The Critical Path Method (CPM) in Project Management

From apppm
(Difference between revisions)
Jump to: navigation, search
(The CPM Computation Process)
 
(682 intermediate revisions by 2 users not shown)
Line 1: Line 1:
<center>* * * * W I P * * * *</center>
+
''Developed by Selma Lind Jonsdottir''
  
According to the <span class="plainlinks">[https://en.wikipedia.org/wiki/Project_Management_Institute Project Management Institute (PMI)]</span>, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet project requirements and objectives.<ref name=PMI2008>Project Management Institute. (2008). <i> A Guide to the Project Management Body of Knowledge</i>. 4th Edition. p. 6. USA. ISBN 9781933890517</ref> The challenging task of managing projects can be supported by an <span class="plainlinks">[https://en.wikipedia.org/wiki/Operations_research operation reserach]</span> technique called the <span class="plainlinks">[https://en.wikipedia.org/wiki/Critical_path_method <b>Critical Path Method (CPM)</b>]</span>. The CPM is a mathematically-network based algorithm in which can be used for planning, scheduling and monitoring project progress. <ref name=Larson2014> Larson, E. W & Gray, C. F. (2014). <i>Project Management - The Managerial Process</i>. 6th edition, p. 161. USA: NY. ISBN 9781259010705</ref>
 
  
The technique developed in late 1950s uses information from a <span class="plainlinks">[https://en.wikipedia.org/wiki/Work_breakdown_structure work breakdowm structure (WBS)]</span> in a network representation to display interrelationships and dependencies between project activities that must be accomplished to complete a project. The technique is used for analyzing projects by determining the longest sequence of tasks through a project network, called the <b>critical path</b>. This determines the shortest possible time to complete the project as well as which tasks or activities should be of extra focus in the project. Furthermore, based on acquired information from the CPM, the next question could be if it is possible to shorten the project in order to finish within certain deadline. <ref name=Larson2014/><ref name=Newbold1998>Newbold, R.C. (1998). <i>Project Management in the Fast Lane – Applying the Theory of Constraint.</i> USA: FL. ISBN 9781498738064 </ref><ref name=Jesper>Larsen, J. & Clausen, J., (2009). Course material in Networks and Integer Programming Supplementary at DTU - Notes to Networks and Integer Programming. Retrieved from campusnet.dtu.dk</ref>
+
According to the <span class="plainlinks">[https://en.wikipedia.org/wiki/Project_Management_Institute '''Project Management Institute (PMI)''']</span>, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet project requirements and objectives<ref name=PMI2008>Project Management Institute. (2008). <i> A Guide to the Project Management Body of Knowledge</i>. 4th Edition. USA. ISBN 9781933890517</ref>. The challenging task of managing projects can be supported by an <span class="plainlinks">[https://en.wikipedia.org/wiki/Operations_research operation research]</span> technique called the <span class="plainlinks">[https://en.wikipedia.org/wiki/Critical_path_method <b>Critical Path Method (CPM)</b>]</span>. The <b>CPM</b> is a mathematically-network based algorithm in which can be used for planning, scheduling and monitoring project progress.<ref name=Larson2014> Larson, E. W & Gray, C. F. (2014). <i>Project Management - The Managerial Process</i>. 6th edition. USA: NY. ISBN 9781259010705</ref><ref name=Jesper>Larsen, J. & Clausen, J., (2009). Course material in Networks and Integer Programming Supplementary at DTU - Notes to Networks and Integer Programming. Retrieved 04. September 2016 from campusnet.dtu.dk</ref>
  
The article includes brief introduction and background of the CPM method in project management together with the methodology behind it. An example of the method is carried out step-by-step and a solution is presented. Following is a discussion on time-cost trade offs in project acceleration together with an example of project crashing. Lastly, the article ends on a brief summary on the benefits and limitation of the CPM method within the field of project management.
+
The technique developed in late 1950s utilizes information from a <span class="plainlinks">[https://en.wikipedia.org/wiki/Work_breakdown_structure <b>work breakdown structure (WBS)</b>]</span> in a network representation to display interrelationships and dependencies between project activities that must be accomplished to complete a '''project'''. The technique is used for analyzing projects by determining the longest sequence of tasks through a project network, called the <b>critical path</b>.  This determines the shortest possible time to complete the project as well as which activities should be given a particular focus within the project.<ref name=Larson2014/><ref name=Newbold1998>Newbold, R.C. (1998). <i>Project Management in the Fast Lane – Applying the Theory of Constraint.</i> USA: FL. ISBN 9781498738064</ref>
 +
 
 +
Based on acquired information from the '''CPM''', the next question could be if it is possible to shorten the project in order to finish within certain deadline and what is the least expensive way to do it. In today’s competitive environment, there is an increasing pressure to get projects done earlier and quicker, either from the very beginning, prior to setting the project baseline, or in the midst of project execution in order to get the project back on schedule. Comparison of the benefits by reducing project time with the total cost associated with it can often be a huge challenge for project managers, thus, the decision to reduce the project duration should be based on an analysis of the '''trade-offs''' between '''time''' and '''cost'''.<ref name=Larson2014/><ref name=Jesper/><ref name = Komesh2014>Sahu, K. & Sahu, M. (2014). <i>Cost & Time and Also Minimum Project Duration Using Alternative Method </i> International Review of Applied Engineering Research.  5(4), pp. 403-412. Retrieved 10. September 2016. [http://www.ripublication.com/iraer-spl/iraerv4n5spl_03.pdf Available Online]</ref>
  
 
== Overview ==
 
== Overview ==
Line 12: Line 13:
  
  
Organizations across the world and within different sectors have been using project management as a way to improve project results. The increased awareness and acceptance indicates that the application of knowledge, skills, tools and techniques can have significant impact on project success.<ref name=PMIVOPM> Project Management Institute. (2010). The Value of Project Management. [http://www.pmi.org/-/media/pmi/documents/public/pdf/white-papers/value-of-project-management.pdf Available Online Version]</ref><ref name=PMI2008/>  
+
Organizations across the world and within different sectors have been using project management as a way to improve project results. The increased awareness and acceptance supports that the application of knowledge, skills, tools and techniques can have significant impact on project success.<ref name=PMI2008/><ref name=PMIVOPM> Project Management Institute. (2010). The Value of Project Management. Retrieved 05. September 2016. [http://www.pmi.org/-/media/pmi/documents/public/pdf/white-papers/value-of-project-management.pdf Available Online Version]</ref>
  
[[File:The_triad_constraints1.png|220px|thumb|right|Figure 1: The Project Management Iron Triangle <ref name=WIKITRIANGLE>Wikipedia. <span class="plainlinks">[https://en.wikipedia.org/wiki/Project_management_triangleProject <i>The Project management Triangle.</i>]</span> Retrieved 10.08.2016</ref> ]]
+
[[File:The_triad_constraints1.png|220px|thumb|right|<b>Figure 1:</B> The Project Management Iron Triangle <ref name=WIKITRIANGLE>Wikipedia. <span class="plainlinks">[https://en.wikipedia.org/wiki/Project_management_triangleProject <i>The Project management Triangle.</i>]</span> Retrieved 10.08.2016</ref> ]]
  
According to the <span class="plainlinks">[https://en.wikipedia.org/wiki/ISO_21500 ISO 21500]</span> a project is defined as a<i> “unique set of processes consisting of coordinated and controlled activities with start and end dates, performed to achieve project objectives. Achievement of the project objectives requires the provision of deliverables conforming to specific requirements.” </i><ref name=ISO2012> International Organization for Standardization (2012) ISO 21500 – Guidance on Project Management. </ref>  
+
According to the <span class="plainlinks">[https://en.wikipedia.org/wiki/ISO_21500 '''ISO 21500''']</span> a project is defined as a<i> “unique set of processes consisting of coordinated and controlled activities with start and end dates, performed to achieve project objectives. Achievement of the project objectives requires the provision of deliverables conforming to specific requirements.” </i><ref name=ISO2012> International Organization for Standardization (2012) ISO 21500 – Guidance on Project Management. </ref>  
  
Each and every project is carried out under certain constraints. The most traditional ones, the three constraints of cost, time and scope represent together the iron triangle of project management, which can be seen in Figure 1. Each constraint forms the vertices with quality as the central theme and all together it indicates that projects must be delivered within agreed time and cost and furthermore to meet the agreed scope and customer quality requirements. The three constraints are closely linked and changes to one of them will likely affect the others, or impact the quality of the project. This emphasizes the importance of project management and that the area is challenging and not at all easy to deal with.<ref name=WIKITRIANGLE/><ref name=MINDTOOLS>Mind Tools.<i> The Iron Triangle of Project Management.</i> Retrieved 10.08.2016 from [https://www.mindtools.com/pages/article/newPPM_54.htm MindTools online page]</ref>
+
Each and every project is carried out under certain constraints. The three constraints of cost, time and scope represent together the <span class="plainlinks">[https://en.wikipedia.org/wiki/Project_management_triangle '''iron triangle''']</span> of project management, which can be seen in <i>Figure 1</i>. Each constraint forms the vertices with quality as the central theme and together indicates that projects must be delivered within agreed time and cost and furthermore to meet the agreed scope and customer quality requirements. The three constraints are aligned and changes in one will likely affect the others, or impact the quality of the project. This emphasizes the importance of project management and its challenging area in which is not at all easy to deal with.<ref name=WIKITRIANGLE/><ref name=MINDTOOLS>Mind Tools.<i> The Iron Triangle of Project Management.</i> Retrieved 10. September 2016. [https://www.mindtools.com/pages/article/newPPM_54.htm Available Online]</ref>
  
 
Project management is accomplished through the appropriate application of five processes: <ref name=PMI2008/>
 
Project management is accomplished through the appropriate application of five processes: <ref name=PMI2008/>
Line 28: Line 29:
 
# Closing
 
# Closing
  
Each and every organization can be involved in a project of any size, duration and complexity level at any given time. It is notable that project planning, scheduling and monitoring is a major part involved in project management. Therefore the '''critical path method (CPM)''' can be of good support within the challenging process of managing projects and helps those involved to address questions such as:
+
Each and every organization can be involved in a project of any size, duration and complexity level at any given time. It is notable that project planning, scheduling and monitoring is a major part involved in project management. Therefore the '''critical path method (CPM)''' can be of good support within the challenging process of managing projects and helps those involved to address questions such as: <ref name=NETWORK>Chapter on Deterministic Decision Models. (n.d.). Course material in Network Optimization at DTU autumn 2015. <i>Project Scheduling: PERT/CPM.</i> [https://www.google.dk/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0ahUKEwixqcub74nPAhUMFSwKHS1pAFIQFggeMAA&url=http%3A%2F%2Fhighered.mheducation.com%2Fsites%2Fdl%2Ffree%2F0070813809%2F700204%2FsampleChapter8.pdf&usg=AFQjCNGErOnRK7sLSe6Ii4g7lsOCaWXpuA&sig2=ss1geYqxTa5GJ2feFpsi7Q Available online]</ref>
  
 
* What is the (minimum) total time required to complete the whole project?  
 
