Work Break Down Structure(WBS)

From apppm
(Difference between revisions)
Jump to: navigation, search
(The WBS on a port construction project under risk)
(Limitations of WBS)
 
(73 intermediate revisions by one user not shown)
Line 12: Line 12:
 
*Work: tasks that can produce tangible results;
 
*Work: tasks that can produce tangible results;
 
*Breakdown: a hierarchical structure of progressive subdivision and classification;
 
*Breakdown: a hierarchical structure of progressive subdivision and classification;
*Structure: organization of the sections according to a certain pattern.
+
*Structure: organization of the sections according to a certain pattern.<ref name="two"/>
  
 
===Types of WBS===
 
===Types of WBS===
Here are three main types of WBS: 1) Deliverable-Based, 2) Phase-Based and
+
Here are three main types of WBS: 1) Deliverable-Based, 2) Phase-Based and<ref name="one"/>
3) Responsibility-Based. And the main difference between the two approaches are the elements identified in the first level of WBS.
+
3) Responsibility-Based<ref name="two"/>. And the main difference between the two approaches are the elements identified in the first level of WBS.
  
 
*A deliverable-based work breakdown structure clearly demonstrates the relationship between the project deliverables (i.e., products, services, or results) and the scope (i.e., work to be executed). From figure 1(a), the level 1 elements are summary deliverable descriptions, while level 2 elements in each leg of the WBS are all the unique deliverables required to create the respective level 1 deliverable.
 
*A deliverable-based work breakdown structure clearly demonstrates the relationship between the project deliverables (i.e., products, services, or results) and the scope (i.e., work to be executed). From figure 1(a), the level 1 elements are summary deliverable descriptions, while level 2 elements in each leg of the WBS are all the unique deliverables required to create the respective level 1 deliverable.
[[File:Figure 1(a).png|500px|thumb|center|Figure 1(a):A structure of Deliverable-Based WBS]]
+
[[File:Figure 1(a).png|500px|thumb|center|Figure 1(a):A structure of Deliverable-Based WBS<ref name="two"/>]]
  
 
*A phase-based WBS clearly demonstrates the process of a project. From figure 1 (b), each element of level 1 is typical phases of a project, while the level 2 elements are the unique deliverables in each phase. This kind of WBS type requires work associated with multiple elements be divided into the work unique to each level 1 element.
 
*A phase-based WBS clearly demonstrates the process of a project. From figure 1 (b), each element of level 1 is typical phases of a project, while the level 2 elements are the unique deliverables in each phase. This kind of WBS type requires work associated with multiple elements be divided into the work unique to each level 1 element.
[[File:Figure 1(b).png|500px|thumb|center|Figure 1(b):A structure of Phase-Based WBS]]
+
[[File:Figure 1(b).png|500px|thumb|center|Figure 1(b):A structure of Phase-Based WBS<ref name="two"/>]]
  
 
*A responsibility- based WBS clearly defines project activities based on the organization units that will work on the project. This structure allows the responsibilities involved in the project management process to be assigned to each member.
 
*A responsibility- based WBS clearly defines project activities based on the organization units that will work on the project. This structure allows the responsibilities involved in the project management process to be assigned to each member.
[[File:Figure 1(c).png|500px|thumb|center|Figure 1(c):A structure of Responsibility-Based WBS]]
+
[[File:Figure 1(c).png|500px|thumb|center|Figure 1(c):A structure of Responsibility-Based WBS<ref name="two"/>]]
  
 
===Features of WBS===
 
===Features of WBS===
Line 34: Line 34:
  
 
===Importance of WBS===
 
===Importance of WBS===
In the execution of the project, there will be found a variety of problems that will lead to disadvantageous impacts on the project target. Many factors lead to several project stumbling blocks, such as over budget, delayed projects, poor quality, and rework. These problems affect the project objectives of cost, quality, and time of project[3]. A constructed WBS can result in the following outcomes:
+
In the execution of the project, there will be found a variety of problems that will lead to disadvantageous impacts on the project target. Many factors lead to several project stumbling blocks, such as over budget, delayed projects, poor quality, and rework. These problems affect the project objectives of cost, quality, and time of project<ref name="three"/>. A constructed WBS can result in the following outcomes:
 
