Communication in Project Management
(→Communication Plan) |
|||
(16 intermediate revisions by one user not shown) | |||
Line 1: | Line 1: | ||
+ | ''Developed by Edvinas Bureika'' | ||
− | In these rapid times of extensive consumerism and competition, organizations are forced to deliver their products more effectively and efficiently in order to meet the growing requirements. | + | |
+ | In these rapid times of extensive consumerism and competition, organizations are forced to deliver their products more effectively and efficiently in order to meet the growing requirements. Among all other required plans and actions, there lies project management, playing an essential role in successful business development, product design, construction, and even at everyday life of an individual. There are numerous types of projects with different project management techniques and strategies, but the backbone is the communication. In fact, more than half of the projects result in being unsuccessful, and one of the main causes of failure is poor or insufficient communication. A project can have well-defined goals, structure, timeline and stakeholders, but it all might just remain in paper if there is no communication plan between them. Communication is one of the biggest challenges in the activities that organizations face today, and project management is no exception. Therefore, this article examines different methodologies behind the successful communication management strategies within project management. | ||
==Effective Communication in Project Management== | ==Effective Communication in Project Management== | ||
− | [[File:22-09-2015_12-41-18.png|300px|thumb|left|Figure 1: Effectively communicating organizations have more projects that are successful <ref name="pulse"> PMI, 2013 “Pulse of the Profession™ In-Depth Report: The Essential Role of Communications </ref> ]] | + | [[File:22-09-2015_12-41-18.png|300px|thumb|left|Figure 1: Effectively communicating organizations have more projects that are successful <ref name="pulse"> PMI, 2013 “Pulse of the Profession™ In-Depth Report: The Essential Role of Communications" </ref> ]] |
− | Despite of its form, effective communication serves as a bedrock of business. Every project needs effective direction, management, control and communication. Establishing an effective project management team structure and strategy for communication at the beginning of a project, and maintaining these throughout the project’s life, are essential elements of a project’s success. Communication builds trust among project teams, stakeholders, executives and customers. Among organizations, which are considered as highly effective communicators, 80 percent of projects meet original goals, versus 52 percent of their minimally effective competitors (Figure 1). One out of five projects is unsuccessful due to ineffective communications. Usually the lack of effective communication dramatically increases the risk projects face. Even though the most managers are aware of communication gap, not all of them succeed in reducing it. In order to overcome this issue, organizations must help everyone to say the right things to the right people in the right channels, and it should be a part of the project culture. Moreover, communication does not end here. Even if the project is finished, team leaders and project sponsors are still responsible for communicating with end users and business unit managers about what has been accomplished and what value is brought to the organization. According to PMI, the effectively communicating organizations are nearly twice as likely to use formal project Communication Plans and Strategies. | + | Despite of its form, effective communication serves as a bedrock of business. Every project needs effective direction, management, control and communication. Establishing an effective project management team structure and strategy for communication at the beginning of a project, and maintaining these throughout the project’s life, are essential elements of a project’s success. Communication builds trust among project teams, stakeholders, executives and customers. Among organizations, which are considered as highly effective communicators, 80 percent of projects meet original goals, versus 52 percent of their minimally communication-effective competitors (Figure 1). One out of five projects is unsuccessful due to ineffective communications. Usually the lack of effective communication dramatically increases the risk projects face. Even though the most managers are aware of communication gap, not all of them succeed in reducing it. In order to overcome this issue, organizations must help everyone to say the right things to the right people in the right channels, and it should be a part of the project culture. Moreover, communication does not end here. Even if the project is finished, team leaders and project sponsors are still responsible for communicating with end users and business unit managers about what has been accomplished and what value is brought to the organization. According to PMI<ref name="pmi"> PMI, 2013 “Communication: The message is clear” White Paper </ref>, the effectively communicating organizations are nearly twice as likely to use formal project Communication Plans and Strategies. PMI recommends five action steps to improve communication: |
− | |||
* Position communication as a strategic function. The communication must not be positioned as a main task, but more like a context of achievements, in order to avoid the risk of being too focused on the task instead of big-picture goal. | * Position communication as a strategic function. The communication must not be positioned as a main task, but more like a context of achievements, in order to avoid the risk of being too focused on the task instead of big-picture goal. | ||
* Define the target. Any group that is left out can turn from a possible supporter into a detractor. | * Define the target. Any group that is left out can turn from a possible supporter into a detractor. | ||
Line 71: | Line 72: | ||
==Communication Plan== | ==Communication Plan== | ||
− | [[File:Commatrix.png| | + | [[File:Commatrix.png|400px|thumb|left|Figure 4: Communications Matrix <ref name="commanplan"> Communications Management Plan Template from projectmanagementdocs.com http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#ixzz3mk5ki6QE </ref> ]] |
− | + | ||
Communication Management Plan is an activity of Project Initiation Documentation, and thus, a part of Project Plan. The purpose of the Communications Management Plan is to define the communication requirements for the project and how information will be distributed. Although Communication Plans should be customized to suit the particular organization, it typically defines the following<ref name="commanplan"> Communications Management Plan Template from projectmanagementdocs.com http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#ixzz3mk5ki6QE </ref>: | Communication Management Plan is an activity of Project Initiation Documentation, and thus, a part of Project Plan. The purpose of the Communications Management Plan is to define the communication requirements for the project and how information will be distributed. Although Communication Plans should be customized to suit the particular organization, it typically defines the following<ref name="commanplan"> Communications Management Plan Template from projectmanagementdocs.com http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#ixzz3mk5ki6QE </ref>: | ||
Line 88: | Line 89: | ||
* Process for communication-based conflicts. | * Process for communication-based conflicts. | ||
− | Formal Communication Plans allow organizations to target efforts so the right people get the right message in the right channel. It defines communication responsibilities as well as it fosters the explicit understanding of the project’s strategic benefits to all stakeholders at every stage of the project. The importance of a Communication Plan is | + | Formal Communication Plans allow organizations to target efforts so the right people get the right message in the right channel. It defines communication responsibilities as well as it fosters the explicit understanding of the project’s strategic benefits to all stakeholders at every stage of the project. These can be defined in the Communications Matrix (Figure 4). |
+ | |||
+ | The importance of a Communication Plan is obvious. The communication roles, responsibilities and governance must be clarified, otherwise, the people will focus in different directions. In theory, it is not difficult, but the challenge comes in sticking to the plan consciously, which requires a constant effort. | ||
Line 98: | Line 101: | ||
===Ishikawa Fish-bone Diagram=== | ===Ishikawa Fish-bone Diagram=== | ||
− | [[File:Ishikawa.png|300px|thumb| | + | [[File:Ishikawa.png|300px|thumb|right|Figure 5: Causal Diagram by Ishikawa]] |
[https://en.wikipedia.org/wiki/Ishikawa_diagram Ishikawa Diagram] (also called Fish-bone Diagram, or Fishikawa) is a causal analysis tool. It is usually used in product design in order to detect and prevent potential independent factors causing the overall effect. Causes are grouped into categories in order to define the more in-depth sources of the problem. The groups normally are defined as: Equipment, Process, People, Materials, Environment, and Management. The potential primary, secondary, ... causes are then defined in these groups in this way making the overall causal picture. This tool can be used to improve the communication in project management in regards to the problematic approach. | [https://en.wikipedia.org/wiki/Ishikawa_diagram Ishikawa Diagram] (also called Fish-bone Diagram, or Fishikawa) is a causal analysis tool. It is usually used in product design in order to detect and prevent potential independent factors causing the overall effect. Causes are grouped into categories in order to define the more in-depth sources of the problem. The groups normally are defined as: Equipment, Process, People, Materials, Environment, and Management. The potential primary, secondary, ... causes are then defined in these groups in this way making the overall causal picture. This tool can be used to improve the communication in project management in regards to the problematic approach. | ||
Line 104: | Line 107: | ||
===RACI Matrix=== | ===RACI Matrix=== | ||
− | [[File:RACI_Matrix.png|300px|thumb| | + | [[File:RACI_Matrix.png|300px|thumb|right|Figure 6: RACI Matrix <ref name="raci"> https://en.wikipedia.org/wiki/Responsibility_assignment_matrix </ref>]] |
RACI Matrix is a alternative practical derivative from the Responsibility Assignment Matrix (RAM). It describes the participation of various roles in completing the tasks for a project or business process. It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projects and processes. <ref name="raci"> https://en.wikipedia.org/wiki/Responsibility_assignment_matrix </ref> | RACI Matrix is a alternative practical derivative from the Responsibility Assignment Matrix (RAM). It describes the participation of various roles in completing the tasks for a project or business process. It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projects and processes. <ref name="raci"> https://en.wikipedia.org/wiki/Responsibility_assignment_matrix </ref> | ||
The matrix is typically created with a vertical axis, deploying tasks from a Work Breakdown Structure, and a horizontal axis deploying roles. RACI stands for: Responsible, Accountable, Consulted, and Informed. Explanation of roles: | The matrix is typically created with a vertical axis, deploying tasks from a Work Breakdown Structure, and a horizontal axis deploying roles. RACI stands for: Responsible, Accountable, Consulted, and Informed. Explanation of roles: | ||
Line 113: | Line 116: | ||
The matrix helps to define not only the responsibilities, but also the communication channels and direction. It ensures that at least one person is in charge of each category, as well as it helps others to see their role in assisting the responsible person in getting the job done. It also helps to prevent unnecessary communication which might interrupt the whole flow. RACI Matrix can be a complementary for the Communication Plan. | The matrix helps to define not only the responsibilities, but also the communication channels and direction. It ensures that at least one person is in charge of each category, as well as it helps others to see their role in assisting the responsible person in getting the job done. It also helps to prevent unnecessary communication which might interrupt the whole flow. RACI Matrix can be a complementary for the Communication Plan. | ||
+ | |||
+ | |||
+ | ===Communications Flow Chart=== | ||
+ | |||
+ | [[File:Comflow.png|400px|thumb|left|Figure 7: Example of Communincations Flow Chart <ref name="commanplan"> Communications Management Plan Template from projectmanagementdocs.com http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#ixzz3mk5ki6QE </ref>]] | ||
+ | |||
+ | Flowcharts provide a visual representation of a process or processes which often allow a better understanding of how the process is intended to work. Project communications may be extremely complex depending on the size and scope of the project and the number of stakeholders. A flowchart provides all stakeholders with a better understanding of the steps involved with the distribution of all project communications | ||
+ | The communication flowchart below was created to aid in project communication. The example flowchart (Figure 7) provides a framework for the project team to follow for the particular project. However, there may be occasions or situations which fall outside of the communication flowchart where additional clarification is necessary. In these situations the Project Manager is responsible for discussing the communication with the Project Sponsor and making a determination on how to proceed. | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | ==Conclusion and Limitations== | ||
+ | |||
+ | This article represents a theory and several techniques behind an effective communication in project management. However, these should not always be taken as the universal truth, because communication is a phenomena heavily influenced by human behavior, which is in turn different among individuals and situations they are exposed to. Not only different are the people, but also every project is an unique occurrence, having its own character and particularity. The implemented tools can serve well for the time being, but while running a project it is important to maintain vigilance due to the fact that human environment is alive and constantly changing. | ||
+ | |||
==References== | ==References== | ||
Line 118: | Line 146: | ||
<references /> | <references /> | ||
+ | |||
+ | |||
+ | |||
+ | ==Annotated bibliography== | ||
+ | |||
+ | '''''PMI, 2013 “Pulse of the Profession™ In-Depth Report: The Essential Role of Communications"''''' | ||
+ | |||
+ | It is a report written by Project Management Institute for educational reasons. It is based on the research research which was conducted among over 700 experienced project management practitioners, over 100 executive sponsors, and over 200 business owners who have been involved in large capital projects. | ||
+ | |||
+ | |||
+ | '''''PMI, 2013 “Communication: The message is clear” White Paper''''' | ||
+ | |||
+ | It is a white paper, based on analyzing best practices of real business cases within project management, including quotations of relevant stakeholders, project owners, presidents of top performing organizations. | ||
+ | |||
+ | |||
+ | '''''Office Of Government Commerce, 2009 “Managing Successful Projects with PRINCE2™ ”''''' | ||
+ | |||
+ | PRINCE2™ is considered as one of the leading methods in project management, extensively used in more than 150 countries around the world. This book is a guidance that helps running projects of any size and in any environment to effectively deliver what is required by appropriately managing the costs, timescales, quality, scope, risks and benefits. |
Latest revision as of 15:58, 18 December 2018
Developed by Edvinas Bureika
In these rapid times of extensive consumerism and competition, organizations are forced to deliver their products more effectively and efficiently in order to meet the growing requirements. Among all other required plans and actions, there lies project management, playing an essential role in successful business development, product design, construction, and even at everyday life of an individual. There are numerous types of projects with different project management techniques and strategies, but the backbone is the communication. In fact, more than half of the projects result in being unsuccessful, and one of the main causes of failure is poor or insufficient communication. A project can have well-defined goals, structure, timeline and stakeholders, but it all might just remain in paper if there is no communication plan between them. Communication is one of the biggest challenges in the activities that organizations face today, and project management is no exception. Therefore, this article examines different methodologies behind the successful communication management strategies within project management.
Contents |
[edit] Effective Communication in Project Management
Despite of its form, effective communication serves as a bedrock of business. Every project needs effective direction, management, control and communication. Establishing an effective project management team structure and strategy for communication at the beginning of a project, and maintaining these throughout the project’s life, are essential elements of a project’s success. Communication builds trust among project teams, stakeholders, executives and customers. Among organizations, which are considered as highly effective communicators, 80 percent of projects meet original goals, versus 52 percent of their minimally communication-effective competitors (Figure 1). One out of five projects is unsuccessful due to ineffective communications. Usually the lack of effective communication dramatically increases the risk projects face. Even though the most managers are aware of communication gap, not all of them succeed in reducing it. In order to overcome this issue, organizations must help everyone to say the right things to the right people in the right channels, and it should be a part of the project culture. Moreover, communication does not end here. Even if the project is finished, team leaders and project sponsors are still responsible for communicating with end users and business unit managers about what has been accomplished and what value is brought to the organization. According to PMI[2], the effectively communicating organizations are nearly twice as likely to use formal project Communication Plans and Strategies. PMI recommends five action steps to improve communication:
- Position communication as a strategic function. The communication must not be positioned as a main task, but more like a context of achievements, in order to avoid the risk of being too focused on the task instead of big-picture goal.
- Define the target. Any group that is left out can turn from a possible supporter into a detractor.
- Make it a group effort. Everyone should be involved in the communication process to make it work correctly.
- Mix it up. By integrating variety in messaging style, timing and channel, organizations ensure everyone can access the information they need, when they need it.
- Get outsider’s opinion. It brings objectivity into the plan and a project team closer to reality.
[edit] Communication Management Strategy in Project Management
A Communication Management Strategy is done in the project initiation phase and is a document, spreadsheet or a mind map, describing frequency and means of communication between parties within or outside the project [3]. It controls the bi-directional flow of information with stakeholders, thus encouraging their engagement. PRINCE2™ [4] recommends the following ingredients of the Communication Management Strategy:
- Introduction
- Communication management procedure
- Tools and Techniques that will be used
- Records that will be kept
- The ways of reporting the performance of the communication management procedure
- Timing of communication activities
- Roles and responsibilities for communication activities
- Stakeholder analysis
- Quality assessment
The purpose, objective and scope are defined in the introduction, as well as the responsible for the strategy. Communication procedure is description of communication methods that are to be used. It accentuates any deviations from the program management standards. Tools and Techniques refer to any communication tools that may be used for each step of communication. Records describe the required logging of communication activities, as well as where to store them. Reporting describes any needed reports of communication process, including their purpose, timing and recipients. Timing of communication activities describes when the formal communication activities need to take place. Timing also describes when audits of communication methods’ performance need to take place. Stakeholder analysis is a critical component of any communication strategy.
Additionally, the Communication Management Strategy can include or have links to Corporate Communication Policies, Rules for Disclosure, Project Management Team’s structure, Risk Management strategy, Quality Management strategy, information about facilitated discussions or workshops with stakeholders.
The communication Management Strategy aims on both internal and external communications. The strategy must specify the details about how the project management team is going to send and receive information from wider organizations and stakeholders involved or affected in the project. The Stakeholder engagement procedure should also be included as a part of the Communication Management Strategy; it should state the stakeholder types, desired relationships and key messages, strategies for communication, and methodology to evaluate the communication.
The following actions are needed to generate the inputs for Communication Management Strategy:
- Analyze the Project Brief in order to define if any corporate or program management strategies, standards or practices, regarding the communication, need to be employed.
- Create the Lessons Log by seeking lessons from previous similar projects, corporate or program management, and external organizations, related to communication management.
- Review the Risk Register and Issue Register for the issues associated with communication.
- Identify the Stakeholders and consult them for their information needs, such as desired relationships, key communication messages, desired outcomes from successful communications.
- Establish the information needs associated with the Quality Management Strategy, the Risk Management Strategy and the Configuration Management Strategy.
Figure 2 displays inputs and activities of Communication Management Strategy.
[edit] Quality of Communication Management Strategy
After defining the Communication Strategy, it must be consulted whether it meets the needs of Project Board and corporate program management. The Risk Register and Issue Register must be updated if any new risks or issues have been identified. Project Board should approve the Communication Management Strategy despite of a likely preference of approving it later as a part of the Project Initiation Documentation. Communication Management Strategy is evaluated upon certain quality criteria. All stakeholders must have been identified and consulted upon their communication requirements. There must be an agreement from all stakeholders about the content, frequency and methods of communication, furthermore, the common standard for communication has been considered. The resources to carry out any identified communication must be allowed for every stage of the project. If the project is a part of a corporate program, the communication channels and reporting structure to the program must be designated.
[edit] Stakeholder Analysis
According to the Project Management Institute (PMI), the term project stakeholder refers to, ‘an individual, group, or organization, who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project’. Project stakeholders are ones having interest in a particular project. They can be inside or outside of the organization. They can sponsor the project, they can be interested in benefits of a successful project, and they might have positive or negative influence to the project. Not all of them might be aware that they actually are the stakeholders of the particular project. Important is to define and engage as many as possible different stakeholder groups, including definition of the actual individuals. The stakeholder examples can be project leaders, customers, external consultants, product user groups, product testers etc. In order to benefit of the stakeholders’ activity, project stakeholders’ community can be designed and enhanced by using numerous techniques, “Stakeholder Circle” [5] being one of them. It is an online project management tool, which helps to engage the right people in the right way. It can be used to identify stakeholders and understand their needs, as well as prioritize them and map their profiles. It also is a dynamic tool, which makes it possible to monitor changes over time by updating major change points of the activity. The tool is visualized in the figure 3.
The input of the Stakeholder Circle is a stakeholders’ list developed by the project team, including roles, requirements and significance of each one. The tool prioritizes stakeholders and visualizes the top 15 according to their designated power, proximity and urgency. It displays their order of importance in a form of a radar. The project team must ensure that the expectations of key stakeholders are understood, acknowledged, and managed. The technique provides assessment of each stakeholder’s support and receptiveness to messages regarding the project, thus providing the foundation to develop the Tailored Communication Plan. After the aforementioned plan is developed, the project team can concentrate on monitoring effectiveness by mapping changes in the levels of support and receptiveness of each stakeholder, and eventually evaluate whether the communication plan produces the expected results, or should it be updated.
Other relevant stakeholder control techniques can be explored in the article Stakeholder Analysis.
[edit] Communication Plan
Communication Management Plan is an activity of Project Initiation Documentation, and thus, a part of Project Plan. The purpose of the Communications Management Plan is to define the communication requirements for the project and how information will be distributed. Although Communication Plans should be customized to suit the particular organization, it typically defines the following[6]:
- WHAT information will be communicated
- HOW the information will be communicated
- WHEN information will be distributed - the frequency of communications
- WHO is responsible for communicating the information
- Communication requirements for all project stakeholders
- Resources allocated for communication
- Communication of sensitive information
- Management of changes in communication
- The flow of project communication
- External and internal constraints, affecting the communication
- Any standard templates, formats, and documents used for communication
- Process for communication-based conflicts.
Formal Communication Plans allow organizations to target efforts so the right people get the right message in the right channel. It defines communication responsibilities as well as it fosters the explicit understanding of the project’s strategic benefits to all stakeholders at every stage of the project. These can be defined in the Communications Matrix (Figure 4).
The importance of a Communication Plan is obvious. The communication roles, responsibilities and governance must be clarified, otherwise, the people will focus in different directions. In theory, it is not difficult, but the challenge comes in sticking to the plan consciously, which requires a constant effort.
[edit] Tools for improving the communication
[edit] Ishikawa Fish-bone Diagram
Ishikawa Diagram (also called Fish-bone Diagram, or Fishikawa) is a causal analysis tool. It is usually used in product design in order to detect and prevent potential independent factors causing the overall effect. Causes are grouped into categories in order to define the more in-depth sources of the problem. The groups normally are defined as: Equipment, Process, People, Materials, Environment, and Management. The potential primary, secondary, ... causes are then defined in these groups in this way making the overall causal picture. This tool can be used to improve the communication in project management in regards to the problematic approach.
[edit] RACI Matrix
RACI Matrix is a alternative practical derivative from the Responsibility Assignment Matrix (RAM). It describes the participation of various roles in completing the tasks for a project or business process. It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projects and processes. [7] The matrix is typically created with a vertical axis, deploying tasks from a Work Breakdown Structure, and a horizontal axis deploying roles. RACI stands for: Responsible, Accountable, Consulted, and Informed. Explanation of roles:
- Responsible (R) - responsible for task performance. Only one R for each task
- Accountable (A) - assists the completion of the task
- Consulted (C) - the ones whose opinions are taken into account, two-way communication
- Informed (I) - is informed about the progress, one-way communication.
The matrix helps to define not only the responsibilities, but also the communication channels and direction. It ensures that at least one person is in charge of each category, as well as it helps others to see their role in assisting the responsible person in getting the job done. It also helps to prevent unnecessary communication which might interrupt the whole flow. RACI Matrix can be a complementary for the Communication Plan.
[edit] Communications Flow Chart
Flowcharts provide a visual representation of a process or processes which often allow a better understanding of how the process is intended to work. Project communications may be extremely complex depending on the size and scope of the project and the number of stakeholders. A flowchart provides all stakeholders with a better understanding of the steps involved with the distribution of all project communications The communication flowchart below was created to aid in project communication. The example flowchart (Figure 7) provides a framework for the project team to follow for the particular project. However, there may be occasions or situations which fall outside of the communication flowchart where additional clarification is necessary. In these situations the Project Manager is responsible for discussing the communication with the Project Sponsor and making a determination on how to proceed.
[edit] Conclusion and Limitations
This article represents a theory and several techniques behind an effective communication in project management. However, these should not always be taken as the universal truth, because communication is a phenomena heavily influenced by human behavior, which is in turn different among individuals and situations they are exposed to. Not only different are the people, but also every project is an unique occurrence, having its own character and particularity. The implemented tools can serve well for the time being, but while running a project it is important to maintain vigilance due to the fact that human environment is alive and constantly changing.
[edit] References
- ↑ PMI, 2013 “Pulse of the Profession™ In-Depth Report: The Essential Role of Communications"
- ↑ PMI, 2013 “Communication: The message is clear” White Paper
- ↑ Communication Management Strategy template: https://www.hashdoc.com/documents/21812/prince2-communications-management-strategy
- ↑ Office Of Government Commerce, 2009 “Managing Successful Projects with PRINCE2™ ”, pp. 150 – 240.
- ↑ 5.0 5.1 http://www.stakeholder-management.com
- ↑ 6.0 6.1 6.2 Communications Management Plan Template from projectmanagementdocs.com http://www.projectmanagementdocs.com/project-planning-templates/communications-management-plan.html#ixzz3mk5ki6QE
- ↑ 7.0 7.1 https://en.wikipedia.org/wiki/Responsibility_assignment_matrix
[edit] Annotated bibliography
PMI, 2013 “Pulse of the Profession™ In-Depth Report: The Essential Role of Communications"
It is a report written by Project Management Institute for educational reasons. It is based on the research research which was conducted among over 700 experienced project management practitioners, over 100 executive sponsors, and over 200 business owners who have been involved in large capital projects.
PMI, 2013 “Communication: The message is clear” White Paper
It is a white paper, based on analyzing best practices of real business cases within project management, including quotations of relevant stakeholders, project owners, presidents of top performing organizations.
Office Of Government Commerce, 2009 “Managing Successful Projects with PRINCE2™ ”
PRINCE2™ is considered as one of the leading methods in project management, extensively used in more than 150 countries around the world. This book is a guidance that helps running projects of any size and in any environment to effectively deliver what is required by appropriately managing the costs, timescales, quality, scope, risks and benefits.