* What is the (minimum) total time required to complete the whole project?  
* What are the (earliest and latest) start and completion times for individual activities?
+
* What are the (earliest and latest) start and completion times for individual activities in the project?
 
* Which activities are critical and must be completed on time in order to complete the whole project on time?
 
* Which activities are critical and must be completed on time in order to complete the whole project on time?
*How much delay is tolerated of non-critical activities without impacting the overall project schedule and project completion time?
+
* How much delay is tolerated of non-critical activities without impacting the overall project schedule and project completion time?
*With cost information on each activity: What is the least expensive way to speed up a project to meet a targeted completion time?
+
* With cost information on each activity: What is the least expensive way to reduce project duration in order to meet a targeted completion time?
  
All these questions are valid and important to have under control when managing projects.
+
All these questions are extremely valid and important to have under control when managing projects.
  
 
=== Background ===
 
=== Background ===
  
The '''critical path method (CPM)''' is a mathematically-network based project modeling technique developed in late 1950s in order to plan, schedule and control large, complex projects with many activities. CPM is one approach of <b>network techniques</b> that has been widely used and was developed by a DuPont engineer Morgan R. Walker and a Remington Rand computer expert, James E. Kelly, Jr. to manage plant maintenance and construction work. Furthermore, a critical path network technique developed simultaneously and independently from CPM, called <span class="plainlinks">[https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique <b>PERT (Program evaluation and review technique)</b>]</span>. PERT was developed by the U.S. Navy for managing Fleet Ballistic Missile (Polaris) submarine project and is commonly used in conjunction with CPM and and the two optimization techniques are ofen referred to collectively. Today, there exists project management software packages in which are based on these two techniques, for example <span class="plainlinks">[https://en.wikipedia.org/wiki/Microsoft_Project Microsoft Projects]</span>.<ref name=Jesper/><ref name=Anderson1986>Anderson, E. B., & Hales, R. S., (1986).<i> Critical Path Method Applied to Project Planning: FEES</i>. United States Department of Agriculture. USA. [http://www.fs.fed.us/psw/publications/documents/psw_gtr093/psw_gtr093.pdf Available Online]</ref><ref>Stelth, P. (2009). <i>Project’s Analysis through CPM (Critical Path Method). </i>Isles International University. [http://www.iiuedu.eu/press/journals/sds/sds1_july_2008/05_SECC_01.pdf Available Online]</ref>
+
The '''critical path method (CPM)''' is a mathematically-network based project modeling technique developed in late 1950s in order to plan, schedule and control large, complex projects with many activities. '''CPM''' is one approach of <b>network techniques</b> that has been widely used and was developed by a DuPont engineer Morgan R. Walker and a Remington Rand computer expert, James E. Kelly, Jr., to manage plant maintenance and construction work. Furthermore, <span class="plainlinks">[https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique <b>PERT (Program Evaluation and Review Technique)</b>]</span>, a critical path network technique was developed simultaneously and independently from the '''CPM''' by the U.S. Navy for managing the Fleet Ballistic Missile <span class="plainlinks">[https://en.wikipedia.org/wiki/UGM-27_Polaris <b>(Polaris)</b>]</span> submarine project. <span class="plainlinks">[https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique <b>PERT</b>]</span> is commonly used in conjunction with '''CPM''' and the two optimization techniques are often referred to collectively. <ref name=Jesper/><ref name=Anderson1986>Anderson, E. B., & Hales, R. S., (1986).<i> Critical Path Method Applied to Project Planning: Fire Economics Evaluation Systems (FEES)</i>. United States Department of Agriculture. USA. [http://www.fs.fed.us/psw/publications/documents/psw_gtr093/psw_gtr093.pdf Available Online]</ref><ref name=STELTH2009>Stelth, P. (2009). <i>Project’s Analysis through CPM (Critical Path Method). </i>Isles International University. Retrieved 06. September 2016. [http://www.iiuedu.eu/press/journals/sds/sds1_july_2008/05_SECC_01.pdf Available Online]</ref>
  
The '''CPM''' technique has been used for many different forms of projects including construction of a new building, bridge or a road, construction of IT-systems, building of ships and research and development of new products. All these projects consist of multiple activities or tasks that have to be completed in order to finish the whole project. Furthermore, some activities are independent and therefore cannot start before other activity has been completed and so on. The ones who manage projects have to deal with multiple challenges within planning, coordinating and monitoring these activities in order to complete the project of interest successfully within agreed time, cost and scope and according to customer quality requirements.<ref name=Jesper/>
+
The '''CPM''' technique has been used for many different forms of projects including construction of a new building, bridge or a road, construction of IT-systems, building of ships and research and development of new products. As can be imagined, these projects consist of multiple activities that have to be completed in order to finish the project as a whole.
 +
It is important to note that the methodology is normally not applied to real large scale and complex problems with many activities, since developing the project network and applying the technique can be extremely time consuming. Today, there exists project management software packages based on the methodology, for example <span class="plainlinks">[https://en.wikipedia.org/wiki/Microsoft_Project <b>Microsoft Project</b>]</span>, which are used to calculate all completion times based on a input. The programs are further able to create a visualization of the whole project which is used to ease overview and understanding, as well as supporting the monitoring of the project. On the other hand, the methodology can easily be applied manually to smaller problems in which will be the case in this article. Despite what already mentioned, a knowledge of the concept is important, thus the ones who manage projects have to deal with multiple challenges within planning, coordinating and monitoring all project activities in order to complete the project of interest successfully within agreed time, cost and scope as well as according to customer quality requirements.<ref name=Jesper/>
  
== Application and use ==
+
== Methodology ==
  
=== Methodology ===
 
  
The following input requirements are needed in order to construct a network model of the project of interest: <ref name=Larson2014/>
+
The '''Critical Path Method (CPM)''' can be divided into the following steps:
  
* A list of all activities or specific tasks required to comlete the project also known as the <span class="plainlinks">[https://en.wikipedia.org/wiki/Work_breakdown_structure '''work breakdowm structure (WBS)''']</span>
+
*<b>STEP 1:</B>  <i>Developing the Project Network</i>
* The duration of each activity for completion
+
 
 +
*<b>STEP 2: </B>  <i>Constructing the Project Network</i>
 +
 
 +
*<b>STEP 3: </B>  <i>The Computation Process of forward pass, backward pass and slack</i>
 +
 
 +
*<b>STEP 4: </B>  <i>Critical Path Identification</i>
 +
 
 +
*<b>STEP 5: </B>  <i>Update of Project Progress</i>
 +
 
 +
The methodology will be explained step-by-step as well as with an example in <span class="plainlinks">[http://apppm.man.dtu.dk/index.php/The_Critical_Path_Method_(CPM)_in_Project_Management#CPM_Example <i>Chapter 3: CPM Example</i>.]</span>
 +
 
 +
====Step 1: Developing the Project Network====
 +
<!-- Comment <b>Step 1: Developing the Project Network</b>====-->
 +
 
 +
When developing the project network, the following input requirements are needed in order to construct a network model of the project of interest: <ref name=STANFORD>Santiago, J. & Magallon, D. (2009). <I>The Critical Path Method</I> - (CEE 320 – VDC Seminar). Stanford University.  Retrieved 06. September 2016. [http://web.stanford.edu/class/cee320/CEE320B/CPM.pdf Available online]</ref>
 +
 
 +
* A list of all activities required to complete  the project also known as the <span class="plainlinks">[https://en.wikipedia.org/wiki/Work_breakdown_structure '''work breakdown structure (WBS)''']</span>
 +
* The duration of each individual activity for completion
 
* The dependencies between the activities
 
* The dependencies between the activities
  
With this information, the <b>critical path method</b> is able to determine the longest path of activities through the '''project network''', defined as the <b>critical path</b> and the corresponding activities are defined as <b>critical activities</b>. Based on the fact that the entire project cannot finish until all the activities are completed, the longest path or the '''critical path''' gives also the minimum required time to complete the entire project.  
+
With this information, the <b>critical path method (CPM)</b> is able to determine the longest path of activities through the '''project network''', defined as the <b>critical path</b> and the corresponding activities are defined as <b>critical activities</b>. Based on the fact that the entire project cannot finish until all the activities are completed, the longest path or the '''critical path''' gives also the minimum required time to complete the entire project.
  
The '''critical path''' is of great importance since all '''critical activities''' must be completed as scheduled in order to meet the scheduled project completion time, that is, if an activity on the '''critical path''' is delayed, the project is delayed by the same amount of time. This is due to the fact that the activities on the '''critical path''' have a '''zero slack'''. '''Slack (SL)''' is defined as the amount of time an activity can be delayed without delaying the whole project. Therefore, project managers need pay close attention to the critical path activities in order to ensure that they are not delayed and therefore put the entire project in risk of being late.
+
====Step 2: Constructing the Project Network====
 +
<!-- Comment <b>Step 2: Constructing the Project Network</b>====-->
 +
The second step involves drawing the project network by placing the activities that need to be completed in the right logical sequence based on their interdependencies. The '''CPM''' notation used for each and every activity in the project network can be seen in <i>Figure 2</i>. Therefore, for all activities in the network the following information is registered and/or computed:  [[File:Notation.png|220px|thumb|right|<b>Figure 2:</b> Activity Notation in a Project Network <ref name=Larson2014/>]]
  
The '''sensitivity''' of a project network is aligned with the number of critical or noncritical paths. A network is considered sensitive when it has more than one critical path and/or non-critical activities with little slack and therefore, it is considered more likely that the original critical path(s) will change, once the project has started. On the other hand, a network is considered '''insensitive''' when it has one critical path and noncritical activities with very large slack, and therefore less likely that the critical path will change, once the project has started.
+
* '''ID:''' Identification code of individual activity based on the WBS
 +
* '''Description:''' Description of individual activity based on the WBS
 +
* '''Duration (DUR):''' Duration time of individual activity
 +
* '''Early Start (ES):''' The earliest starting time of an individual activity
 +
* '''Early Finish (EF):''' The earliest finishing time of an individual activity
 +
* '''Late Start (LS):''' The latest starting time of an individual activity
 +
* '''Late Finish (LF):''' The latest finishing time of an individual activity
 +
* '''SL (Slack):''' The tolerance of delay of an individual activity without affecting  project completion date
  
It is important to note that the methodology is normally not applied to real large scale and complex problems with many activities, since developing the project network and applying the technique can be extremely time consuming. Today, there exists project management software packages based on the methodology in which are used to calculate all completion times based on an input. The programs are further able create a visualization the whole project network in which is used to ease overview and understanding as well as supporting the monitoring of the project as a whole.  But the methodology can easily be applied manually to smaller problems and that will be the case here.   
+
====Step 3: The Computation Process====
 +
<!-- Comment <b>Step 3: The Computation Process</b>====-->
  
The '''CPM''' notation used for each and every activity in the project network can be seen in <i>Figure 2</i>. Therefore, for all activities in the network the following information is registerd and/or computed:  [[File:NetworkNotation.png|220px|thumb|right|Figure 2: Activity Notation in a Project Network <ref name=Larson2014/>]]
+
The third step involves the two procedures of '''forward pass''' used to compute earliest times, '''ES''' and '''EF''', and the '''backward pass''' used to compute latest times, '''LS''' and '''LF''' as well as <b>slack</b> computation. <ref name=Larson2014/><ref name=NETWORK/>
  
* '''ID:''' Identification code of individual activity  
+
<b>Forward Pass</b> begins at the initial activity and traces each path through the network step-by-step, to the end of the last project activity/activities. An important rule of the forward pass procedure is that all immediate predecessors must be completed before a succeeding activity can start. That is, early start (ES) of an activity equals the <b>largest</b> early finish (EF) of the immediate predecessors.
* '''DUR:''' Duration time of individual activity based on the WBS
+
* '''ES (Early Start):''' The earliest starting time of an individual activity  
+
* '''EF (Early Finish):''' The earliest finishing time of an individual activity
+
* '''LS (Late Start):''' The latest starting time of an individual activity
+
* '''LF (Late Finish):''' The latest finishing time of an individual activity
+
* '''SL (Slack):''' The tolerance of delay of an activity without affecting imposed completion date
+
  
The '''network computation process''' involves drawing the project network by placing the activities that need to be completed in the right logical sequence based on their interdependencies. The methodology involves the two procedures of '''forward pass''' used to compute earliest times, '''ES''' and '''EF''', and '''backward pass''' used to compute latest times, '''LS''' and '''LF'''. <ref name=Larson2014/><ref name=NETWORK>Chapter on Deterministic Decision Models. (n.d.). Course material in Network Optimization at DTU autumn 2015. <i>Project Scheduling: PERT/CPM.</i>  [https://www.google.dk/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0ahUKEwixqcub74nPAhUMFSwKHS1pAFIQFggeMAA&url=http%3A%2F%2Fhighered.mheducation.com%2Fsites%2Fdl%2Ffree%2F0070813809%2F700204%2FsampleChapter8.pdf&usg=AFQjCNGErOnRK7sLSe6Ii4g7lsOCaWXpuA&sig2=ss1geYqxTa5GJ2feFpsi7Q Available online]</ref>
+
For the starting activity/activities of the network, early start (ES) is set as '''ES = 0''' (or some other known value) and each path is traced forward to the finishing activity/activities by applying '''EF = ES + DUR''' to all activities in the project network. When finished, the longest path denotes the project completion time for the plan, that is, '''largest EF = Total Time.'''  
  
====Forward Pass====
+
<b>Backward Pass</b> is initiated after the forward pass has been completed and starts with the last project activity/activities without successors and the late finish (LF) is set as equal to the maximum early finish (EF) of those activities. An important rule of the backward pass is that at the latest time a succeeding activity can start is only when all immediate predecessors are completed. That is, late finish (LF) for an preceding activity equals the <b>smallest</b> late start (LS) of the immediate successor activities.
'''Forward Pass''' begins at the initial activity and traces each path through the network step-by-step, to the end of the last project activity/activities. An important rule of the forward pass prodeadure is  is that all immediate predecessors must be completed before an activity can begin. That is, ES of an activity equals the largest EF of the immediate predecessors.  
+
  
For the starting activity of the network, '''ES = 0''' (or some other known value) and '''EF = ES + DUR''' is applied to all activies in the network. When finished, the longest path denotes the project completion time for the plan, that is, '''largest EF = Total Time.'''
+
With that in mind, each path is traced backward towards the initial starting activity/activities by applying '''LS = LF - DUR'''. When this has been applied to all the activities in the project network, the total '''slack''' of an activity can be determined by using '''SL = LS – ES''' or '''LF – EF'''. <ref name=NETWORK/>
  
====Backward Pass====
+
====Step 4: Critical Path Identification====
'''Backward Pass''' is initiated after the forward pass has been compleated and starts with the last project activity/activities without successors and the LF is set as equal to EF for those activities.  An important rule of the backward pass is that an activity can start the latest time, only if all immediate predecessors are completed. That is, LF for an activity equals the smallest LS of the immediate successor activities.
+
<!-- Comment <b>Step 4: Critical Path Identification</b>====-->
  
With that in mind, each path is traced backward towards the starting activity applying '''LS = LF - DUR'''. When this has been applied to all the activities in the project network, the total '''slack''' of an activity can be determined by using '''SL = LS – ES''' or '''LF – EF'''.  
+
The '''critical path''' is of great importance since all '''critical activities''' must be completed as scheduled in order to meet the scheduled project completion time, that is, if an activity on the '''critical path''' is delayed, the project is delayed by the same amount of time. This is due to the fact that the activities on the '''critical path''' have a '''zero slack''''''Slack (SL)''' is defined as the amount of time an activity can be delayed without delaying the whole project. Therefore, project managers need pay close attention to the '''critical path activities''', which can represent around 10% of all project activities, in order to ensure that they are not delayed and therefore put the entire project in the risk of being late. <ref name=Larson2014/>
  
The methodology will be explained step-by-step with an example.
+
====Step 5: Update of project progress====
 +
<!-- ====<b>Step 4: Update of project pogress</b>====-->
  
=== CPM Example ===
+
As the project progresses, the actual activity completion times will be known and the project network can be updated in order to include this information. It is important to note that a new critical path may emerge and changes may be made in the network if project requirements suddenly change. <ref name=Komesh2014\>SmartSheet. <i>The Ultimate Guide to the Critical Path Method.</i> Retrieved 18.08.2016 from [https://www.smartsheet.com/critical-path-method SmartSheets online page]</ref>
 +
 
 +
The emerge of new critical path is related to the '''sensitivity''' of a project network. A network is considered '''sensitive''' when it has one or more critical path(s) and/or non-critical activities with little slack and therefore it is more likely that the original critical path(s) will change once the project has started. On the other hand, a network is considered '''insensitive''' when it has one critical path and non-critical activities with very large slack, and therefore less likely that the critical path will change once the project has started. <ref name=Larson2014/>
 +
 
 +
== CPM Example ==
  
 
In order to gain understanding of the critical path method, the following example is provided.
 
In order to gain understanding of the critical path method, the following example is provided.
====Developing the CPM Project Network====
+
 
<i>Table 1</i> provides information on 9 activities required to complete a project of intrest as well as their dependencies and duration times. Based on those information, the project’s needs can be translated into a network diagram in which the CPM can be utilized. The diagram graphically shows the project flow and precedence relationships among all project activities and gives the project manager a visual represensation of the entire project.  
+
===Constructing the CPM Project Network===
 +
<i>Table 1</i> provides the required information of <b>Step 1</B>, that is, 9 activities required to complete a project of interest as well as their dependencies and duration times. Based on those information, the projects needs can be translated into a network diagram in which the CPM can be utilized. The diagram in <b>Step 2</b> graphically shows the project flow and precedence relationships among all project activities and gives the project manager a visual representation of the entire project.  
 
{| class="wikitable" style="margin-left: auto; margin-right: auto; border: none;"
 
{| class="wikitable" style="margin-left: auto; margin-right: auto; border: none;"
 
|+ Table 1: Project Information for the CPM  
 
|+ Table 1: Project Information for the CPM  
Line 97: Line 124:
 
! Duration [Weeks]
 
! Duration [Weeks]
 
! Predecessor
 
! Predecessor
! Decription
+
! Description
 
|-
 
|-
 
| <center>A</center>
 
| <center>A</center>
Line 117: Line 144:
 
| <center>10</center>
 
| <center>10</center>
 
| <center>B, C</center>
 
| <center>B, C</center>
| Raise the roof.
+
| Raise the roof
 
|-
 
|-
 
| <center>E</center>
 
| <center>E</center>
Line 145: Line 172:
 
|}
 
|}
  
A network model of the project of intrest represented in <i>Table 1</i> can be seen in <i>Figure 3</i> where all project activities have been placed in the right logical sequence based on their interdependencies, using the project activity notation presented in <i>Figure 2</i>. This is the inital starting point of the critical path method.  
+
A network model of the project of interest represented in <i>Table 1</i> can be seen in <i>Figure 3</i> where all project activities have been placed in the right logical sequence based on their interdependencies and using the activity notation presented in <i>Figure 2</i>. This is the initial starting point of the critical path method before computation process, <b>Step 3</B>, takes place.  
  
  
[[File:ProjectNetwork2.png|800px|thumb|center|Figure 3: Network Representsation of the Project Example presented in Table 1]]
+
[[File:ProjectNetwork2.png|800px|thumb|center|<b>Figure 3:</b> Network Representsation of the Project Example presented in Table 1]]
  
====The CPM Computation Process====
+
===The CPM Computation Process===
Following the CPM methodology presented earlier, the first step is to perform the <b>forward pass</b>. The earliest finish (EF) date for activty A can now be computed as 0+1=1. Activities B and C have activity A as their immediate predecessor with early start as 1 and early finish (EF) as 1+5=6 and 1+5=5. Activity D is a merge activity since it is preceded by both B and C. The early start (ES) of a merge activity depends on the largest early finish (EF) of all activities that merge to it, since the activity cannot start until both the predecessing activities have finished. Therefore, early start of activity D=max(6_\text{EF-B},5_\text{EF-C})=6. If we continue this forward pass, the early start and early finish for all activities can be computed as summerized in <i>Figure 3</i>. When the forward pass has been completed,  it can be see that the early finish for activity I or the project in total is 29 weeks.  
+
Following the <b>CPM</b> methodology presented earlier, the first step of the computation process is to perform the <b>forward pass</b>. Activity A has no predecessors and therefore we assume that the activity can start as soon as the project can start, at time 0. The earliest finish (EF) date for activity A can now be computed as <i>0 + 1 = 1</i>. Activities B and C have activity A as their immediate predecessor with early start (ES) as 1 and early finish (EF) as <i>1 + 5 = 6</i> and <i>1 + 4 = 5</i>. Activity D is a <b>merge activity</b> since it is preceded by both B and C. The early start (ES) of a merge activity depends on the largest early finish (EF) of all activities that merge to it, since the activity cannot start until both the predeceasing activities have finished. Therefore, early start of activity D is <i>max(6<sub>(EF-B)</sub>,5<sub>(EF-C)</sub>) = 6</i>. By continuing the forward pass, the early start (ES) and early finish (EF) for all activities can be computed as shown in <i>Figure 4</i>. When the forward pass has been completed,  it can be seen that the early finish (EF) for activity I, or the project in total is <b>29 weeks</b>.  
  
The later step in the CPM methodology is the <b>backward pass</b>.  The first step is that the late finish (LF) of the finish node is set equal to its early finish EF = 29 weeks. The immediate successor of activities G, F and H is node finish node I.  
+
The second step in the CPM methodology is the <b>backward pass</b> starting with the last project activity, which in this case is I.  The late finish (LF) of the finishing node I is set equal to its early finish (EF) of 29 weeks and late start (LS) can be computed as <i>29 - 6 = 23.</i> The finishing node I is an immediate successor of activities G, F and H, hence the latest finishing (LF) time for all the three activities is set to 23 and their late starts (LS) are computed as <i>23 - 5 = 18</i>, <i>23 - 7 = 16</i> and <i>23 - 4 = 19</i>. Activity E is a <b>burst activity</b> since it is a immediate predecessor for both activities F and H. Hence, the late finish (LF) for activity E is controlled by the smallest late starts (LS) of the two succeeding activities since activity E cannot finish later than the latest start of an immediate successor. Therefore, late finish (LF) of activity E is <i>min(16<sub>(LS-F)</sub>,19<sub>(LS-H)</sub>) = 16</i>. If the backward pass is continued until the starting node, the late start (LS) and late finish (LF) for all activities can be computed as shown in <i>Figure 4</i>.
  
  
[[File:ProjectNetworkSolution1.png|800px|thumb|center|Figure 3: Solution of the Project Example presented in Table 1 based on CPM - <b>Critical Path</b>: A - B - D - F - I ]]
+
[[File:ProjectNetworkSolution1.png|800px|thumb|center|<b>Figure 4:</b> Solution of the Project Example presented in Table 1 based on CPM - <b>Critical Path</b>: A - B - D - F - I ]]
  
 +
===Slack Computation and Critical Path Identification===
 +
After the completion of forward and backward passes, it is possible to determine which activities can be delayed by calculating the slack for individual activities in the project network. The slack for activity A is 0 since there is no difference between ES/EF and LS/LF.  On the other hand, the slack for activity C is <i>2 - 1 = 6 - 5 = 1.</i> The slack for individual activities can be computed as shown in <i>Figure 4</i>.  After the slack computation, the critical path can easily be identified as the longest path through the network with critical activities consisting of <b>zero slack</b>. The <b>critical path</b> in this example is: <b><i>A – B – D – F – I. </i></B>. That is, if an activity on the path is delayed, the project is delayed by the same amount of time.
  
{{main|Wikipedia:Manual of Style (mathematics)#Superscripts and subscripts}}
+
== Consideration of Time-Cost trade-offs ==
  
 +
[[File:TC-tradeoff.png|260px|thumb|right|<b>Figure 5:</B> Project Time-Cost Trade-Off Curve. <ref name=Tradeoffpicture>Hegazy, T. (1999). <i>Optimization of construction time – Cost trade-off analysis using genetic algorithms.</i> Figure of Time-Cost Trade-Offs Retrieved 09. September 2016. [https://www.google.dk/search?q=project+time+cost+relationship&client=safari&rls=en&source=lnms&tbm=isch&sa=X&ved=0ahUKEwiH5dKvk5LPAhUDXCwKHdZhBoUQ_AUICCgB&biw=1080&bih=634#imgrc=288dO6iwGcV2gM%3A Available online]</ref> ]]
  
<code>D=max(6_\text{EF-B},5_\text{EF-C})=6.</code>
+
The consideration of '''time-cost trade-offs''' for a project is often considered an essential part of a complete '''Critical Path Method (CPM)''' analysis <ref name=CPMTRADEOFF>Panagiotakopoulos, D. <i>A CPM Time-Cost Computational Algorithm for Arbitrary Activity Cost Functions.</i> Department of Civil Engineering, McGill University, Montreal.  Retrieved 20.08.2016.</ref>. Based on acquired information from the <b>CPM</b>, the next questions could be if it is possible to shorten the project in order to finish within certain deadline and what is the least expensive way to do it. <b>Project crashing</B> is a procedure to identify the cost of reducing project duration so that comparisons can be made with the benefits of getting the project completed earlier. It requires information of the '''total project cost''', which includes both '''direct''' and '''indirect costs'''. Shortening the project duration will normally increase the '''direct costs''', which can be assigned directly to project activities and commonly represents labor, materials and etc. Meanwhile, a reduction in project duration indicates a reduction in '''indirect costs''', necessary costs for doing work, which continues for the life of the project and is not related to individual project activities. Therefore, the '''time-cost trade-off analysis''' can help to identify the <b>optimum cost-time point</b> between increasing cost of individual activities and decreasing overall project costs. The outcome of such analysis results in a time-cost trade-off curve as shown in <i>Figure 5</i> which furthermore shows that the optimum project duration can be determined as the project duration that results in the least total project cost. <ref name=TRADEOFF>Elbeltagi, E. <i>Construction Management - Chapter on Project Time-Cost Trade-Offs.</i> Retrieved 15. September 2016. [http://osp.mans.edu.eg/elbeltagi/CM%20CH8%20Time-Cost.pdf Available online]</ref><ref name=CPMtutor>CPM Tutor. (2010). <i>Time-Cost Trade-Off</i>. Retrieved 15. September 2016 [http://www.cpmtutor.com/c08/timecosttradeoff.html Available online]</ref>
D=max(6{{sup|EF-B},5{{sup|EF-C}}}=6
+
vii{{sup|o}}
+
D=max(<math>6_\text{EF-B}</math>,<math>5_\text{EF-C}</math>)=6.
+
  
<code>{{tlx|Nuclide2|He|3}}</code>
 
  
 +
[[File:AcTrelationship1.png|350px|thumb|right|<b>Figure 6:</B> Activity Cost & Time Relationship.<ref name=NETWORK/> ]]
  
{{main|Wikipedia:Manual of Style (music)}}
+
Simplified represensation of the relationship between activity duration and its direct costs can be seen in <i>Figure 6</i>. <b>Normal time</B> for an activity represents estimated activity duration under normal conditions retrieved from the <B>CPM</B> and <b>normal cost</B> refers to the corresponding cost of that activity, which implies minimum direct cost. <b>Crashing</b> refers to speeding up the duration of an activity and the <b>crash time</B> is the shortest possible time an activity can be completed in. The direct cost for completing an activity in its crash time is called <b>crash cost</b> and <b>crash point</b> represents the maximum time an activity can be compressed. The cost-time relationship is assumed to be linear as shown in <i>Figure 6</i> and for each activity a <b>crash cost per period</b> can be derived as:
<code><nowiki>vii{{sup|o}}</nowiki></code>, <code><nowiki>I{{sub|6}}</nowiki></code>. This looks like: {{xt|vii{{sup|o}}}}, {{xt|I{{sub|6}}}}.
+
  
== Consdideration of Time-Cost trade-offs ==
 
  
''Question from "Introduction" in bullet point number five:
+
<center><math> \text{crash cost period}  =  \tfrac{\text{Crash Cost - Normal Cost}}{\text{Normal Time - Crash Time}}</math></center>
  
*With cost information on each activity and how much it costs to speed up that activity: what is the least expensive way to speed up a project to meet a targeted completion time?''
 
  
 +
That is, the <b>slope</b> gives information about the <b>cost per unit of time</b> for shortening an individual activity and therefore allows comparison of which <b>critical activities</b> to shorten in order to minimize the total direct cost. <ref name=Larson2014/><ref name=NETWORK/><ref name=TRADEOFF/>
  
 +
After having utilized the '''CPM''', the procedure for '''project crashing''' involves the following steps: <ref name=NETWORK/><ref name=TRADEOFF/>
  
Once the '''critical path''' and '''timeing''' of activities has been identified - the next question is if it is possible to shorten the project in order to finish within a certein deadline. If you put in information about the cost of each activity, and how much it costs to speed up each activity, CPM can be of help to find out:
+
# Compute the '''crash cost per period''' for all activities in the project network
 +
# Find '''critical path(s)''' and '''critical activities''' in the project network
 +
# In the case of only '''one''' '''critical path''', identify a critical activity with the '''smallest crash cost per period''' that can still be crashed. '''Otherwise''', identify critical activity/activities from '''each critical path''' with the s'''mallest crash cost per period''', which can still be crashed.
 +
# Reduce the duration of the critical activity/activities identified in step 3 by one time period.
 +
# Reconstruct or adjust the project network based on changes made in step 4. Calculate the <b>total costs</b> = <b>directs</b> + <b>indirect costs</b>. '''Stop''' the procedure if the desired completion deadline is reached, otherwise return to step 3. Continue until the '''crash point''' has been reached, that is, no further shortening is possible.
  
*whether we should try to speed up the project, and if so,
+
An example of project crashing where the procedure is utilized and explained step-by-step is available in <span class="plainlinks">[https://www.google.dk/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0ahUKEwixqcub74nPAhUMFSwKHS1pAFIQFggeMAA&url=http%3A%2F%2Fhighered.mheducation.com%2Fsites%2Fdl%2Ffree%2F0070813809%2F700204%2FsampleChapter8.pdf&usg=AFQjCNGErOnRK7sLSe6Ii4g7lsOCaWXpuA&sig2=ss1geYqxTa5GJ2feFpsi7Q <b>Chapter 8.7: Project Crashing</b>]</span>. The procedure can be used as a continuation of the example that was provided above in <span class="plainlinks">[http://apppm.man.dtu.dk/index.php/The_Critical_Path_Method_(CPM)_in_Project_Management#CPM_Example <i>Chapter 3: CPM Example</i>]</span>, with a relatively small change. The only change required is that the duration time of activity A is set to 0 since it is considered as a dummy activity.  
*what is the least costly way to speed up the project.
+
  
=== Project Crashing Example ===
+
For additional knowledge and understanding, <i>Video 1</i> below provides a detailed step-by-step guidance on the project crashing procedure. Good examples are as well provided in <span class="plainlinks">[http://osp.mans.edu.eg/elbeltagi/CM%20CH8%20Time-Cost.pdf <b>Chapter 8.4: Shortening Project Duration</b>]</span>.
  
 +
<center>{{#ev:youtube|www.youtube.com/watch?v=zg0-yzl3neY|600|center|'''Video 1: '''Example of Project Acceleration / Activity Crashing with detailed step-by-step guidance.<ref name=Youtube>Youtube video of <i>Project Acceleration / Activity Crashing - Project Management</i>. Retrieved 26. September 2016 [https://www.youtube.com/watch?v=zg0-yzl3neY Available online]</ref> |frame}}</center>
  
* Do an example of project crashing.
+
== Advantages and Benefits of the CPM ==
* Show how you have to look at the critical path closely
+
  
== Benefits of CPM ==
+
The <b>critical path method (CPM)</b> has been widely used in planning, scheduling and monitoring of project progress by a variety of organizations and industries with great success. The advantages of the '''CPM''' are multiple which can be used as a framework  for project information and insight used by project managers and members concerning project time, cost and performance. Following is a list of advantages and benefit reasons of why <B>CPM</B> is utilized in organizations today: <ref name=Larson2014/><ref name= Anderson1986/><ref name=STELTH2009/><ref name=TheConstructor>The Constructor – Civil Engineering Home. <i>Advantages of Critical Path Method (CPM)</i>. Retrieved 16. September 2016 [http://theconstructor.org/construction/const-management/scheduling/advantages-of-critical-path-method-cpm/6873/ Available Online] </ref>
  
Here I am going to write about the benefits of the method!
+
* The method encourages all project members to identify and graphically represent all various project activities that need to be accomplished together with their interrelationship and dependencies in a logical manner. This is beneficial in the planning stage since it requires that the project is thought through in sufficient details in the long range. This minimizes the chances of overlooking necessary project activities and goals.
  
* Benefits in planning, sceaduling and monitoring
+
*The network representation is a graphic visualization of the entire project flow, giving complete overview in which is understood by all members in the project. Furthermore, smaller project network diagrams can easily be modified or changed when unexpected events occur as the project progresses.
 +
 +
* The method provides an estimate of the minimum project duration together with scheduling of individual project activities needed to complete the project of interest in an efficient manner. Furthermore, the method also identifies the slack or the tolerance of delay without affecting the imposed completion time for individual activities.
  
== Limitations of CPM ==
+
* The method provides a basis for documentation standard and enhances the communication of project plans, schedules and time-cost performances. 
  
Here I am going to write about the limitation to the method.
+
* The method enables the identification of the critical path(s) and corresponding critical activities in which special attention should be on in the project due to risk of delay. This is extremely beneficial in the monitoring stage when tracking the project progress. That means regular updates on project status as well as the critical path(s) with the concept of network sensitivity in mind, since the critical paths do not necessary remain static for the life of the project.  
  
* Details known with certainty - make use of PERT, these detailes are not known with certenty so with combination of those two as mentioned in the Overview chapter
+
* The benefit of time-cost trade off optimization is possible with cost [normal and crash] information on each activity in the project. That is, the '''CPM''' can help to identify the steps to be taken in order to accelerate a project completion or identify the shortest possible time or least possible cost that is needed as well as the optimum point of time and cost.
 +
 
 +
* The method provides the basis for scheduling labor and equipment as well as budgeting the cash flow of the project.
 +
 
 +
== Disadvantages and Limitations of the CPM ==
 +
 
 +
Despite the multiple advantages and benefits of the <b>CPM</b> mentioned earlier, the method possesses of several limitations or disadvantages which can be listed as following: <ref name=Larson2014/><ref name=STELTH2009/><ref name=MindToolsPERT> Mind Tools. <i> Critical Path Analysis and PERT Charts.</i> Retrieved 15. September 2016 [https://www.mindtools.com/critpath.html Available online]</ref><ref name=BrightHub>Bright Hub Project Managmenet. (2013). <i>Advantages and Disadvantages of Critical Path Method</i>. Retrieved 17. September 2016. [http://www.brighthubpm.com/project-planning/60960-advantages-and-disadvantages-of-critical-path-method/ Available online]</ref>
 +
 
 +
* The '''CPM''' and the analysis process can become extremely complicated  as the scope and complexity of the project increases and without a software it might be hard to manage. For large and complex projects, there can be thousands of activities and dependency relationships and the risk of making a mistake in the network computation becoming very high.
 +
 
 +
*The '''CPM''' and network diagrams are highly dependent on information technology and computer software in which can be of high initial and usage cost for organizations.
 +
 
 +
*The method does not include labor, equipment scheduling and resource allocation, only provides the basis for it. 
 +
 
 +
*The method requires time in order to develop the project network and relies heavily on project managers and members involved in that stage. Poorly defined project scope and activities can result in ineffective use of '''CPM''', which becomes difficult to manage.
 +
 
 +
*The method operates based on the assumption that the duration time of individual activities in the project are known with certainty, which may not always be the case. This is where the network technique variation of '''CPM''', <span class="plainlinks">[https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique <b>PERT</b>]</span> can be useful which takes more skeptical view of the time needed to complete an individual activity.
 +
 
 +
*The method cannot effectively handle changes in the project plan during the project execution. Changes require that the project network is redrawn and the computation process repeated according to new information midway in the project.
 +
 
 +
*Critical path(s) is/are not always clear and can sometimes be hard to identify and follow when monitoring the project progress. Constant review of the network diagram is necessary to identify the shifting and movement of the critical path(s) over time.
 +
 
 +
==Annotated Bibliography==
 +
 
 +
<b>Project Management Institute. (2008). A Guide to the Project Management Body of Knowledge.</b><ref name=PMI2008/>
 +
 
 +
This is a recognized formal standard for the project management profession and describes established norms, methods, processes and practices for project, program and portfolio management.
 +
 
 +
<b>Larson, E. W & Gray, C. F. (2014). Project Management - The Managerial Process.</b> <ref name=Larson2014/>
 +
 
 +
This book provides a holistic, socio-technical view of project management and focuses on the integration of project management into the organization as a whole. The focus is on the essential tools and processes used to manage projects as well as the human dimension and how they interact to determine the effectiveness and outcomes of projects. <i>Chapter 6</i> focuses on the development of project plan and the use of project networks. In addition, the chapter builds on and extends the network technique by introducing different lag relationships between project activities. <i>Chapter 9</i> focuses on project duration reduction and consideration on time-cost trade-offs. For a detailed example of the project crashing procedure, the reader is recommended to look up pages 316-318. 
 +
 
 +
<b>Chapter on Deterministic Decision Models. (n.d.). Course material in Network Optimization at DTU autumn 2015. Project Scheduling: PERT/CPM.</b><ref name=NETWORK/>
 +
 
 +
This chapter based on Deterministic Decision Models is extremely good reading material for better understanding and knowledge of the two modeling techniques, PERT/CPM, as well as their connection/differences. It introduces the basics concepts and describes in a useful and comprehensive way the methodologies behind. Detailed example is provided on project crashing in which can be used as a continuation on the example provided above (<span class="plainlinks">[http://apppm.man.dtu.dk/index.php/The_Critical_Path_Method_(CPM)_in_Project_Management#CPM_Example <i>Chapter 3: CPM Example</i>]</span>) with relatively small changes. Furthermore, based on that example, the use of linear programming in project acceleration and project scheduling is introduced and explained with an example. 
 +
 
 +
<b>Anderson, E. B., & Hales, R. S., (1986). Critical Path Method Applied to Project Planning: Fire Economics Evaluation Systems (FEES).</b><ref name= Anderson1986/>
 +
 
 +
The article provides a good introduction of the critical path method as a technique for planning, scheduling and monitoring projects together with its advantages in all the three phases. It provides the basic knowledge of the methodology and the different steps that have to be taken. Additionally to what has been described above, the construction of time chart is embedded in the '''CPM''' method as one step. Furthermore, the article provides a short introduction on resource as well as time-cost analysis.
 +
 
 +
<b>Stelth, P. (2009). Project’s Analysis through CPM (Critical Path Method). Isles International University.</b><ref name= STELTH2009/>
 +
 
 +
The focus of the study is to understand and evaluate critical paths and critical chains in a project. The study identifies the salient features of the '''critical path (CPM)''' and critical chain method (CCM) together with potential problematic areas. Furthermore, it provides the reader with evaluation of the similarities and differences of the two methods,  the ability to use them in conjunction as well as the impact the two methods can have on project management. The study covers various points under each of those areas and provides the reader with good insight and knowledge by good and detailed discussion. For more detailed and good summation on the advantages and disadvantages of the <B>CPM</B>, the reader is recommended to look up pages 21-25.
 +
 
 +
<b>Elbeltagi, E. Construction Management - Chapter on Project Time-Cost Trade-Offs.</b><ref name=TRADEOFF/>
 +
 
 +
This chapter on project time-cost trade-off gives good understanding of the relationship between those two important constraints in a project.  It provides detailed discussion of the basic concepts of project & activity time-cost relationships as well as the project crashing procedure. The reader is highly recommended to look at the many different examples provided based on the project crashing procedure to exercise and gain further understanding.
  
 
== References ==
 
== References ==
 
<references />
 
<references />
 +
 +
[[Category:Project Management]][[Category:Scheduling]][[Category:Operations research]]
 +
[[Category:Management]][[Category:Planning]]

Latest revision as of 15:05, 18 December 2018

Developed by Selma Lind Jonsdottir


According to the Project Management Institute (PMI), project management is the application of knowledge, skills, tools and techniques to project activities in order to meet project requirements and objectives[1]. The challenging task of managing projects can be supported by an operation research technique called the Critical Path Method (CPM). The CPM is a mathematically-network based algorithm in which can be used for planning, scheduling and monitoring project progress.[2][3]

The technique developed in late 1950s utilizes information from a work breakdown structure (WBS) in a network representation to display interrelationships and dependencies between project activities that must be accomplished to complete a project. The technique is used for analyzing projects by determining the longest sequence of tasks through a project network, called the critical path. This determines the shortest possible time to complete the project as well as which activities should be given a particular focus within the project.[2][4]

Based on acquired information from the CPM, the next question could be if it is possible to shorten the project in order to finish within certain deadline and what is the least expensive way to do it. In today’s competitive environment, there is an increasing pressure to get projects done earlier and quicker, either from the very beginning, prior to setting the project baseline, or in the midst of project execution in order to get the project back on schedule. Comparison of the benefits by reducing project time with the total cost associated with it can often be a huge challenge for project managers, thus, the decision to reduce the project duration should be based on an analysis of the trade-offs between time and cost.[2][3][5]

Contents

[edit] Overview

[edit] Introduction

Organizations across the world and within different sectors have been using project management as a way to improve project results. The increased awareness and acceptance supports that the application of knowledge, skills, tools and techniques can have significant impact on project success.[1][6]

Figure 1: The Project Management Iron Triangle [7]

According to the ISO 21500 a project is defined as a “unique set of processes consisting of coordinated and controlled activities with start and end dates, performed to achieve project objectives. Achievement of the project objectives requires the provision of deliverables conforming to specific requirements.” [8]

Each and every project is carried out under certain constraints. The three constraints of cost, time and scope represent together the iron triangle of project management, which can be seen in Figure 1. Each constraint forms the vertices with quality as the central theme and together indicates that projects must be delivered within agreed time and cost and furthermore to meet the agreed scope and customer quality requirements. The three constraints are aligned and changes in one will likely affect the others, or impact the quality of the project. This emphasizes the importance of project management and its challenging area in which is not at all easy to deal with.[7][9]

Project management is accomplished through the appropriate application of five processes: [1]

  1. Initiating
  2. Planning
  3. Executing
  4. Monitoring and Controlling
  5. Closing

Each and every organization can be involved in a project of any size, duration and complexity level at any given time. It is notable that project planning, scheduling and monitoring is a major part involved in project management. Therefore the critical path method (CPM) can be of good support within the challenging process of managing projects and helps those involved to address questions such as: [10]

  • What is the (minimum) total time required to complete the whole project?
  • What are the (earliest and latest) start and completion times for individual activities in the project?
  • Which activities are critical and must be completed on time in order to complete the whole project on time?
  • How much delay is tolerated of non-critical activities without impacting the overall project schedule and project completion time?
  • With cost information on each activity: What is the least expensive way to reduce project duration in order to meet a targeted completion time?

All these questions are extremely valid and important to have under control when managing projects.

[edit] Background

The critical path method (CPM) is a mathematically-network based project modeling technique developed in late 1950s in order to plan, schedule and control large, complex projects with many activities. CPM is one approach of network techniques that has been widely used and was developed by a DuPont engineer Morgan R. Walker and a Remington Rand computer expert, James E. Kelly, Jr., to manage plant maintenance and construction work. Furthermore, PERT (Program Evaluation and Review Technique), a critical path network technique was developed simultaneously and independently from the CPM by the U.S. Navy for managing the Fleet Ballistic Missile (Polaris) submarine project. PERT is commonly used in conjunction with CPM and the two optimization techniques are often referred to collectively. [3][11][12]

The CPM technique has been used for many different forms of projects including construction of a new building, bridge or a road, construction of IT-systems, building of ships and research and development of new products. As can be imagined, these projects consist of multiple activities that have to be completed in order to finish the project as a whole. It is important to note that the methodology is normally not applied to real large scale and complex problems with many activities, since developing the project network and applying the technique can be extremely time consuming. Today, there exists project management software packages based on the methodology, for example Microsoft Project, which are used to calculate all completion times based on a input. The programs are further able to create a visualization of the whole project which is used to ease overview and understanding, as well as supporting the monitoring of the project. On the other hand, the methodology can easily be applied manually to smaller problems in which will be the case in this article. Despite what already mentioned, a knowledge of the concept is important, thus the ones who manage projects have to deal with multiple challenges within planning, coordinating and monitoring all project activities in order to complete the project of interest successfully within agreed time, cost and scope as well as according to customer quality requirements.[3]

[edit] Methodology

The Critical Path Method (CPM) can be divided into the following steps:

  • STEP 1: Developing the Project Network
  • STEP 2: Constructing the Project Network
  • STEP 3: The Computation Process of forward pass, backward pass and slack
  • STEP 4: Critical Path Identification
  • STEP 5: Update of Project Progress

The methodology will be explained step-by-step as well as with an example in Chapter 3: CPM Example.

[edit] Step 1: Developing the Project Network

When developing the project network, the following input requirements are needed in order to construct a network model of the project of interest: [13]

  • A list of all activities required to complete the project also known as the work breakdown structure (WBS)
  • The duration of each individual activity for completion
  • The dependencies between the activities

With this information, the critical path method (CPM) is able to determine the longest path of activities through the project network, defined as the critical path and the corresponding activities are defined as critical activities. Based on the fact that the entire project cannot finish until all the activities are completed, the longest path or the critical path gives also the minimum required time to complete the entire project.

[edit] Step 2: Constructing the Project Network

The second step involves drawing the project network by placing the activities that need to be completed in the right logical sequence based on their interdependencies. The CPM notation used for each and every activity in the project network can be seen in Figure 2. Therefore, for all activities in the network the following information is registered and/or computed:
Figure 2: Activity Notation in a Project Network [2]
  • ID: Identification code of individual activity based on the WBS
  • Description: Description of individual activity based on the WBS
  • Duration (DUR): Duration time of individual activity
  • Early Start (ES): The earliest starting time of an individual activity
  • Early Finish (EF): The earliest finishing time of an individual activity
  • Late Start (LS): The latest starting time of an individual activity
  • Late Finish (LF): The latest finishing time of an individual activity
  • SL (Slack): The tolerance of delay of an individual activity without affecting project completion date

[edit] Step 3: The Computation Process

The third step involves the two procedures of forward pass used to compute earliest times, ES and EF, and the backward pass used to compute latest times, LS and LF as well as slack computation. [2][10]

Forward Pass begins at the initial activity and traces each path through the network step-by-step, to the end of the last project activity/activities. An important rule of the forward pass procedure is that all immediate predecessors must be completed before a succeeding activity can start. That is, early start (ES) of an activity equals the largest early finish (EF) of the immediate predecessors.

For the starting activity/activities of the network, early start (ES) is set as ES = 0 (or some other known value) and each path is traced forward to the finishing activity/activities by applying EF = ES + DUR to all activities in the project network. When finished, the longest path denotes the project completion time for the plan, that is, largest EF = Total Time.

Backward Pass is initiated after the forward pass has been completed and starts with the last project activity/activities without successors and the late finish (LF) is set as equal to the maximum early finish (EF) of those activities. An important rule of the backward pass is that at the latest time a succeeding activity can start is only when all immediate predecessors are completed. That is, late finish (LF) for an preceding activity equals the smallest late start (LS) of the immediate successor activities.

With that in mind, each path is traced backward towards the initial starting activity/activities by applying LS = LF - DUR. When this has been applied to all the activities in the project network, the total slack of an activity can be determined by using SL = LS – ES or LF – EF. [10]

[edit] Step 4: Critical Path Identification

The critical path is of great importance since all critical activities must be completed as scheduled in order to meet the scheduled project completion time, that is, if an activity on the critical path is delayed, the project is delayed by the same amount of time. This is due to the fact that the activities on the critical path have a zero slack. Slack (SL) is defined as the amount of time an activity can be delayed without delaying the whole project. Therefore, project managers need pay close attention to the critical path activities, which can represent around 10% of all project activities, in order to ensure that they are not delayed and therefore put the entire project in the risk of being late. [2]

[edit] Step 5: Update of project progress

As the project progresses, the actual activity completion times will be known and the project network can be updated in order to include this information. It is important to note that a new critical path may emerge and changes may be made in the network if project requirements suddenly change. [14]

The emerge of new critical path is related to the sensitivity of a project network. A network is considered sensitive when it has one or more critical path(s) and/or non-critical activities with little slack and therefore it is more likely that the original critical path(s) will change once the project has started. On the other hand, a network is considered insensitive when it has one critical path and non-critical activities with very large slack, and therefore less likely that the critical path will change once the project has started. [2]

[edit] CPM Example

In order to gain understanding of the critical path method, the following example is provided.

[edit] Constructing the CPM Project Network

Table 1 provides the required information of Step 1, that is, 9 activities required to complete a project of interest as well as their dependencies and duration times. Based on those information, the projects needs can be translated into a network diagram in which the CPM can be utilized. The diagram in Step 2 graphically shows the project flow and precedence relationships among all project activities and gives the project manager a visual representation of the entire project.

Table 1: Project Information for the CPM
Activity Duration [Weeks] Predecessor Description
A
1
-
Constructing a base
B
5
A
Build and construct wall structure
C
4
A
Create bearings for the roof
D
10
B, C
Raise the roof
E
5
C
Isolate and close the walls
F
7
D, E
Insert windows and doors
G
5
B, D
Prepare floors and lay parquet
H
4
E
Prepare the outside area
I
6
G, F, H
Paint walls and interior

A network model of the project of interest represented in Table 1 can be seen in Figure 3 where all project activities have been placed in the right logical sequence based on their interdependencies and using the activity notation presented in Figure 2. This is the initial starting point of the critical path method before computation process, Step 3, takes place.


Figure 3: Network Representsation of the Project Example presented in Table 1

[edit] The CPM Computation Process

Following the CPM methodology presented earlier, the first step of the computation process is to perform the forward pass. Activity A has no predecessors and therefore we assume that the activity can start as soon as the project can start, at time 0. The earliest finish (EF) date for activity A can now be computed as 0 + 1 = 1. Activities B and C have activity A as their immediate predecessor with early start (ES) as 1 and early finish (EF) as 1 + 5 = 6 and 1 + 4 = 5. Activity D is a merge activity since it is preceded by both B and C. The early start (ES) of a merge activity depends on the largest early finish (EF) of all activities that merge to it, since the activity cannot start until both the predeceasing activities have finished. Therefore, early start of activity D is max(6(EF-B),5(EF-C)) = 6. By continuing the forward pass, the early start (ES) and early finish (EF) for all activities can be computed as shown in Figure 4. When the forward pass has been completed, it can be seen that the early finish (EF) for activity I, or the project in total is 29 weeks.

The second step in the CPM methodology is the backward pass starting with the last project activity, which in this case is I. The late finish (LF) of the finishing node I is set equal to its early finish (EF) of 29 weeks and late start (LS) can be computed as 29 - 6 = 23. The finishing node I is an immediate successor of activities G, F and H, hence the latest finishing (LF) time for all the three activities is set to 23 and their late starts (LS) are computed as 23 - 5 = 18, 23 - 7 = 16 and 23 - 4 = 19. Activity E is a burst activity since it is a immediate predecessor for both activities F and H. Hence, the late finish (LF) for activity E is controlled by the smallest late starts (LS) of the two succeeding activities since activity E cannot finish later than the latest start of an immediate successor. Therefore, late finish (LF) of activity E is min(16(LS-F),19(LS-H)) = 16. If the backward pass is continued until the starting node, the late start (LS) and late finish (LF) for all activities can be computed as shown in Figure 4.


Figure 4: Solution of the Project Example presented in Table 1 based on CPM - Critical Path: A - B - D - F - I

[edit] Slack Computation and Critical Path Identification

After the completion of forward and backward passes, it is possible to determine which activities can be delayed by calculating the slack for individual activities in the project network. The slack for activity A is 0 since there is no difference between ES/EF and LS/LF. On the other hand, the slack for activity C is 2 - 1 = 6 - 5 = 1. The slack for individual activities can be computed as shown in Figure 4. After the slack computation, the critical path can easily be identified as the longest path through the network with critical activities consisting of zero slack. The critical path in this example is: A – B – D – F – I. . That is, if an activity on the path is delayed, the project is delayed by the same amount of time.

[edit] Consideration of Time-Cost trade-offs

Figure 5: Project Time-Cost Trade-Off Curve. [15]

The consideration of time-cost trade-offs for a project is often considered an essential part of a complete Critical Path Method (CPM) analysis [16]. Based on acquired information from the CPM, the next questions could be if it is possible to shorten the project in order to finish within certain deadline and what is the least expensive way to do it. Project crashing is a procedure to identify the cost of reducing project duration so that comparisons can be made with the benefits of getting the project completed earlier. It requires information of the total project cost, which includes both direct and indirect costs. Shortening the project duration will normally increase the direct costs, which can be assigned directly to project activities and commonly represents labor, materials and etc. Meanwhile, a reduction in project duration indicates a reduction in indirect costs, necessary costs for doing work, which continues for the life of the project and is not related to individual project activities. Therefore, the time-cost trade-off analysis can help to identify the optimum cost-time point between increasing cost of individual activities and decreasing overall project costs. The outcome of such analysis results in a time-cost trade-off curve as shown in Figure 5 which furthermore shows that the optimum project duration can be determined as the project duration that results in the least total project cost. [17][18]


Figure 6: Activity Cost & Time Relationship.[10]

Simplified represensation of the relationship between activity duration and its direct costs can be seen in Figure 6. Normal time for an activity represents estimated activity duration under normal conditions retrieved from the CPM and normal cost refers to the corresponding cost of that activity, which implies minimum direct cost. Crashing refers to speeding up the duration of an activity and the crash time is the shortest possible time an activity can be completed in. The direct cost for completing an activity in its crash time is called crash cost and crash point represents the maximum time an activity can be compressed. The cost-time relationship is assumed to be linear as shown in Figure 6 and for each activity a crash cost per period can be derived as:


 \text{crash cost period}  =  \tfrac{\text{Crash Cost - Normal Cost}}{\text{Normal Time - Crash Time}}


That is, the slope gives information about the cost per unit of time for shortening an individual activity and therefore allows comparison of which critical activities to shorten in order to minimize the total direct cost. [2][10][17]

After having utilized the CPM, the procedure for project crashing involves the following steps: [10][17]

  1. Compute the crash cost per period for all activities in the project network
  2. Find critical path(s) and critical activities in the project network
  3. In the case of only one critical path, identify a critical activity with the smallest crash cost per period that can still be crashed. Otherwise, identify critical activity/activities from each critical path with the smallest crash cost per period, which can still be crashed.
  4. Reduce the duration of the critical activity/activities identified in step 3 by one time period.
  5. Reconstruct or adjust the project network based on changes made in step 4. Calculate the total costs = directs + indirect costs. Stop the procedure if the desired completion deadline is reached, otherwise return to step 3. Continue until the crash point has been reached, that is, no further shortening is possible.

An example of project crashing where the procedure is utilized and explained step-by-step is available in Chapter 8.7: Project Crashing. The procedure can be used as a continuation of the example that was provided above in Chapter 3: CPM Example, with a relatively small change. The only change required is that the duration time of activity A is set to 0 since it is considered as a dummy activity.

For additional knowledge and understanding, Video 1 below provides a detailed step-by-step guidance on the project crashing procedure. Good examples are as well provided in Chapter 8.4: Shortening Project Duration.

Video 1: Example of Project Acceleration / Activity Crashing with detailed step-by-step guidance.[19]

[edit] Advantages and Benefits of the CPM

The critical path method (CPM) has been widely used in planning, scheduling and monitoring of project progress by a variety of organizations and industries with great success. The advantages of the CPM are multiple which can be used as a framework for project information and insight used by project managers and members concerning project time, cost and performance. Following is a list of advantages and benefit reasons of why CPM is utilized in organizations today: [2][11][12][20]

  • The method encourages all project members to identify and graphically represent all various project activities that need to be accomplished together with their interrelationship and dependencies in a logical manner. This is beneficial in the planning stage since it requires that the project is thought through in sufficient details in the long range. This minimizes the chances of overlooking necessary project activities and goals.
  • The network representation is a graphic visualization of the entire project flow, giving complete overview in which is understood by all members in the project. Furthermore, smaller project network diagrams can easily be modified or changed when unexpected events occur as the project progresses.
  • The method provides an estimate of the minimum project duration together with scheduling of individual project activities needed to complete the project of interest in an efficient manner. Furthermore, the method also identifies the slack or the tolerance of delay without affecting the imposed completion time for individual activities.
  • The method provides a basis for documentation standard and enhances the communication of project plans, schedules and time-cost performances.
  • The method enables the identification of the critical path(s) and corresponding critical activities in which special attention should be on in the project due to risk of delay. This is extremely beneficial in the monitoring stage when tracking the project progress. That means regular updates on project status as well as the critical path(s) with the concept of network sensitivity in mind, since the critical paths do not necessary remain static for the life of the project.
  • The benefit of time-cost trade off optimization is possible with cost [normal and crash] information on each activity in the project. That is, the CPM can help to identify the steps to be taken in order to accelerate a project completion or identify the shortest possible time or least possible cost that is needed as well as the optimum point of time and cost.
  • The method provides the basis for scheduling labor and equipment as well as budgeting the cash flow of the project.

[edit] Disadvantages and Limitations of the CPM

Despite the multiple advantages and benefits of the CPM mentioned earlier, the method possesses of several limitations or disadvantages which can be listed as following: [2][12][21][22]

  • The CPM and the analysis process can become extremely complicated as the scope and complexity of the project increases and without a software it might be hard to manage. For large and complex projects, there can be thousands of activities and dependency relationships and the risk of making a mistake in the network computation becoming very high.
  • The CPM and network diagrams are highly dependent on information technology and computer software in which can be of high initial and usage cost for organizations.
  • The method does not include labor, equipment scheduling and resource allocation, only provides the basis for it.
  • The method requires time in order to develop the project network and relies heavily on project managers and members involved in that stage. Poorly defined project scope and activities can result in ineffective use of CPM, which becomes difficult to manage.
  • The method operates based on the assumption that the duration time of individual activities in the project are known with certainty, which may not always be the case. This is where the network technique variation of CPM, PERT can be useful which takes more skeptical view of the time needed to complete an individual activity.
  • The method cannot effectively handle changes in the project plan during the project execution. Changes require that the project network is redrawn and the computation process repeated according to new information midway in the project.
  • Critical path(s) is/are not always clear and can sometimes be hard to identify and follow when monitoring the project progress. Constant review of the network diagram is necessary to identify the shifting and movement of the critical path(s) over time.

[edit] Annotated Bibliography

Project Management Institute. (2008). A Guide to the Project Management Body of Knowledge.[1]

This is a recognized formal standard for the project management profession and describes established norms, methods, processes and practices for project, program and portfolio management.

Larson, E. W & Gray, C. F. (2014). Project Management - The Managerial Process. [2]

This book provides a holistic, socio-technical view of project management and focuses on the integration of project management into the organization as a whole. The focus is on the essential tools and processes used to manage projects as well as the human dimension and how they interact to determine the effectiveness and outcomes of projects. Chapter 6 focuses on the development of project plan and the use of project networks. In addition, the chapter builds on and extends the network technique by introducing different lag relationships between project activities. Chapter 9 focuses on project duration reduction and consideration on time-cost trade-offs. For a detailed example of the project crashing procedure, the reader is recommended to look up pages 316-318.

Chapter on Deterministic Decision Models. (n.d.). Course material in Network Optimization at DTU autumn 2015. Project Scheduling: PERT/CPM.[10]

This chapter based on Deterministic Decision Models is extremely good reading material for better understanding and knowledge of the two modeling techniques, PERT/CPM, as well as their connection/differences. It introduces the basics concepts and describes in a useful and comprehensive way the methodologies behind. Detailed example is provided on project crashing in which can be used as a continuation on the example provided above (Chapter 3: CPM Example) with relatively small changes. Furthermore, based on that example, the use of linear programming in project acceleration and project scheduling is introduced and explained with an example.

Anderson, E. B., & Hales, R. S., (1986). Critical Path Method Applied to Project Planning: Fire Economics Evaluation Systems (FEES).[11]

The article provides a good introduction of the critical path method as a technique for planning, scheduling and monitoring projects together with its advantages in all the three phases. It provides the basic knowledge of the methodology and the different steps that have to be taken. Additionally to what has been described above, the construction of time chart is embedded in the CPM method as one step. Furthermore, the article provides a short introduction on resource as well as time-cost analysis.

Stelth, P. (2009). Project’s Analysis through CPM (Critical Path Method). Isles International University.[12]

The focus of the study is to understand and evaluate critical paths and critical chains in a project. The study identifies the salient features of the critical path (CPM) and critical chain method (CCM) together with potential problematic areas. Furthermore, it provides the reader with evaluation of the similarities and differences of the two methods, the ability to use them in conjunction as well as the impact the two methods can have on project management. The study covers various points under each of those areas and provides the reader with good insight and knowledge by good and detailed discussion. For more detailed and good summation on the advantages and disadvantages of the CPM, the reader is recommended to look up pages 21-25.

Elbeltagi, E. Construction Management - Chapter on Project Time-Cost Trade-Offs.[17]

This chapter on project time-cost trade-off gives good understanding of the relationship between those two important constraints in a project. It provides detailed discussion of the basic concepts of project & activity time-cost relationships as well as the project crashing procedure. The reader is highly recommended to look at the many different examples provided based on the project crashing procedure to exercise and gain further understanding.

[edit] References

  1. 1.0 1.1 1.2 1.3 Project Management Institute. (2008). A Guide to the Project Management Body of Knowledge. 4th Edition. USA. ISBN 9781933890517
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 Larson, E. W & Gray, C. F. (2014). Project Management - The Managerial Process. 6th edition. USA: NY. ISBN 9781259010705
  3. 3.0 3.1 3.2 3.3 Larsen, J. & Clausen, J., (2009). Course material in Networks and Integer Programming Supplementary at DTU - Notes to Networks and Integer Programming. Retrieved 04. September 2016 from campusnet.dtu.dk
  4. Newbold, R.C. (1998). Project Management in the Fast Lane – Applying the Theory of Constraint. USA: FL. ISBN 9781498738064
  5. Sahu, K. & Sahu, M. (2014). Cost & Time and Also Minimum Project Duration Using Alternative Method International Review of Applied Engineering Research. 5(4), pp. 403-412. Retrieved 10. September 2016. Available Online
  6. Project Management Institute. (2010). The Value of Project Management. Retrieved 05. September 2016. Available Online Version
  7. 7.0 7.1 Wikipedia. The Project management Triangle. Retrieved 10.08.2016
  8. International Organization for Standardization (2012) ISO 21500 – Guidance on Project Management.
  9. Mind Tools. The Iron Triangle of Project Management. Retrieved 10. September 2016. Available Online
  10. 10.0 10.1 10.2 10.3 10.4 10.5 10.6 Chapter on Deterministic Decision Models. (n.d.). Course material in Network Optimization at DTU autumn 2015. Project Scheduling: PERT/CPM. Available online
  11. 11.0 11.1 11.2 Anderson, E. B., & Hales, R. S., (1986). Critical Path Method Applied to Project Planning: Fire Economics Evaluation Systems (FEES). United States Department of Agriculture. USA. Available Online
  12. 12.0 12.1 12.2 12.3 Stelth, P. (2009). Project’s Analysis through CPM (Critical Path Method). Isles International University. Retrieved 06. September 2016. Available Online
  13. Santiago, J. & Magallon, D. (2009). The Critical Path Method - (CEE 320 – VDC Seminar). Stanford University. Retrieved 06. September 2016. Available online
  14. SmartSheet. The Ultimate Guide to the Critical Path Method. Retrieved 18.08.2016 from SmartSheets online page
  15. Hegazy, T. (1999). Optimization of construction time – Cost trade-off analysis using genetic algorithms. Figure of Time-Cost Trade-Offs Retrieved 09. September 2016. Available online
  16. Panagiotakopoulos, D. A CPM Time-Cost Computational Algorithm for Arbitrary Activity Cost Functions. Department of Civil Engineering, McGill University, Montreal. Retrieved 20.08.2016.
  17. 17.0 17.1 17.2 17.3 Elbeltagi, E. Construction Management - Chapter on Project Time-Cost Trade-Offs. Retrieved 15. September 2016. Available online
  18. CPM Tutor. (2010). Time-Cost Trade-Off. Retrieved 15. September 2016 Available online
  19. Youtube video of Project Acceleration / Activity Crashing - Project Management. Retrieved 26. September 2016 Available online
  20. The Constructor – Civil Engineering Home. Advantages of Critical Path Method (CPM). Retrieved 16. September 2016 Available Online
  21. Mind Tools. Critical Path Analysis and PERT Charts. Retrieved 15. September 2016 Available online
  22. Bright Hub Project Managmenet. (2013). Advantages and Disadvantages of Critical Path Method. Retrieved 17. September 2016. Available online
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox