The magic triangle as a project management tool
(→Abstract) |
(→Quality) |
||
(85 intermediate revisions by one user not shown) | |||
Line 1: | Line 1: | ||
==Abstract== | ==Abstract== | ||
− | The definition of project success to many has been limited to only three main measurement criteria popularly known as the iron triangle <ref>Atkinson, 1999 | + | The definition of project success to many has been limited to only three main measurement criteria popularly known as the iron triangle <ref>Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342.</ref>. <br>The model was introduced by Dr. Martin Barnes in 1969 and was given the name ''iron'' because the three constraints are interdependent <ref> Dr. Martin Barnes - The iron-triangle constraints of project-management.</ref>.<br> [[According to Freeman & Beale ,1992]], these are the three key pillars of the triangle and includes ''Cost'' –measured in terms of meeting the <br/>budget, ''Time'' – measured in terms of meeting the schedule, and ''Quality'' – measured in terms of meeting the requirements of the scope, adhering <br/> to functional and technical specifications, defects and reliability<ref> J.K Pinto, D.P Slevin- Critical success factors across the project lifecycle, Project Management Journal.</ref>. |
− | This article focuses on the magic triangle as a project management tool for delivering a project taking into account | + | This article focuses on the magic triangle as a project management tool for delivering a project taking into account the three key pillars, applications and limitations of this triangle in project management and some modifications by PMBOK and PMI<ref>. The Project Management Body of Knowledge (PMBOK) </ref>. |
− | <br> Based on statistics<ref> J. Wateridge - How can IS/IT projects be measured for success? , International Journal of project Management,1998. </ref>, project managers tend to focus on cost and time | + | <br> Based on statistics<ref> J. Wateridge - How can IS/IT projects be measured for success? , International Journal of project Management,1998. </ref>, project managers tend to focus on cost and time because they are the main criteria by which projects are assessed. |
− | Many consider a project as success when it is delivered under budget, time and all the requirements and quality of the project are met. | + | <br> Many consider a project as success when it is delivered under budget, time and all the requirements(scope) and quality of the project are met. |
− | This article also delves into a few type of cost estimation methods used for budgeting projects | + | <br>This article also delves into a few type of cost estimation methods used for budgeting projects. <br/>''The terms magic triangle, iron triangle and the triple of constraints are used interchangeable in this article to mean the same''. |
− | ''key words'': ''cost estimation, critical path, project success, iron/magic triangle, project management ,key performance indicators''. | + | |
+ | ''key words'': ''cost estimation, project management star, critical path, project success, iron/magic triangle, project management ,key performance indicators''. | ||
==The big idea and concept of the iron triangle== | ==The big idea and concept of the iron triangle== | ||
Line 17: | Line 18: | ||
− | The three constraints are cost, time and quality. The scope is usually located in the middle of the triangle because it is the scope that determines the three constraints such as cost, quality and time. | + | The three constraints are cost, time and quality. <ref>The scope is usually located in the middle of the triangle because it is the scope that determines the three constraints such as cost, quality and time. T Saarinen Systems development methodology and project success Information and Management, 19 (1990),pp. 183-193.</ref> |
− | The position of these three pillars depends on the original scope of the project , the purpose of the project or its desired outcome depending on the amount of resources and time available.However, it normally requires an experienced project manager to balance or adjust these three pillars to achieve the desired outcome. The iron triangle also forms the basis of the success criteria that will later be used to ascertain whether a project is a success or failure. The success criteria however goes beyond the three pillars to include other factors like safety and scope. Each of the three constraints are discussed below in a much greater detail. | + | The position of these three pillars depends on the original scope of the project , the purpose of the project or its desired outcome depending on the amount of resources and time available. However, it normally requires an experienced project manager to balance or adjust these three pillars to achieve the desired outcome. The iron triangle also forms the basis of the success criteria that will later be used to ascertain whether a project is a success or failure. The success criteria however goes beyond the three pillars to include other factors like safety and scope. Each of the three constraints are discussed below in a much greater detail. |
===Cost=== | ===Cost=== | ||
The cost of a project includes the estimated budget and resources both capital and human available for the execution of the entire project. <br> Cost is a very important factor in budgeting to achieve the desired outcome of a project delivery. The cost must be reasonably estimated because it can affect other factors such as schedule, project delivery and quality as the three constraints are interdependent. | The cost of a project includes the estimated budget and resources both capital and human available for the execution of the entire project. <br> Cost is a very important factor in budgeting to achieve the desired outcome of a project delivery. The cost must be reasonably estimated because it can affect other factors such as schedule, project delivery and quality as the three constraints are interdependent. | ||
− | The cost of defined scope of a project can be redefined depending on the scope of the project and that can affect the project quality and the | + | The cost of defined scope of a project can be redefined depending on the scope of the project and that can affect the project quality and the delivery time <ref>www.villanovau.com/resources/project-management/iron-triangle-project-management.</ref>.<br>For instance, decreasing cost will affect the project quality and likewise increasing cost. This is because the cost directly affects the resources available both human and capital for the execution of the project. |
In determining the cost of a project, its important for the project manager to consider effectively plan by considering other factors like inflation and uncertainties like unknown unknowns that can significantly delay projects and affect their critical path and delivery dates. | In determining the cost of a project, its important for the project manager to consider effectively plan by considering other factors like inflation and uncertainties like unknown unknowns that can significantly delay projects and affect their critical path and delivery dates. | ||
Project managers always try to opt for the lowest cost possible however it requires experience to balance or adjust them in order not to affect the quality of the desired outcome. | Project managers always try to opt for the lowest cost possible however it requires experience to balance or adjust them in order not to affect the quality of the desired outcome. | ||
− | <br/>Cost estimation forms the basis for budgeting and is also known as the financial constraint of the iron triangle. For instance, when the cost is increased it means more workers can be employed to speed up project delivery and capital or resources can also be increased simultaneously. Cost estimation and budgeting are very important especially in the initial phase of the project planning. | + | <br/>Cost estimation forms the basis for budgeting and is also known as the financial constraint of the iron triangle. For instance, when the cost is increased it means more workers can be employed to speed up project delivery and capital or resources can also be increased simultaneously.<br/> Cost estimation and budgeting are very important especially in the initial phase of the project planning. |
+ | |||
===Time=== | ===Time=== | ||
− | A project delivery time involves planning and scheduling and using the critical path to predict the shortest project delivery time. It is always advisable for project managers to have three options in planning and scheduling. The impossible project delivery time should be given to the stakeholder, the likely one be given to project teams and the most likely for the project manager himself. Project managers | + | A project delivery time involves planning and scheduling and using the critical path to predict the shortest project delivery time. It is always advisable for project managers to have three options in planning and scheduling. The impossible project delivery time should be given to the stakeholder, the likely one be given to project teams and the most likely for the project manager himself. Project managers normally focus on the shortest realistically possible project delivery time, however cost and uncertainties should be taken into account when planning the project delivery time without affecting the quality. |
+ | |||
===Quality=== | ===Quality=== | ||
− | Quality is the product of time and cost because these two constraints determine whether a project is a success or failure. The quality therefore determines whether the desired outcome and scope of the project are achieved or not. | + | Quality is the product of time and cost because these two constraints determine whether a project is a success or failure <ref>Encyclopedia - The iron triangle</ref>. The quality therefore determines whether the desired outcome and scope of the project are achieved or not. This extends to the requirements defined by the scope of the project. Quality delivery can be assessed as soon as the project is completed, the success however may be realized immediately or perhaps it may take many years to be able to evaluate its success or failure after the project has ended. |
The scope of a project comprises all the necessary tasks that need to be carried out to achieve the project’s overall goal. <br> Any change affecting time and cost eventually affects the scope of the project and requires experience and expertise of project managers to find the right balance between the three constraints of the iron triangle. Depending on some factors, the scope of a project can be redefined by the stakeholders, or the project manager and some adjustments can also be made to achieve the desired quality and outcome. | The scope of a project comprises all the necessary tasks that need to be carried out to achieve the project’s overall goal. <br> Any change affecting time and cost eventually affects the scope of the project and requires experience and expertise of project managers to find the right balance between the three constraints of the iron triangle. Depending on some factors, the scope of a project can be redefined by the stakeholders, or the project manager and some adjustments can also be made to achieve the desired quality and outcome. | ||
− | There two types of scope definition or goal setting in project management namely SMART and FAST goal | + | There two types of scope definition or goal setting in project management namely SMART and FAST goal settings [[https://www.workpath.com/magazine/fast-goals]].The abbreviations [[SMART]] and [[FAST]] are given below ''but this article will not focus on them''. |
F - Frequently discussed, | F - Frequently discussed, | ||
Line 47: | Line 50: | ||
==Applications of the iron triangle== | ==Applications of the iron triangle== | ||
− | + | Instead of juggling between the three constraints as suggested by a classic triple constraints, strategic choice is about giving priority to one or two of the three. Such prioritisation will help the project team to make quick decisions and focus effort on what is most relevant <ref> C. Thuesen 42430 — Project Management — lecture: Purpose - 2022</ref>. | |
− | + | ||
The iron triangle provides time and information for scheduling and prioritizing tasks to deliver the project within time and under budget. Prioritizing the most important tasks, proper scheduling, and the use of work breakdown structures like Gannt diagram and Scrum plan methods to mention but just a few in planning will provide information about the project and whether it is on tract of the project delivery time. | The iron triangle provides time and information for scheduling and prioritizing tasks to deliver the project within time and under budget. Prioritizing the most important tasks, proper scheduling, and the use of work breakdown structures like Gannt diagram and Scrum plan methods to mention but just a few in planning will provide information about the project and whether it is on tract of the project delivery time. | ||
− | Additionally, the use of stakeholder matrix, task identification and scheduling are some of the tools that can be used when it comes to time management. When these tools are effectively utilized, it will ensure that the project delivery is within the critical path. | + | <br> Additionally, the use of stakeholder matrix, task identification and scheduling are some of the tools that can be used when it comes to time management. When these tools are effectively utilized, it will ensure that the project delivery is within the critical path. |
− | + | <br> Generally, project managers opt for the shortest project delivery time known as the ''critical path'', however it is recommended to consider the following scenarios in the ''critical path analysis''. | |
− | The three scenarios are ''Most likely'', ''Optimistic'' and ''Pessimistic'' abbreviated as ''MOP''. The most likely which is based on the most realistic cost or | + | <br>The three scenarios are ''Most likely'', ''Optimistic'' and ''Pessimistic'' abbreviated as ''MOP''. The most likely which is based on the most realistic cost or delivery time should be kept by the project manager himself for reference <ref> www.copperproject.com/iron-triangle-constraints-project-management.</ref>.The Optimistic method is based on the best scenario of a project activity and this plan should be given to the project team or members. The last method called pessimistic which is based on the worst-case scenario of the project activity should be given to the stakeholders. While this is done, the project manager opts for the most likely scenario which is usually called the critical path which is defined as the shortest predicted project delivery time. |
− | Furthermore, the ''requirements of the scope'' defined by the project manager helps to meet the target. | + | <br> Furthermore, the ''requirements of the scope'' defined by the project manager helps to meet the target. When the requirements of the project are not met, it is deemed a failure. On the other hand, when all the requirements are met, and the desired outcome achieved then it is considered a success. |
− | The success of some projects can easily be determined while others that are very complex may take a longer time to get the benefits and the desired outcome. A similar scenario is the | + | The success of some projects can easily be determined while others that are very complex may take a longer time to get the benefits and the desired outcome. A similar scenario is the [[Sydney Opera House]] in Australia that took so many years to realize its quality and benefits. |
− | The quality of a project can be assessed using quality assurance by contracting third parties or the project manager who supervised the project. | + | <br>The quality of a project can be assessed using quality assurance by contracting third parties or the project manager who supervised the project.<br/>Cost estimation is used to establish the financial controls to be used throughout the lifecycle of the project to facilitate delivery within the approved budget<ref>The PMI-PMBOK standards & ISO 21500 and 21502 standards.</ref>. |
− | + | <br> The cost estimation of a project include the cost of materials and resources (including human resources) that will be available for the execution of the project. Thus, cost estimation as a ''key pillar of the iron triangle'' provides more information for planning, scheduling, and budgeting. The principle of cost estimation involves estimating each component of the planned work to be done, developing a budget, and using control techniques such as ''earned value management'' to monitor and foretell future performance of the company <ref> The constructor.org/construction/methods - cost-estimation.</ref>. <br> Budgeting and cost estimation go hand in hand, however budgeting is broader and involves using cost estimation to provide a general overview of the allocated funds available in order to spend within the budget, thus reducing overspending and embezzlement of funds.<br> | |
− | The cost estimation of a project include the cost of materials and resources (including human resources) that will be available for the execution of the project. Thus, cost estimation as a ''key pillar of the iron triangle'' provides more information for planning, scheduling, and budgeting. The principle of cost estimation involves estimating each component of the planned work to be done, developing a budget, and using control techniques such as ''earned value management'' to monitor and foretell future performance of the company <ref> The constructor.org/construction/methods - cost-estimation.</ref>. Budgeting and cost estimation go hand in hand, however budgeting is broader and involves using cost estimation to provide a general overview of the allocated funds available in order to spend within the budget, thus reducing overspending and embezzlement of funds. | + | Making estimation of costs can be a headache even to many experienced project managers.<ref>Morris, P., & Pinto, J. K. (2004). The Wiley guide to managing projects. Hoboken, NJ: John Wiley & Sons. </ref> |
− | + | I have therefore delved into a few of the most popular cost estimation methods used by project managers below. The estimation of cost is done using one or a combination of the following methods. It is also noteworthy that, there are two main methods of estimation. | |
− | + | ||
− | + | ||
− | Making estimation of costs can be a headache even to many experienced project managers. | + | |
− | I have therefore delved into a few of the most popular cost estimation methods used by project managers below. The estimation of cost is done using one | + | |
Ground up and Top down estimation methods. | Ground up and Top down estimation methods. | ||
− | • '''Analogous estimation''' - In this type of | + | • '''Analogous estimation''' - In this type of estimating costs, the project manager uses similar projects that were completed by the same |
organization to estimate the current project and by using historical data of important projects of the same profile. The analogous method can be used to estimate cost of equipment, Project overheads, travel expenses and other costs that might be incurred by contracting third party contractors to do certain works. | organization to estimate the current project and by using historical data of important projects of the same profile. The analogous method can be used to estimate cost of equipment, Project overheads, travel expenses and other costs that might be incurred by contracting third party contractors to do certain works. | ||
− | • '''Expert Judgement''' - This method is very quick, easy and requires no resources to be carried out. However, it requires experience in similar projects and the ability to foresee things. There are other estimation methods like data analysis, decision making | + | • '''Expert Judgement''' - This method is very quick, easy and requires no resources to be carried out. However, it requires experience in similar projects and the ability to foresee things. There are other estimation methods like data analysis, decision making etc. |
• '''Parametric estimation''' - Project management is the second most important competence of an engineer. | • '''Parametric estimation''' - Project management is the second most important competence of an engineer. | ||
Line 74: | Line 72: | ||
==Limitations of the iron triangle== | ==Limitations of the iron triangle== | ||
− | |||
The magic triangle despite its importance in project management has some limitations that need to be addressed.The iron triangle should be modified because of the following limitations. | The magic triangle despite its importance in project management has some limitations that need to be addressed.The iron triangle should be modified because of the following limitations. | ||
Line 88: | Line 85: | ||
'''• Cost and time estimations are uncertain and unrealistic.''' | '''• Cost and time estimations are uncertain and unrealistic.''' | ||
− | |||
Cost estimations are done when uncertainty is at its highest. Projects are full of uncertainties when estimating costs, time and the quality cannot be defined in detail. The need for flexibility is what the magic triangle is lacking. | Cost estimations are done when uncertainty is at its highest. Projects are full of uncertainties when estimating costs, time and the quality cannot be defined in detail. The need for flexibility is what the magic triangle is lacking. | ||
For instance, If the initial investment target was 80%, a reduction in quality is likely to occur because of tight unrealistic budget and time will reduce it to about 60 %. However, cost needs to be optimized to avoid over expenditure and inflation of budgets which do not match with the benefits and outcome of projects. | For instance, If the initial investment target was 80%, a reduction in quality is likely to occur because of tight unrealistic budget and time will reduce it to about 60 %. However, cost needs to be optimized to avoid over expenditure and inflation of budgets which do not match with the benefits and outcome of projects. | ||
Line 97: | Line 93: | ||
The magic triangle is too traditional and simplistic and needs to be modified to make it more reasonable. | The magic triangle is too traditional and simplistic and needs to be modified to make it more reasonable. | ||
There are many other requirements that are crucial to the successful management of projects and they are not limited to the ability to foresee and reduce uncertainty but also using the proper communication channels effectively. However, only a few modifications currently exist and they have been suggested by the PMI and PMBOK. | There are many other requirements that are crucial to the successful management of projects and they are not limited to the ability to foresee and reduce uncertainty but also using the proper communication channels effectively. However, only a few modifications currently exist and they have been suggested by the PMI and PMBOK. | ||
− | An alternative to the triple of constraints known as the project management star has been proposed by the PMBOK® Guide which has six constraints instead of three. This looks much better than traditional magic triangle because of the addition of risk but still looks incomplete. Below is a diagram of the six constraints by PMBOK®. | + | An alternative to the triple of constraints known as the ''[[project management star]]'' has been proposed by the PMBOK® Guide which has six constraints instead of three. This looks much better than traditional magic triangle because of the addition of risk but still looks incomplete. Below is a diagram of the six constraints by PMBOK®.<REF>Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342.</ref> |
[[File:Picture1.5.png|center|320x320px|frame| Project management star by PMBOK®.]] | [[File:Picture1.5.png|center|320x320px|frame| Project management star by PMBOK®.]] | ||
Line 108: | Line 104: | ||
− | The PMI model modification created space to add soft skills to the traditional iron triangle to enable the project manager facilitate communication among his team members among others. The space for soft factors are around the sides of the triangle making room for flexibility and they include the following: | + | The PMI model modification created space to add soft skills to the traditional iron triangle to enable the project manager facilitate communication among his team members among others. The space for soft factors are around the sides of the triangle, making room for flexibility and they include the following: |
1. '''''Motivational space''''' - This is also known as the ABV space and has to do with motivation of the individual such as job security, working | 1. '''''Motivational space''''' - This is also known as the ABV space and has to do with motivation of the individual such as job security, working | ||
Line 115: | Line 111: | ||
2. '''''Social space''''' - Also depicted as ACV, it has to do with punctuality, rules regarding tasks, decision making, honesty, attendance at meetings. | 2. '''''Social space''''' - Also depicted as ACV, it has to do with punctuality, rules regarding tasks, decision making, honesty, attendance at meetings. | ||
− | 3. '''''Analytic space''''' depicted as BCV. It is the serene environment available for team members to forge ties, friendships, co-operation, competition and assertiveness. This looks much better than the PMBOK model and looks set to be the future of the traditional magic triangle. | + | 3. '''''Analytic space''''' depicted as BCV. It is the serene environment available for team members to forge ties, friendships, co-operation, competition and assertiveness. This looks much better than the PMBOK model and looks set to be the future of the traditional magic triangle. The hard factors and soft factors have been illustrated in the diagram above as proposed by PMI<ref>Beyond the iron triangle: year zero. Paper presented at PMI® Global Congress 2012—EMEA, Marsailles, France. Newtown Square, PA: Project Management Institute.</ref> |
[[File:P5_05.jpg|PMI modified model of the iron triangle]] | [[File:P5_05.jpg|PMI modified model of the iron triangle]] | ||
− | == | + | <br> One way the traditional iron triangle can be effectively utilized is by prioritizing one or two of the constraints to aid in quick decision making instead of juggling between the three constraints. This suggestion does not eliminate the weaknesses of the traditional iron triangle but the modifications offered by PMI reduce the lapses in using it. |
+ | These modifications provide room that are used to identify, negotiate, mediate, and integrate diverse constraints of the project being worked on. Maintenance factors like team spirit, personal involvement, openness to teamwork belong to the individuals and task force factors like man-hours, tools, technologies, processes, and materials. <br> These soft skills have been incorporated into the triangle which the project manager will employ together with the use of hard skills such as estimation techniques, cost control, scheduling techniques and so on. | ||
+ | The hard factors differ from soft factors in that, their attributes are not only quantitative but they also have qualitative attributes. | ||
+ | |||
+ | == Annotated bibliography== | ||
+ | '''• International Project Management Association (IPMA - 2006)'''. IPMA Competence Baseline. Version 3.0. Nijkerk, The Netherlands: International Project Management Association. | ||
+ | <br> '''• Kerzner H. (2009). Project management''': A systems approach to planning, scheduling and controlling—Tenth edition. New York, NY: John Wiley & Sons. | ||
+ | <br> '''• Müller, R. & Turner, J. R. (2006)'''. Matching the project manager's leadership style to project type. International Journal of Project Management, 25(1), 21–32. | ||
+ | |||
+ | ==References== | ||
<references /> | <references /> |
Latest revision as of 22:33, 22 March 2022
Contents |
[edit] Abstract
The definition of project success to many has been limited to only three main measurement criteria popularly known as the iron triangle [1].
The model was introduced by Dr. Martin Barnes in 1969 and was given the name iron because the three constraints are interdependent [2].
According to Freeman & Beale ,1992, these are the three key pillars of the triangle and includes Cost –measured in terms of meeting the
budget, Time – measured in terms of meeting the schedule, and Quality – measured in terms of meeting the requirements of the scope, adhering
to functional and technical specifications, defects and reliability[3].
This article focuses on the magic triangle as a project management tool for delivering a project taking into account the three key pillars, applications and limitations of this triangle in project management and some modifications by PMBOK and PMI[4].
Based on statistics[5], project managers tend to focus on cost and time because they are the main criteria by which projects are assessed.
Many consider a project as success when it is delivered under budget, time and all the requirements(scope) and quality of the project are met.
This article also delves into a few type of cost estimation methods used for budgeting projects.
The terms magic triangle, iron triangle and the triple of constraints are used interchangeable in this article to mean the same.
key words: cost estimation, project management star, critical path, project success, iron/magic triangle, project management ,key performance indicators.
[edit] The big idea and concept of the iron triangle
The three constraints are cost, time and quality. [6]
The position of these three pillars depends on the original scope of the project , the purpose of the project or its desired outcome depending on the amount of resources and time available. However, it normally requires an experienced project manager to balance or adjust these three pillars to achieve the desired outcome. The iron triangle also forms the basis of the success criteria that will later be used to ascertain whether a project is a success or failure. The success criteria however goes beyond the three pillars to include other factors like safety and scope. Each of the three constraints are discussed below in a much greater detail.
[edit] Cost
The cost of a project includes the estimated budget and resources both capital and human available for the execution of the entire project.
Cost is a very important factor in budgeting to achieve the desired outcome of a project delivery. The cost must be reasonably estimated because it can affect other factors such as schedule, project delivery and quality as the three constraints are interdependent.
The cost of defined scope of a project can be redefined depending on the scope of the project and that can affect the project quality and the delivery time [7].
For instance, decreasing cost will affect the project quality and likewise increasing cost. This is because the cost directly affects the resources available both human and capital for the execution of the project.
In determining the cost of a project, its important for the project manager to consider effectively plan by considering other factors like inflation and uncertainties like unknown unknowns that can significantly delay projects and affect their critical path and delivery dates.
Project managers always try to opt for the lowest cost possible however it requires experience to balance or adjust them in order not to affect the quality of the desired outcome.
Cost estimation forms the basis for budgeting and is also known as the financial constraint of the iron triangle. For instance, when the cost is increased it means more workers can be employed to speed up project delivery and capital or resources can also be increased simultaneously.
Cost estimation and budgeting are very important especially in the initial phase of the project planning.
[edit] Time
A project delivery time involves planning and scheduling and using the critical path to predict the shortest project delivery time. It is always advisable for project managers to have three options in planning and scheduling. The impossible project delivery time should be given to the stakeholder, the likely one be given to project teams and the most likely for the project manager himself. Project managers normally focus on the shortest realistically possible project delivery time, however cost and uncertainties should be taken into account when planning the project delivery time without affecting the quality.
[edit] Quality
Quality is the product of time and cost because these two constraints determine whether a project is a success or failure [8]. The quality therefore determines whether the desired outcome and scope of the project are achieved or not. This extends to the requirements defined by the scope of the project. Quality delivery can be assessed as soon as the project is completed, the success however may be realized immediately or perhaps it may take many years to be able to evaluate its success or failure after the project has ended.
The scope of a project comprises all the necessary tasks that need to be carried out to achieve the project’s overall goal.
Any change affecting time and cost eventually affects the scope of the project and requires experience and expertise of project managers to find the right balance between the three constraints of the iron triangle. Depending on some factors, the scope of a project can be redefined by the stakeholders, or the project manager and some adjustments can also be made to achieve the desired quality and outcome.
There two types of scope definition or goal setting in project management namely SMART and FAST goal settings [[1]].The abbreviations SMART and FAST are given below but this article will not focus on them.
F - Frequently discussed, A - Ambitious S - Specific T - Transparent [ FAST ]
S - Specific M - Measurable A - Attainable R - Relevant T - Time-bound [ SMART ]
The choice of SMART or FAST goal setting method depends on the nature, complexity and long term benefits.
[edit] Applications of the iron triangle
Instead of juggling between the three constraints as suggested by a classic triple constraints, strategic choice is about giving priority to one or two of the three. Such prioritisation will help the project team to make quick decisions and focus effort on what is most relevant [9].
The iron triangle provides time and information for scheduling and prioritizing tasks to deliver the project within time and under budget. Prioritizing the most important tasks, proper scheduling, and the use of work breakdown structures like Gannt diagram and Scrum plan methods to mention but just a few in planning will provide information about the project and whether it is on tract of the project delivery time.
Additionally, the use of stakeholder matrix, task identification and scheduling are some of the tools that can be used when it comes to time management. When these tools are effectively utilized, it will ensure that the project delivery is within the critical path.
Generally, project managers opt for the shortest project delivery time known as the critical path, however it is recommended to consider the following scenarios in the critical path analysis.
The three scenarios are Most likely, Optimistic and Pessimistic abbreviated as MOP. The most likely which is based on the most realistic cost or delivery time should be kept by the project manager himself for reference [10].The Optimistic method is based on the best scenario of a project activity and this plan should be given to the project team or members. The last method called pessimistic which is based on the worst-case scenario of the project activity should be given to the stakeholders. While this is done, the project manager opts for the most likely scenario which is usually called the critical path which is defined as the shortest predicted project delivery time.
Furthermore, the requirements of the scope defined by the project manager helps to meet the target. When the requirements of the project are not met, it is deemed a failure. On the other hand, when all the requirements are met, and the desired outcome achieved then it is considered a success.
The success of some projects can easily be determined while others that are very complex may take a longer time to get the benefits and the desired outcome. A similar scenario is the Sydney Opera House in Australia that took so many years to realize its quality and benefits.
The quality of a project can be assessed using quality assurance by contracting third parties or the project manager who supervised the project.
Cost estimation is used to establish the financial controls to be used throughout the lifecycle of the project to facilitate delivery within the approved budget[11].
The cost estimation of a project include the cost of materials and resources (including human resources) that will be available for the execution of the project. Thus, cost estimation as a key pillar of the iron triangle provides more information for planning, scheduling, and budgeting. The principle of cost estimation involves estimating each component of the planned work to be done, developing a budget, and using control techniques such as earned value management to monitor and foretell future performance of the company [12].
Budgeting and cost estimation go hand in hand, however budgeting is broader and involves using cost estimation to provide a general overview of the allocated funds available in order to spend within the budget, thus reducing overspending and embezzlement of funds.
Making estimation of costs can be a headache even to many experienced project managers.[13]
I have therefore delved into a few of the most popular cost estimation methods used by project managers below. The estimation of cost is done using one or a combination of the following methods. It is also noteworthy that, there are two main methods of estimation.
Ground up and Top down estimation methods.
• Analogous estimation - In this type of estimating costs, the project manager uses similar projects that were completed by the same organization to estimate the current project and by using historical data of important projects of the same profile. The analogous method can be used to estimate cost of equipment, Project overheads, travel expenses and other costs that might be incurred by contracting third party contractors to do certain works.
• Expert Judgement - This method is very quick, easy and requires no resources to be carried out. However, it requires experience in similar projects and the ability to foresee things. There are other estimation methods like data analysis, decision making etc.
• Parametric estimation - Project management is the second most important competence of an engineer. This is where the project manager uses parameters of project data or historical data of past projects and breaks them down into smaller units for easy estimation. For instance, if we need about 100 bags of cement for a project, then what’s the cost of each bag of cement? This way, the project manager can easily estimate the cost of the entire project. This method also involves the use of modern software like Agile to facilitate operations and compare statistical data.
[edit] Limitations of the iron triangle
The magic triangle despite its importance in project management has some limitations that need to be addressed.The iron triangle should be modified because of the following limitations.
• Wrong measurements (particularly baseline). First of all, the perception that the triple of constraints ensure on time delivery ,on budget and project quality is not entirely true and the actual scope of the project cannot be limited to only these as it tends to affect project success in general. The concept of this iron triangle is too traditional and simplistic because the scope of complex projects evolve with time and circumstances.
• The iron triangle is incomplete because other important factors like safety, benefits, etc are ignored. The magic triangle is only used as a tool for the execution of a project but cannot be used to ascertain the success of a project. The triangle should be modified to include other tools that are used by management.
• The iron triangle undermines the overall Investment and focus of projects [14]
Projects exist not to be delivered on time, cost and quality but to add value to the society. Thus it undermines the investment goals and focus of projects. Projects are designed to serve a particular purpose and so when the cost and project delivery time is manipulated, it affects the actual purpose of the project. Attempts by project teams to target project delivery at the expense of the desired outcome and long-term benefits affect the detailed plan and scope of the project leading to some portions of the benefits being left out. What project managers and stakeholders should rather consider is that, the project should be able to achieve the goal for which it was planned and whether the project was completed on budget or on time should be a secondary matter.
• Cost and time estimations are uncertain and unrealistic. Cost estimations are done when uncertainty is at its highest. Projects are full of uncertainties when estimating costs, time and the quality cannot be defined in detail. The need for flexibility is what the magic triangle is lacking. For instance, If the initial investment target was 80%, a reduction in quality is likely to occur because of tight unrealistic budget and time will reduce it to about 60 %. However, cost needs to be optimized to avoid over expenditure and inflation of budgets which do not match with the benefits and outcome of projects.
[edit] Modification of the Iron triangle
The magic triangle is too traditional and simplistic and needs to be modified to make it more reasonable. There are many other requirements that are crucial to the successful management of projects and they are not limited to the ability to foresee and reduce uncertainty but also using the proper communication channels effectively. However, only a few modifications currently exist and they have been suggested by the PMI and PMBOK. An alternative to the triple of constraints known as the project management star has been proposed by the PMBOK® Guide which has six constraints instead of three. This looks much better than traditional magic triangle because of the addition of risk but still looks incomplete. Below is a diagram of the six constraints by PMBOK®.[15]
[16] The major cause of unsuccessful projects is poor communication (about 28%) and among others as illustrated in the bar chart below as opposed to the limited triple of constraints used to ascertain project success.
Instead of limiting the magic triangle to only cost, time and quality, there should be room for some factors like communication, risks etc.
The PMI model modification created space to add soft skills to the traditional iron triangle to enable the project manager facilitate communication among his team members among others. The space for soft factors are around the sides of the triangle, making room for flexibility and they include the following:
1. Motivational space - This is also known as the ABV space and has to do with motivation of the individual such as job security, working conditions, reward systems.
2. Social space - Also depicted as ACV, it has to do with punctuality, rules regarding tasks, decision making, honesty, attendance at meetings.
3. Analytic space depicted as BCV. It is the serene environment available for team members to forge ties, friendships, co-operation, competition and assertiveness. This looks much better than the PMBOK model and looks set to be the future of the traditional magic triangle. The hard factors and soft factors have been illustrated in the diagram above as proposed by PMI[17]
One way the traditional iron triangle can be effectively utilized is by prioritizing one or two of the constraints to aid in quick decision making instead of juggling between the three constraints. This suggestion does not eliminate the weaknesses of the traditional iron triangle but the modifications offered by PMI reduce the lapses in using it.
These modifications provide room that are used to identify, negotiate, mediate, and integrate diverse constraints of the project being worked on. Maintenance factors like team spirit, personal involvement, openness to teamwork belong to the individuals and task force factors like man-hours, tools, technologies, processes, and materials.
These soft skills have been incorporated into the triangle which the project manager will employ together with the use of hard skills such as estimation techniques, cost control, scheduling techniques and so on.
The hard factors differ from soft factors in that, their attributes are not only quantitative but they also have qualitative attributes.
[edit] Annotated bibliography
• International Project Management Association (IPMA - 2006). IPMA Competence Baseline. Version 3.0. Nijkerk, The Netherlands: International Project Management Association.
• Kerzner H. (2009). Project management: A systems approach to planning, scheduling and controlling—Tenth edition. New York, NY: John Wiley & Sons.
• Müller, R. & Turner, J. R. (2006). Matching the project manager's leadership style to project type. International Journal of Project Management, 25(1), 21–32.
[edit] References
- ↑ Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342.
- ↑ Dr. Martin Barnes - The iron-triangle constraints of project-management.
- ↑ J.K Pinto, D.P Slevin- Critical success factors across the project lifecycle, Project Management Journal.
- ↑ . The Project Management Body of Knowledge (PMBOK)
- ↑ J. Wateridge - How can IS/IT projects be measured for success? , International Journal of project Management,1998.
- ↑ The scope is usually located in the middle of the triangle because it is the scope that determines the three constraints such as cost, quality and time. T Saarinen Systems development methodology and project success Information and Management, 19 (1990),pp. 183-193.
- ↑ www.villanovau.com/resources/project-management/iron-triangle-project-management.
- ↑ Encyclopedia - The iron triangle
- ↑ C. Thuesen 42430 — Project Management — lecture: Purpose - 2022
- ↑ www.copperproject.com/iron-triangle-constraints-project-management.
- ↑ The PMI-PMBOK standards & ISO 21500 and 21502 standards.
- ↑ The constructor.org/construction/methods - cost-estimation.
- ↑ Morris, P., & Pinto, J. K. (2004). The Wiley guide to managing projects. Hoboken, NJ: John Wiley & Sons.
- ↑ Project Manager - Ways the iron triangle destroys Project success.
- ↑ Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337–342.
- ↑ A de Wit - Measurement of project management success, International Journal of Project Management, 6 (3) (1988), pp. 164-170.
- ↑ Beyond the iron triangle: year zero. Paper presented at PMI® Global Congress 2012—EMEA, Marsailles, France. Newtown Square, PA: Project Management Institute.