# Clear work assignments, goals, objectives, and deliverables.
 
# Clear work assignments, goals, objectives, and deliverables.
 
# Scope can be fixed and manageable.
 
# Scope can be fixed and manageable.
Line 41: Line 41:
  
 
==Preparation methods of creating a WBS==
 
==Preparation methods of creating a WBS==
When creating a WBS, here are several methods that can be used for creating a WBS. These included outlines and organization charts, fishbone, and brainstorming techniques, top-down and bottom-up development strategies. And WBS templates are available and corporate guidelines or standards can be referenced or copied for quick-starting WBS development[6].
+
When creating a WBS, here are several methods that can be used for creating a WBS. These included outlines and organization charts, fishbone, and brainstorming techniques, top-down and bottom-up development strategies. And WBS templates are available and corporate guidelines or standards can be referenced or copied for quick-starting WBS development <ref name="seven"/>.
  
 
It should be based on the specific project aim, requirements, assumptions, and constraints to choose an appropriate method. The following table highlights some advantages and disadvantages of the above-mentioned methods.
 
It should be based on the specific project aim, requirements, assumptions, and constraints to choose an appropriate method. The following table highlights some advantages and disadvantages of the above-mentioned methods.
Line 106: Line 106:
 
===WBS standards and templates===
 
===WBS standards and templates===
 
In general, if WBS standards or WBS templates are available, they should be used. There are many samples WBSs in the literature, but care must be taken when choosing to use a sample WBS as a template. Organizations can have WBS templates for very similar projects and are highly encouraged to use these templates. However, if the project is very different from other projects in the organization and no template seems applicable, then develop the WBS "from scratch" using a top-down approach.
 
In general, if WBS standards or WBS templates are available, they should be used. There are many samples WBSs in the literature, but care must be taken when choosing to use a sample WBS as a template. Organizations can have WBS templates for very similar projects and are highly encouraged to use these templates. However, if the project is very different from other projects in the organization and no template seems applicable, then develop the WBS "from scratch" using a top-down approach.
Regardless of the method chosen to prepare the WBS, the resulting WBS must have all the core characteristics of a high-quality WBS. the WBS must describe 100% of the project's work, must be oriented toward deliverables rather than activities, and must be hierarchically arranged.
+
Regardless of the method chosen to prepare the WBS, the resulting WBS must have all the core characteristics of a high-quality WBS. the WBS must describe 100% of the project's work, must be oriented toward deliverables rather than activities, and must be hierarchically arranged.<ref name="six"/>
  
 
==Application of WBS==
 
==Application of WBS==
 
===The WBS in the project management===
 
===The WBS in the project management===
 
====The process of project management with WBS====
 
====The process of project management with WBS====
Project management is a continue process. It focuses on achieving the project objectives within the project management triad of performance, constraints and goals[2]. Here are five types of activities included in the project management process: initiation, planning, execution, controlling and closing (see figure 3.1). This illustration emphasizes the importance of planning before extensive project work and the importance of bringing the project to closure once all the work done.
+
Project management is a continue process. It focuses on achieving the project objectives within the project management triad of performance, constraints and goals<ref name="two"/>. Here are five types of activities included in the project management process: initiation, planning, execution, controlling and closing (see figure 3.1)<ref name="three"/>. This illustration emphasizes the importance of planning before extensive project work and the importance of bringing the project to closure once all the work done.
[[File:Figure 3.1.png|500px|thumb|right|Figure 3.1:the project management process]]
+
[[File:Figure 3.1.png|500px|thumb|right|Figure 3.1:the project management process<ref name="three"/>]]
  
 
The WBS is a critical element in the planning and execution of a successful project. Many projects cost, schedule, and quality failures can be traced directly to flaws in the development of the project’s WBS. It is highly unlikely that a project will be successful without the existence of a quality WBS. In contrast, developing and applying a quality WBS will significantly increase the likelihood of successful project completion.
 
The WBS is a critical element in the planning and execution of a successful project. Many projects cost, schedule, and quality failures can be traced directly to flaws in the development of the project’s WBS. It is highly unlikely that a project will be successful without the existence of a quality WBS. In contrast, developing and applying a quality WBS will significantly increase the likelihood of successful project completion.
Line 154: Line 154:
 
===The WBS and PFMEA in closed loop management===
 
===The WBS and PFMEA in closed loop management===
 
====The concept of PFMEA====
 
====The concept of PFMEA====
Failure models and effects analysis (PFMEA) is an effective model for ensuring a high reliability[5].. It is used for analyzing potential failure modes and their effects, finding the corresponding root causes, and providing measures to prevent failures in the life cycle of a product. PFMEA is a systematical management method used to improve the process reliability[4].
+
Failure models and effects analysis (PFMEA) is an effective model for ensuring a high reliability<ref name="five"/>. It is used for analyzing potential failure modes and their effects, finding the corresponding root causes, and providing measures to prevent failures in the life cycle of a product. PFMEA is a systematical management method used to improve the process reliability<ref name="four"/>
  
 
====PFMEA combined with WBS====
 
====PFMEA combined with WBS====
Line 165: Line 165:
 
The general PFMEA worksheet included the following elements:  
 
The general PFMEA worksheet included the following elements:  
 
Function, Failure mode, Cause, Effect, Detection, Occurrence, Severity, RPN threshold, Action.
 
Function, Failure mode, Cause, Effect, Detection, Occurrence, Severity, RPN threshold, Action.
[[File:Figure 3.2.png|thumb|right|Figure 3.2: PFMEA combined with WBS]]
+
[[File:Figure 3.2.png|thumb|400px|right|Figure 3.2: PFMEA combined with WBS<ref name="six"/>]]
  
 
The combination of PFMEA and WBS is the process of breaking down the preventive and control measures proposed in the PFMEA into top-down and bottom-up components for measure management purposes, using tools such as the WBS. Each improvement measure proposed in PFMEA table for a failure mode can be regarded as a project.  
 
The combination of PFMEA and WBS is the process of breaking down the preventive and control measures proposed in the PFMEA into top-down and bottom-up components for measure management purposes, using tools such as the WBS. Each improvement measure proposed in PFMEA table for a failure mode can be regarded as a project.  
  
Apply WBS to decompose it into work units, in turn allocate to the corresponding departments. Lebel these distribution results to form a work schedule finally. Monitor the implementation of measures to ensure that the measures are carried out based on the work schedule[4].
+
Apply WBS to decompose it into work units, in turn allocate to the corresponding departments. Lebel these distribution results to form a work schedule finally. Monitor the implementation of measures to ensure that the measures are carried out based on the work schedule.<ref name= "three"/>
  
 
Take a core production of turboshaft engine as an example to illustrate the application in the manufacture process and quality control of the methods combined WBS with in PFMEA. The steps are as following:
 
Take a core production of turboshaft engine as an example to illustrate the application in the manufacture process and quality control of the methods combined WBS with in PFMEA. The steps are as following:
Line 176: Line 176:
 
#The team invited related experts to review previous PFMEA work.
 
#The team invited related experts to review previous PFMEA work.
 
#Persons in charge took actions in accordance with WBS of control measures to improve the process reliability.
 
#Persons in charge took actions in accordance with WBS of control measures to improve the process reliability.
#The measures was taken effectively and the process reliability was indeed improved[4].
+
#The measures was taken effectively and the process reliability was indeed improved<ref  name= "four"/>
  
[[File:Figure 3.3.png|thumb|500px|center|Figure 3.3: WBS-PFMEA form of core production]]
+
[[File:Figure 3.3.png|thumb|500px|center|Figure 3.3: WBS-PFMEA form of core production<ref name="six"/>]]
  
 
Seen from the figure 3.3, it is an example for a core production. This method can be meet the practical manufacturing process need better.
 
Seen from the figure 3.3, it is an example for a core production. This method can be meet the practical manufacturing process need better.
Line 186: Line 186:
  
 
Then the level 1 will be divided into work package, and the work package will be divided      into activities and resources.
 
Then the level 1 will be divided into work package, and the work package will be divided      into activities and resources.
[[File:Figure 3.4.png|400px|thumb|center|Figure 3.4: WBS on a specific construction project]]
+
[[File:Figure 3.4.png|500px|thumb|center|Figure 3.4: WBS on a specific construction project<ref name="three"/>]]
 
Identification of risk to the port construction project that may affect cost performance derived from literature studies, and the risk score can be calculated by:
 
Identification of risk to the port construction project that may affect cost performance derived from literature studies, and the risk score can be calculated by:
R=P*I
+
<br />R=P*I
----
+
<br />Where R=Risk Factor, P=Probability and I=Impact.
Where R=Risk Factor, P=Probability and I=Impact
+
  
 
And based on the survey of respondents, there are several risk events:
 
And based on the survey of respondents, there are several risk events:
Line 202: Line 201:
 
#The price of material purchased exceeds estimates in planning
 
#The price of material purchased exceeds estimates in planning
 
#Procurement of labor for implementation is not in accordance with needs
 
#Procurement of labor for implementation is not in accordance with needs
#Tides occur[7]
+
#Tides occur<ref name="seven"/>
  
 
Engineering project risk identification is a particularly complex process, and using        general risk identification methods to identify risk factors that exist during the implementation of engineering projects would be costly in terms of manpower and time, and would affect the balance of risk management benefits and costs.
 
Engineering project risk identification is a particularly complex process, and using        general risk identification methods to identify risk factors that exist during the implementation of engineering projects would be costly in terms of manpower and time, and would affect the balance of risk management benefits and costs.
  
 
The WBS decomposition method, as an important method in engineering project management, is commonly used in engineering project management. A project using the WBS decomposition method will have a complete project flow chart, schedule, cost plan and personnel plan, which will provide sufficient information for project risk identification.
 
The WBS decomposition method, as an important method in engineering project management, is commonly used in engineering project management. A project using the WBS decomposition method will have a complete project flow chart, schedule, cost plan and personnel plan, which will provide sufficient information for project risk identification.
 +
 +
==Limitations of WBS==
 +
Despite having so many benefits of a work breakdown structure, there are a few cons that come with the work breakdown structure. Keep reading this section to find out what are the possibilities and how we can find a solution for them. After all, it is not a large and comprehensive breakdown structure covering the entire project, and many key project information cannot be fully represented in the WBS.  Since we mainly present the "deliverables" of the project, our actual implementation is often trapped in detail, and we do not put it into the project to systematically view its relationship. It is far less used than project activities and progress documents, which are often shelved and reduced to work memos.
 +
Here are some uninventable limitations of WBS.<ref name="seven"/>
 +
 +
===The orientation may be changed ===
 +
The structure of the work breakdown can be the result of a directional rather than a prescriptive approach. Approaches may change, but program outcomes will not. Deliverables or planned results must never be tightly coupled with other methods and actions.
 +
 +
===The details may be wrong===
 +
It is hard to find the best and most accurate level of details when it comes to WBS. Since you must fit just one on the page, it will become extremely difficult to find what exactly the tasks are and what must be the creation of them added to the WBS.This may lead to the creation of useless and vague tasks under which you will have a list of non-similar tasks.
  
 
==Annotated Bibliography==
 
==Annotated Bibliography==
Line 213: Line 222:
  
 
==References==
 
==References==
 +
<references>
  
<references/>
+
<ref name="one"> https://www.workbreakdownstructure.com</ref>
 
+
<ref name="two"> Haugan G T. Effective work breakdown structures[M]. Berrett-Koehler Publishers, 2001. https://www.bkconnection.com/books/title/Effective-Work-Breakdown-Structures </ref>
<ref name="R1"> https://www.workbreakdownstructure.com <ref/>
+
<ref name="three">J T Amin et al 2020 IOP Conf. Ser.: Mater. Sci. Eng. 930 012006.</ref>
 +
<ref name="four">J. Xue and M. Huang, "Closed loop management of PFMEA combined with WBS," 2016 Chinese Control and Decision Conference (CCDC), Yinchuan, China, 2016, pp. 4003-4008.</ref>
 +
<ref name="five"> Z.G. Liu, F. Q. Li. Process FMEA Applied Research, Quality and Reliability, 42-45+48, 2005. </ref>
 +
<ref name="six"> Qiang Maoshan, Chen Ping, Project Management Institute. Work Breakdown Structure (WBS) Implementation Standard [M]. Electronic Industry Press, 2008</ref>
 +
<ref name="seven"> Citra Pradipta Hudoyo et al 2019 IOP Conf. Ser.: Earth Environ. Sci. 258 012051 https://iopscience.iop.org/article/10.1088/1755-1315/258/1/012051</ref>

Latest revision as of 10:50, 10 May 2023

"Developed by Qian Xiao“

Contents

[edit] Abstract

Work break down structure is a project management tool that breaking down complex project into phases, deliverables and work packages. A WBS can integrate scope, cost and deliverables into a single tool and provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. The following article aims to provide an overview of the basic concepts of WBS, the preparation of creating a WBS, and discussing the three different use cases with WBS, finally analysis the limitations of using WBS.

[edit] Introductions of WBS

Work break down structure (WBS) is defined as: "Deliverable oriented hierarchical decomposition of the work to be executed by the project time to accomplish the project objectives and create the required deliverables.” by the Project Management Institute (PMI). For project, it is one of the most important project management tools that integrates scope, cost and schedule baselines ensuring that project plans are in alignment. And the project can be planned, executed, controlled, monitored, and reported effectively with this tool.

[edit] Elements of WBS

Work break down structure is made up of three elements, which are work, breakdown and structure.

  • Work: tasks that can produce tangible results;
  • Breakdown: a hierarchical structure of progressive subdivision and classification;
  • Structure: organization of the sections according to a certain pattern.[1]

[edit] Types of WBS

Here are three main types of WBS: 1) Deliverable-Based, 2) Phase-Based and[2] 3) Responsibility-Based[1]. And the main difference between the two approaches are the elements identified in the first level of WBS.

  • A deliverable-based work breakdown structure clearly demonstrates the relationship between the project deliverables (i.e., products, services, or results) and the scope (i.e., work to be executed). From figure 1(a), the level 1 elements are summary deliverable descriptions, while level 2 elements in each leg of the WBS are all the unique deliverables required to create the respective level 1 deliverable.
Figure 1(a):A structure of Deliverable-Based WBS[1]
  • A phase-based WBS clearly demonstrates the process of a project. From figure 1 (b), each element of level 1 is typical phases of a project, while the level 2 elements are the unique deliverables in each phase. This kind of WBS type requires work associated with multiple elements be divided into the work unique to each level 1 element.
Figure 1(b):A structure of Phase-Based WBS[1]
  • A responsibility- based WBS clearly defines project activities based on the organization units that will work on the project. This structure allows the responsibilities involved in the project management process to be assigned to each member.
Figure 1(c):A structure of Responsibility-Based WBS[1]

[edit] Features of WBS

The WBS represents a specific description of the project deliverables and scope. It is not a statement of how or when the deliverables will be produced, but rather a refinement and description of the project outputs and scope. It has the following features:

  • Supporting the definition of all work required to achieve outputs, objectives, deliverables, or specific outcomes.
  • The hierarchical structure used to describe and define the deliverables, and which is established in a “parent-child” relationship.
  • Having an objective or specific result, which is known as a deliverable or output.

[edit] Importance of WBS

In the execution of the project, there will be found a variety of problems that will lead to disadvantageous impacts on the project target. Many factors lead to several project stumbling blocks, such as over budget, delayed projects, poor quality, and rework. These problems affect the project objectives of cost, quality, and time of project[3]. A constructed WBS can result in the following outcomes:

  1. Clear work assignments, goals, objectives, and deliverables.
  2. Scope can be fixed and manageable.
  3. Budget can be under control.
  4. Deadline can be meet.

[edit] Preparation methods of creating a WBS

When creating a WBS, here are several methods that can be used for creating a WBS. These included outlines and organization charts, fishbone, and brainstorming techniques, top-down and bottom-up development strategies. And WBS templates are available and corporate guidelines or standards can be referenced or copied for quick-starting WBS development [4].

It should be based on the specific project aim, requirements, assumptions, and constraints to choose an appropriate method. The following table highlights some advantages and disadvantages of the above-mentioned methods.

Table1 WBS creation methods
WBS creation method Advantages Challenges
Top-down
  • Convenient status reporting for structural items
  • Ensure the logical structure of the project
  • Whether there is value in brainstorming/discovering project deliverables
  • Can accommodate additional deliverables as they are discovered
  • Need constant attention, don't neglect any work package
  • The WBS needs to be refined to a level of detail enough to allow for management
Bottom up
  • Start with all deliverables and work backwards into the project
  • Verify that the body of the identified work package is included
  • Identify all deliverables before making the WBS
  • Does ensuring that work packages are logically grouped
  • Lose focus on the big picture
WBS standards
  • Format predefinition
  • Enhances consistency across project WBS
  • Conforming a project to standards may result in the inclusion of unnecessary deliverables or failure to include project-specific deliverables
  • Not all projects conform to highly structured WBS standards
WBS template
  • Provides a starting point for creating WBS
  • Predetermining the level of detail
  • Enhances consistency across project WBS
  • Require projects to meet standards
  • Whether results in the inclusion of unnecessary deliverables or failure to include project-specific deliverables
  • Not all projects are suitable for a highly structured set of WBS templates

When developing the WBS, the project management team first needs to decide which development method to use. The choice of a top-down or bottom-up approach is to some extent a personal choice and may depend on the habits and mindset of the project team, as well as organizational practices. In addition to these considerations, some guidelines and explanations as to which approach may be more appropriate.

[edit] Top-down: Use a top-down approach in these situations

Project managers and project management teams have little to no experience in developing WBS. Top-down development allows for a step-by-step understanding and elaboration of the WBS.

The nature of the project's product or service is not well understood. When the scope and nature of the project is not clear, a top-down approach to developing the WBS with all stakeholders helps to gain understanding and consensus. The nature of the project lifecycle is unfamiliar or not well understood. Top-down development of the WBS is more likely to identify lifecycle issues and characteristics. There is no appropriate WBS template available. When developing a WBS "from the ground up", it is much easier to start with the overall project deliverables, such as building a bicycle, and then iterate to identify sub-elements.

[edit] Bottom-up: A bottom-up approach is used in these situations

The nature of the project's product or service is well understood. For example, if the organization has developed a very similar product or service in a previous project, the project team may already have a very good understanding of all the interim deliverables required for the new project. The nature of the project lifecycle is well known, and if the organization always uses the same project lifecycle, then the interim deliverables for that lifecycle are well known and can be used to begin bottom-up WBS development. There are appropriate WBS templates. If the organization has WBSs from similar product or service projects and these WBSs can be reused, then the bottom-up approach is the same.

[edit] WBS standards and templates

In general, if WBS standards or WBS templates are available, they should be used. There are many samples WBSs in the literature, but care must be taken when choosing to use a sample WBS as a template. Organizations can have WBS templates for very similar projects and are highly encouraged to use these templates. However, if the project is very different from other projects in the organization and no template seems applicable, then develop the WBS "from scratch" using a top-down approach. Regardless of the method chosen to prepare the WBS, the resulting WBS must have all the core characteristics of a high-quality WBS. the WBS must describe 100% of the project's work, must be oriented toward deliverables rather than activities, and must be hierarchically arranged.[5]

[edit] Application of WBS

[edit] The WBS in the project management

[edit] The process of project management with WBS

Project management is a continue process. It focuses on achieving the project objectives within the project management triad of performance, constraints and goals[1]. Here are five types of activities included in the project management process: initiation, planning, execution, controlling and closing (see figure 3.1)[3]. This illustration emphasizes the importance of planning before extensive project work and the importance of bringing the project to closure once all the work done.

Figure 3.1:the project management process[3]

The WBS is a critical element in the planning and execution of a successful project. Many projects cost, schedule, and quality failures can be traced directly to flaws in the development of the project’s WBS. It is highly unlikely that a project will be successful without the existence of a quality WBS. In contrast, developing and applying a quality WBS will significantly increase the likelihood of successful project completion.

Table 2 the project management process combined with WBS
Process Importance of WBS in process
Initiating
  • Develop preliminary project scope statement

Historical WBS elements can contribute in determining the scope and viability of projects.

Planning
  • Scope planning: the scope planning process documents how the WBS will be created and defined.
  • Scope definition: the WBS further defines the entire scope of the project.
  • Activity definition: the WBS is an input source to this process and is a key component of a project plan.
  • Human resource planning
  • Cost budgeting
  • Risk identification: the WBS identifies project deliverables that must be evaluate for risk events.
  • Risk response planning: the WBS might be updated to include work and deliverables required for risk management.
  • Plan purchases and acquisition
Executing
  • Information distribution: the WBS provides the basis for developing the communications plan and the level of granularity at which project information can be distributed. the WBS helps determine what level of project detail is appropriate to communicate to different stakeholders groups.
Controlling
  • Scope control: the WBS is an input source to this process, which is a key component of a project plan. It is important to adjust the WBS if project scope is changed so that future changes will be based on an updated, agreed-upon project baseline. A WBS enhance the project manager’s ability to assess the impact of scope changes.
  • Cost control: the creation of the WBS reveals the best point in the hierarchy of deliverables at which to implement cost control.

[edit] The WBS and PFMEA in closed loop management

[edit] The concept of PFMEA

Failure models and effects analysis (PFMEA) is an effective model for ensuring a high reliability[6]. It is used for analyzing potential failure modes and their effects, finding the corresponding root causes, and providing measures to prevent failures in the life cycle of a product. PFMEA is a systematical management method used to improve the process reliability[7]

[edit] PFMEA combined with WBS

To actualize PFMEA management scientifically, normatively, systematically, and effectively, it is necessary to decompose the PFMEA project. And to guarantee the effectiveness of measures by decomposing work. Into smaller specific tasks, work breakdown structure and PFMEA are combined.

[edit] Purpose of the combination

The purpose of this combination is to decompose the improvement measures into work units or work packages. It is convenient for management and supervision. What is more, another purpose is reflecting the technical relation, organisational relation, resource relation and workflow.

[edit] Process of the combination in closed loop management

The general PFMEA worksheet included the following elements: Function, Failure mode, Cause, Effect, Detection, Occurrence, Severity, RPN threshold, Action.

Figure 3.2: PFMEA combined with WBS[5]

The combination of PFMEA and WBS is the process of breaking down the preventive and control measures proposed in the PFMEA into top-down and bottom-up components for measure management purposes, using tools such as the WBS. Each improvement measure proposed in PFMEA table for a failure mode can be regarded as a project.

Apply WBS to decompose it into work units, in turn allocate to the corresponding departments. Lebel these distribution results to form a work schedule finally. Monitor the implementation of measures to ensure that the measures are carried out based on the work schedule.[3]

Take a core production of turboshaft engine as an example to illustrate the application in the manufacture process and quality control of the methods combined WBS with in PFMEA. The steps are as following:

  1. Organizing a special PFMEA work team to take charge the whole work. The group leader was responsible for determining and coordinating the PFMEA projects, directors in charge of determining working steps and formulating corrective actions to the problems in the product manufacturing process, other personnel also took part in the implementation of the project.
  2. The team discussed the process of the core production and fill the result in the table 2.
  3. The team invited related experts to review previous PFMEA work.
  4. Persons in charge took actions in accordance with WBS of control measures to improve the process reliability.
  5. The measures was taken effectively and the process reliability was indeed improved[7]
Figure 3.3: WBS-PFMEA form of core production[5]

Seen from the figure 3.3, it is an example for a core production. This method can be meet the practical manufacturing process need better.

[edit] The WBS on a port construction project under risk

The port project can be divided into 9 elements: preliminaries, dock, trestle, dredging, causeway, container yard, facility buildings, mechanical electrical, and breakwater, all of these can be considered as main project and became WBS level 1.

Then the level 1 will be divided into work package, and the work package will be divided into activities and resources.

Figure 3.4: WBS on a specific construction project[3]

Identification of risk to the port construction project that may affect cost performance derived from literature studies, and the risk score can be calculated by:
R=P*I
Where R=Risk Factor, P=Probability and I=Impact.

And based on the survey of respondents, there are several risk events:

  1. High sea waves
  2. Material usage exceeds the required volume
  3. Qualifying labor is not according to plan
  4. Error of equipment productivity estimates
  5. Error calculate the volume of work
  6. Underwater conditions differ from the assumption of tenders
  7. Error predicting weather and events
  8. The price of material purchased exceeds estimates in planning
  9. Procurement of labor for implementation is not in accordance with needs
  10. Tides occur[4]

Engineering project risk identification is a particularly complex process, and using general risk identification methods to identify risk factors that exist during the implementation of engineering projects would be costly in terms of manpower and time, and would affect the balance of risk management benefits and costs.

The WBS decomposition method, as an important method in engineering project management, is commonly used in engineering project management. A project using the WBS decomposition method will have a complete project flow chart, schedule, cost plan and personnel plan, which will provide sufficient information for project risk identification.

[edit] Limitations of WBS

Despite having so many benefits of a work breakdown structure, there are a few cons that come with the work breakdown structure. Keep reading this section to find out what are the possibilities and how we can find a solution for them. After all, it is not a large and comprehensive breakdown structure covering the entire project, and many key project information cannot be fully represented in the WBS. Since we mainly present the "deliverables" of the project, our actual implementation is often trapped in detail, and we do not put it into the project to systematically view its relationship. It is far less used than project activities and progress documents, which are often shelved and reduced to work memos. Here are some uninventable limitations of WBS.[4]

[edit] The orientation may be changed

The structure of the work breakdown can be the result of a directional rather than a prescriptive approach. Approaches may change, but program outcomes will not. Deliverables or planned results must never be tightly coupled with other methods and actions.

[edit] The details may be wrong

It is hard to find the best and most accurate level of details when it comes to WBS. Since you must fit just one on the page, it will become extremely difficult to find what exactly the tasks are and what must be the creation of them added to the WBS.This may lead to the creation of useless and vague tasks under which you will have a list of non-similar tasks.

[edit] Annotated Bibliography

Project Management Institute. “A Guide to the Project Management Body of Knowledge (PMBOK® Guide)”- Sixth Edition, 2017 The PMBOK Guide is the guide to Body Of Knowledge within Project management, providing widely accepted standards and guide in the use of them. It covers most aspects within project management, although PMI, the publisher, realizes that no book can contain the whole Body of knowledge. This comes clear when the reader looks for motivation in a team, or goal setting techniques. Still, the PMBOK recognizes the importance of both.

[edit] References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 Haugan G T. Effective work breakdown structures[M]. Berrett-Koehler Publishers, 2001. https://www.bkconnection.com/books/title/Effective-Work-Breakdown-Structures
  2. https://www.workbreakdownstructure.com
  3. 3.0 3.1 3.2 3.3 3.4 J T Amin et al 2020 IOP Conf. Ser.: Mater. Sci. Eng. 930 012006.
  4. 4.0 4.1 4.2 Citra Pradipta Hudoyo et al 2019 IOP Conf. Ser.: Earth Environ. Sci. 258 012051 https://iopscience.iop.org/article/10.1088/1755-1315/258/1/012051
  5. 5.0 5.1 5.2 Qiang Maoshan, Chen Ping, Project Management Institute. Work Breakdown Structure (WBS) Implementation Standard [M]. Electronic Industry Press, 2008
  6. Z.G. Liu, F. Q. Li. Process FMEA Applied Research, Quality and Reliability, 42-45+48, 2005.
  7. 7.0 7.1 J. Xue and M. Huang, "Closed loop management of PFMEA combined with WBS," 2016 Chinese Control and Decision Conference (CCDC), Yinchuan, China, 2016, pp. 4003-4008.
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox