenging and depends on a number of factors, such as the available data, the estimators knowledge, etc. and the technique used. Estimations of durations also tend to be larger - look at ref - incentives

Parkinson's Law in agile vs sequential projects

The following scheduling techniques and tools can be subject to Parkinson's Law if not properly managed:

  • Three-point estimating is used to determine the duration of an activity in the fourth process, estimate activity durations. Unlike techniques with the same purpose, three-point estimating considers estimation uncertainty and risk and estimates three durations: The most likely, the optimistic, and the pessimistic. While the three-point estimate clarifies the range of uncertainty, suggesting three durations allows for Parkinson’s Law. If the pessimistic estimate is the longest allowed time while meeting the project completion, people will assume they have more time.[3]

if this is done my people they will overestimate their timelook at methods in standard

  • Reserve analysis is used to determine the amount of reserve needed to handle contingency. Duration estimates can include contingency reserves, also known as schedule reserves, to account for uncertainty. The contingency reserve should be used, reduced, or eliminated as the project progresses and more information is available.[3] According to Parkinson's Law, instead of using the reserve on contingencies, people will assume they have more time to complete an activity without delaying the project and use it. The contingency reserve is most likely used rather than reduced or eliminated.
When dealing with Parkinson’s Law, it is important to set realistic, but tight deadlines. By having contingency reserves, you risk Parkinson's Law.
  • Critical path method (CPM) is one of the techniques used to develop a schedule in the fifth process. CPM is used to identify the shortest time to complete a project based on the estimated activity durations. The schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations. CPM helps the project manager determine if a schedule is on the critical path.
If not properly managed, people will start an activity on its late start date, consuming all float and turning all paths critical.[3][6][7]

The following techniques could compromise efforts to minimise implications of Parkinson's Law:

  • Crashing is a common technique used when an activity or project is behind schedule. More resources are added to shorten the time to completion.[3] Crashing may be applied to a project delayed by the implications of Parkinson's Law.
Parallels can be drawn between the observations Parkinson made in his essay and The Mythical Man-Month by Frederick Brooks (1975). Brooks' Law states that adding people to a late project, makes it later. This statement is based on Brook’s own experiences at IBM. When a software project was behind schedule, the project was crashed. However, by adding more people, bureaucracy and training increased. Instead of being more effective, the project was delayed further.[8][3] Both laws have in common, that the increase in bureaucracy, leads to inefficiency. If a project is affected by Parkinson's Law, crashing may be a technique applied to salvage the schedule. However, crashing can increase risk and cost and may actually have the opposite effect and delay the project even further.
  • Multitasking is typically used when a project, due to some unexpected event, needs to synchronise activities to stay within schedule. Multitasking is unavoidable in most projects as activities often are related.[9]
The nature of multitasking increases the risk of enabling the behaviour caused by Parkinson's Law. Multitasking requires a number of activities to be completed within the same time frame, thus requiring people to divide their attention and effort between each activity. This approach contradicts Parkinson's Law describing that the least amount of time and maximum effort should be used to complete an activity. Attention is diverted from the single activity and time is spent on shifting between activities.[9]

Resources

missing ref!!

As a result of inadequate scheduling, human and financial resources are used unproductively. Resources are allocated according to the schedule to ensure both human and financial resources are available to complete the project. If all of the allocated time is spent on completing an activity, independent on the actual completion time, so are the resources. If time is spent more productively, the resources can be applied to another part of the project or organisation.
The typical response to a delayed activity is to apply more resources to stay within schedule. If the activity is delayed due to Parkinson's Law, resources have initially been spend unproductively and to recover from this, more resources are added. Parkinson's Law plays a great role in project performance because it affects how and when projects are delivered.
This corresponds well with Parkinson's initial observations. If a person feels overworked, they will hire subordinates and complicate the work to occupy everyone. Resources are spent inefficiently and may lead to further stress and complexity.

expenditure expands to budget - if a project is scheduled wrong and assumes more costs are needed, then these costs are used up

https://www.pmi.org/learning/library/program-evaluation-review-technique-parkinsons-1972

Risks

According to Parkinson's Law, people complicate their work to fill the available time to completion. Inherently, this can lead to a number of risks. As described by Parkinson, Parkinson's Law in a bureaucracy leads to increased risk of stress and higher costs. In projects, tasks and activities may appear more complex than they actually are and lead to increased levels of stress. Additionally, inefficiency results in higher costs. By managing Parkinson's Law, the manager can also account for potential risks that affect the project's performance.[10]
Furthermore, contingency reserve is used to manage risk. As mentioned in Scheduling, the use of reserve can lead to increased behaviour arising from Parkinson's Law. Therefore, a manager must be aware of Parkinson's Law while using this technique.

doing more with less, due to PL set aggressive targets and do more with less

Governance

Parkinson's Law can affect decision-making in project management. Studies have shown that the size of a cabinet is negatively correlated with government effectiveness. In large groups, smaller groups begin to form and block each other, which is why decision-making is difficult to manage in large groups.[11]

Typically a project is no larger than 20, but this can affect decision making

Parkinson's Law can also apply to other parts of project management such as the productivity in meetings.

Minimise the Implications of Parkinson’s Law

By monitoring and controlling the status of the project against the developed schedule, the project manager can take corrective action if the project is delayed due to Parkinson's Law. Techniques such as Variance analysis show possible variances in CPM.[3] The variance analysis can uncover if people are starting on the late start date and consuming alarming amounts of float due to Parkinson's Law.
Furthermore, it is important people know when a task or activity is done to avoid spending unnecessary time lingering. If tasks are properly broken down and have clear goals, it is easier to determine when it is done.
The following suggestions are additional initiatives to minimise the implications of Parkinson's Law.

Critical Chain Project Management

Critical Chain Project Management (CCPM) is an alternative approach to CPM that actively seeks to eliminate the implications of Parkinson’s Law. Unlike CPM, CCPM considers activity interdependence and resource constraints and eliminates float and slack. This method assumes activity durations are purposely overestimated to ensure timely completion. This results in a false sense of security as people will use all the allocated time and safety time according to Parkinson’s Law. The safety time of each individual activity is allocated into one central buffer, a project buffer, at the end of the schedule. The activity durations are based on a 50% confidence level, instead of the commonly used 80-90% in project management. By aiming for durations that are too tight, attention is not diverted from the task and multitasking is avoided. Furthermore, if activities are delayed, it will not cause the entire schedule to slip. With a 50% confidence level, the activity cannot realistically be expected to be completed within a certain time. Therefore, task due dates and milestones are not set. This also eliminates the possibility of Student Syndrome.
There are three kinds of buffers: Project buffers, feeding buffers, and resource buffers. Project and feeding buffers are safety times, while resource buffers act as warning signals to ensure timely availability of resources. The critical chain is the longest resource-leveled path through the schedule including all buffers.[6]
During project execution, the consumption of the project buffer is monitered. If activities require more time, it is consumed from the common project buffer and if an activity is completed early, the time is added to the buffer. Using a buffer conumption chart, the project manager can monitor the use of the buffer and take corrective action if needed.[10] [12] The disadvantage of using this method is the risk of oversimplifying the schedule.

“Will they [the task operators] agree to shorten their duration estimates?...the behavioral aspects of identifying the precise amount of safety margin and taking it away from the task operators are dealt with only superficially....” A further concern about CCPM is the relative lack of project progress control that arises from the absence of task deadlines. An important question that remains is whether the effect of Parkinson’s Law can be mitigated or eliminated entirely without removing the control mechanism of task deadlines. Our work designs incentive mechanisms to resolve this question.

Incentive Schemes to Encourage Early Completion

There are a number of reasons why people are not interested in delivering completed work before its deadline. Chen and Hall (2021) highlight the desire to appear busy to not receive additional tasks, the desire to avoid having resources withdrawn as a result of over-performance, the natural tendency towards laziness and procrastination. They suggest incentive schemes applicable to CPM and CCPM to eliminate or mitigate Parkinson's Law. To encourage early delivery, an employee is rewarded for early completion. The schemes are designed to assure the employee works in their own interest independent of others, and thereby eliminates the potential for strategic behaviour by a group. To ensure the employee cannot fake their completion of a task, a certification of completion is provided by an independent expert. The early completion is passed on in the project, resulting in improved project performance. The schemes also encourage higher efficiency at each task level and resolves student syndrome.
The incentive schemes are easy to implement, but are not directly applicable as organisations have different approaches to performance incentives. Nonetheless, the schemes proposed provide a basis to design schemes on.

Annotated bibliography

https://www.sciencedirect.com/science/article/pii/S0377221720305476#bib0008

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 Parkinson, C. Northcote (November 19, 1955) "Parkinson’s Law", The Economist. Retrieved 13 February 2021.
  2. Editors of Encyclopaedia Britannica "C. Northcote Parkinson", Britannica. Retrieved 13 February 2021.
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Project Management Institute, Inc. (September 22, 2017). "Chapter 6: Project Schedule Management". Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute, Inc. (PMI). pp. 173–230. ISBN 978-1-5231-1232-6.
  4. Wen, T. (May 22, 2020). "The ‘law’ that explains why you can't get anything done", BBC. Retrieved 21 February 2021.
  5. Chen, B. & Hall, N. G. (June 12, 2020). "Incentive schemes for resolving Parkinson’s Law in project management". European Journal of Operational Research. 288 (20): 666–682. doi=10.1016/j.ejor.2020.06.006
  6. 6.0 6.1 Project Management Institute, Inc. (PMI) (July 8, 2019). "Chapter 2: Schedule model principles and concepts". Practice Standard for Scheduling (3rd ed.). Project Management Institute, Inc. (PMI). pp. 9–43. ISBN 978-1-5231-2398-8.
  7. Kinser, J. (2008). "The top 10 laws of project management". Paper presented at PMI® Global Congress 2008—North America, Denver, CO. Newtown Square, PA: Project Management Institute. Retrieved 21 February 2021.
  8. Roth, D. (December 12, 2009) "QUOTED OFTEN, FOLLOWED RARELY", CNN. Retrieved 21 February 2021.
  9. 9.0 9.1 Reddy, S. & Espejo, J. (2013) "Is multitasking the enemy?" PM Network, 27(2), 24–25. Retrieved 24 February 2021.
  10. 10.0 10.1 Cooper, J. (2013). Improving focus and predictability with critical chain project management. Paper presented at PMI® Global Congress 2013—North America, New Orleans, LA. Newtown Square, PA: Project Management Institute.
  11. Wen, T. (May 22, 2020). "The ‘law’ that explains why you can't get anything done", BBC. Retrieved 21 February 2021.
  12. Herroelen, W. & Leus, R. (2000). On the merits and pitfalls of critical chain scheduling. Paper presented at PMI® Research Conference 2000: Project Management Research at the Turn of the Millennium, Paris, France. Newtown Square, PA: Project Management Institute.
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox