The dynamics of adversarial relations
(10 intermediate revisions by one user not shown) | |||
Line 1: | Line 1: | ||
+ | ''Developed by Vasile-Vlad Bereghi'' | ||
+ | |||
+ | |||
Control is one of the most important element of the dynamic of ''adversarial relations''. Clients are determined to, protect their benefits obtained through competitive tendering and to ensure that these benefits are not competed away by the contractor through opportunistic behavior. The attempts by clients to manage the problem of moral hazard and to reduce the scope of opportunistic behavior by the contractor have the tendency to generate vicious circles of adversarial behavior between parties.<ref name="winch">Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition "</ref>. The dynamic of adversarial relations created by the client's desire to get the 'best deal', can generate an escalation of the transaction costs while the costs of production seem to be pushed down. <ref name="curtis"> Curtis, B., Ward, S. and Chapman, C., CIRIA, (1989) "Roles, Responsibilities and Risks in Management Contracting. "</ref>. | Control is one of the most important element of the dynamic of ''adversarial relations''. Clients are determined to, protect their benefits obtained through competitive tendering and to ensure that these benefits are not competed away by the contractor through opportunistic behavior. The attempts by clients to manage the problem of moral hazard and to reduce the scope of opportunistic behavior by the contractor have the tendency to generate vicious circles of adversarial behavior between parties.<ref name="winch">Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition "</ref>. The dynamic of adversarial relations created by the client's desire to get the 'best deal', can generate an escalation of the transaction costs while the costs of production seem to be pushed down. <ref name="curtis"> Curtis, B., Ward, S. and Chapman, C., CIRIA, (1989) "Roles, Responsibilities and Risks in Management Contracting. "</ref>. | ||
Line 29: | Line 32: | ||
The professional system became a low-trust system in which all actors spend a growing portion of their time covering their rear rather than moving forward. | The professional system became a low-trust system in which all actors spend a growing portion of their time covering their rear rather than moving forward. | ||
− | Control is the most important element in the adversarial relations dynamic. Clients that are determined to ensure that keen prices are obtained through competitive tendering and are not | + | Control is the most important element in the adversarial relations dynamic. Clients that are determined to ensure that keen prices are obtained through competitive tendering and are not lost away to the contractors through opportunistic behavior, develop the role of - the quantity surveyor. An wide-ranging network of in-project cost control has been implemented, which given the fact that the contracts are fixed price, can do no more than manage the shape of the project cash-flow s-curve.<ref name="winch2">Winch, Graham M., Routledge, (2014) "Institutional reform in British construction: partnering and private finance "</ref>. In response to these techniques, the contractors have developed their own quantity surveying capabilities adding to site overheads and generating the twin hierarchy site management, i.e. with the site surveyor focusing on cost and the contract manager focusing on time and quality. Considering that costs are determined predominantly by design decisions taken throughout the competitive tendering and contract prices are fixed, there is little chance to reduce costs - the process being one of cost control, rather than cost reduction. |
=The dynamic of over-engineering= | =The dynamic of over-engineering= | ||
− | The dynamic of adversarial relations interacts with a second dynamic of over-engineering. Clients have developed a natural tendency to pass the complete | + | The dynamic of adversarial relations interacts with a second dynamic of over-engineering. Clients have developed a natural tendency to pass the complete liability for the design to their professional advisers. Designers can face the possibility of opportunistic behavior from contractors and wish to protect themselves from possible litigation for the defects in their design. The worry to reduce to a minimum the opportunistic behavior of the contractors pushes designers to define the product completely. Yet, the increased complexity and uniqueness of newer and newer projects combined with their inevitable lack of experience of site processes means that their specifications are not reflected on site conditions or the qualifications of the contractors. This is reflected through a rigidity in the design which is not optimized in relation to the problems of construction. The designers are encouraged to allow high safety margins in their design that lead to over-engineered thus costly, designs. |
− | The contractors on the other hand, in the absence of the ability to change the specification to better fit their capabilities, try to maximize their flexibility. This in turn | + | The contractors on the other hand, in the absence of the ability to change the specification to better fit their capabilities, try to maximize their flexibility. This in turn ceases the construction technology, preventing contractors to innovate in order to reduce the pressure on their margins. As a result, further opportunistic behavior occurs.<ref name="winch2">Winch, Graham M., Routledge, (2014) "Institutional reform in British construction: partnering and private finance "</ref>. |
=Challenges= | =Challenges= | ||
− | Competitive tendering despite its | + | Competitive tendering despite its priority on lowest price, was not delivering as a matter of fact low production costs instead was generating very high transaction costs. The requirement that the designs would be fully specified at tender, meant that extensive assumptions had to be made regarding: |
− | In real life, designs were rarely fully specified and changes were inevitable, and thus complex contracts had to be | + | - ''the capability of architects and expertise other designers in the technical details of a wide range of construction technologies.'' |
+ | |||
+ | - ''the ability of the client to keep requirements fixed over a period of years.'' | ||
+ | |||
+ | In real life, designs were rarely fully specified and changes were inevitable, and thus complex contracts had to be refined to enable such changes to be negotiated. Quantity surveyors became guardians of the contract on behalf of the client, trying to minimize the possibility of opportunistic behavior by contractors. Professionals paid on a fee, calculated as a proportion of the construction budget, are given no motivations to reduce budget, while contractors have no encouragement to offer a reduced budget. This is determined because there is no instrument in the lowest price tendering to share potential savings between those that can offer them and the client. The professional system slowly became a risk-shedding rather than a risk-sharing system<ref name="winch">Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition "</ref>. | ||
=From adversaries to partners= | =From adversaries to partners= | ||
− | By the early 1990s a considerable | + | By the early 1990s a considerable drive for change had built up. A series of reports raised serious questions about the organization of the professional system. An increasing number of renown international comparative studies of construction costs and methods, which are reviewed in Edkins et al. (1999) <ref name="edk">Edkins, A.J. and Winch, G.M. (1999) The Performance of the UK Construction Industry: An International Perspective,Bartlett Research Paper 4, London. </ref> contributed to an awareness that there were serious performance problems. |
− | One | + | One advancement that was persistenlty supported was that of ''partnering'' <ref name="barlow">Barlow, J., Cohen, M., Jashapara, A. and Simpson, Y. (1997) Towards Positive Partnering Policy Press, Bristol. </ref>, <ref name="bennett"> Bennett, J. and Jayes, S. (1998) The Seven Pillars of Partnering, Thomas Telford, London. </ref>, <ref name="cox"> Cox, A. and Townsend, M. (1998) Strategic Procurement |
in Construction, Thomas Telford, London.</ref>. Broadly, we can identify two forms of partnering: | in Construction, Thomas Telford, London.</ref>. Broadly, we can identify two forms of partnering: | ||
− | - ''single project partnering'', where the parties commit themselves to | + | - ''single project partnering'', where the parties commit themselves to tolerance in dealing with each other, together with the use of different forms of dispute resolution. |
− | - ''multi-project partnering'', which extends this | + | - ''multi-project partnering'', which extends this even more in order to realize the benefits of longer term relationships between clients and their suppliers. |
− | The tradition of appointment rather than competitive tendering for the supply of design services has meant that repeated relationships - even if never | + | The new tradition of appointment rather than the old once defined by competitive tendering for the supply of design services has meant that repeated relationships - even if never specified as partnering arrangements - have become the norm for architects and consulting engineers. While multi-project partnering is a major shift in the nature of the relationships between clients and their suppliers of site-related services. Partnering and the transformation of standard contracts focus on transaction governance, and by simply reducing transaction costs, important gains can be made as costs are reduced. Differences are resolved before they become conflict, and conflicts can be settled without expensive litigation. |
− | However, an important additional | + | However, an important additional gain of partnering is that it can provide the motivational context for innovation, and thus a direct attack on production costs. The vicious circle of audit and control and the focus on the lowest price, set up in the competitive tendering process largely removes the motivation for tenders to offer alternative ways of meeting client needs. Beneficial effects are strongest with multi-project partnering, but important benefits can also be realized in the single-project context.<ref name="winch2">Winch, Graham M., Routledge, (2014) "Institutional reform in British construction: partnering and private finance "</ref>. |
The evidence comes from the number of partnering agreements, which is rising rapidly, while some leading contractors are reporting that more than half of their work is obtained through partnering arrangements or negotiations. | The evidence comes from the number of partnering agreements, which is rising rapidly, while some leading contractors are reporting that more than half of their work is obtained through partnering arrangements or negotiations. | ||
Line 76: | Line 83: | ||
The British construction industry is presented and how it is presently going through a period of rapid change. This reference was used to present the history behind the development of the professional system. | The British construction industry is presented and how it is presently going through a period of rapid change. This reference was used to present the history behind the development of the professional system. | ||
− | '''(4)''' | + | '''(4)''' Edkins, A.J. and Winch, G.M. (1999) "The Performance of the UK Construction Industry: An International Perspective" ,Bartlett Research Paper 4, London. |
− | + | This paper synthesizes some of the information that exists around international construction industry productivity and competitiveness metrics as well as innovation strategies in order to help inform strategic planning for improving the U.S. construction industry. This reference was used in order to present a solution to the problem of adversarial relations. | |
+ | |||
+ | '''(5)''' Barlow, J., Cohen, M., Jashapara, A. and Simpson, Y. (1997) "Towards Positive Partnering." Policy Press, Bristol. | ||
+ | |||
+ | The report contains a huge amount of useful information about partnering. It presents case studies, research about partnering as well as benefits and pitfalls of partnering. This reference was used in order to provide with a solution to the adversarial relations dynamics. | ||
− | '''( | + | '''(6)''' Bennett, J. and Jayes, S. (1998) "The Seven Pillars of Partnering: A Guide to Second Generation Partnering", Thomas Telford, London. |
− | + | This book presents partnering as a set of strategic actions that deliver vast improvements in construction performance. It is driven by a clear understanding of mutual objectives and cooperative decision making by a number of firms, who are all focused on using feedback to continuously improve their joint performance. This reference was used to emphasize the importance of partnering. | |
− | '''( | + | '''(7)''' Cox, A. and Townsend, M. (1998) "Strategic Procurement in Construction: Towards Better Practice in the Management of Construction Supply Chains", Thomas Telford, London. |
− | + | This book explores the appropriateness of procurement strategies in certain situations. It provides a framework to help organisations develop segmented approaches in the management of their construction supply chains built on fit-for-purpose relationships. |
Latest revision as of 20:24, 20 November 2018
Developed by Vasile-Vlad Bereghi
Control is one of the most important element of the dynamic of adversarial relations. Clients are determined to, protect their benefits obtained through competitive tendering and to ensure that these benefits are not competed away by the contractor through opportunistic behavior. The attempts by clients to manage the problem of moral hazard and to reduce the scope of opportunistic behavior by the contractor have the tendency to generate vicious circles of adversarial behavior between parties.[1]. The dynamic of adversarial relations created by the client's desire to get the 'best deal', can generate an escalation of the transaction costs while the costs of production seem to be pushed down. [2].
In this article the dynamic of adversarial relations will be discussed in detail by, first presenting a short history for the adoption of the professional system and the evolution of the relations between professionals and the contractors. It will address the problem with the professional system and it will present the development of the adversarial relations dynamic as well as the over engineering dynamic. Last it will present the manner in which the construction industry has attacked this problem.
Contents |
[edit] History
The emergence of general contracting in Europe is associated with the housing crisis following World War II while in Britain this happened much earlier, during the first half of the 19th century after the civil war and the rebuilding of London after the great fire. A shift to 'contracting in gross', where a single contractor undertook the financial responsibility in a single contract for the entire work, had to be done because of the urgency in the building program. This required the development of a system of measurement, removed the master craftsmen from direct contact with the architect while the architects were required to produce complete designs before tender.[3].
In civil engineering this trend had a similar outcome in the adoption of the professional system. The building of infrastructure, like roads, railways and canals, was supported by private investments. The private promoters were sometimes landowners or other interested parties but in the railway sector they were mostly engineers. In the beginning, the works were divided into small lots which were carried out by local contractors, closely supervised by the engineers.
But during the 1st half of the 19th century, the role of the general contractor who took on a broader responsibility for the works emerged. Contractors increasingly took over the promotion task, raising the finance for speculative new lines while the momentum of railway building grew. The financial crisis of 1873, that triggered a depression in Europe and North America from 1873-1879 and even longer in some countries, took away much of the competitive advantage of the promoter-contractors. Clients became increasingly public authorities, while banks preferred to lend to governments and established companies rather than finance speculative projects. The consulting engineer became more important, while the enterprise increasingly took the form of the civil engineering contractor of today. [3].
The important feature of this new system was the general contractor undertaking works conceived by others which could be subject to an independent control. It was for the first time that the client could effectively transfer some of the risks inherent in the construction process to a project actor. The rise of the general contractor pushed those not included within its scope, to organize themselves on a professional basis.
The dynamic relationship between the professionals and the contractors was part of a more general trend in the mid 19th century, from a society dominated by entrepreneurial ideal towards the beginnings of a society dominated by the professional ideal.[3].
The development of the professionally organized consultant architect or engineer reimbursed on a fee basis, and the evolution of third parties as control actors responsible for regulating those activities that remained subject to market forces, was driven by the insulation of the activities facing highest uncertainty. The system that emerged in the 19th century is defined as the professional system.
[edit] The problem with the professional system
At its best, the professional system delivered high quality buildings, but delivered them slowly and expensively. As it was put under increasing pressure, its strengths became its weaknesses. By the 1960s, the professional system had become 'an establishment' more concerned with protecting its own interests than meeting client needs.
It was allocating roles, defining responsibilities, specifying liabilities and crucially, it was establishing the reward and penalty structure for the actors in the construction industry. The principal problem generated by this establishment was the double dynamic of adversarial relations and over-engineering.[1].
[edit] The dynamic of adversarial relations
The professional system became a low-trust system in which all actors spend a growing portion of their time covering their rear rather than moving forward.
Control is the most important element in the adversarial relations dynamic. Clients that are determined to ensure that keen prices are obtained through competitive tendering and are not lost away to the contractors through opportunistic behavior, develop the role of - the quantity surveyor. An wide-ranging network of in-project cost control has been implemented, which given the fact that the contracts are fixed price, can do no more than manage the shape of the project cash-flow s-curve.[3]. In response to these techniques, the contractors have developed their own quantity surveying capabilities adding to site overheads and generating the twin hierarchy site management, i.e. with the site surveyor focusing on cost and the contract manager focusing on time and quality. Considering that costs are determined predominantly by design decisions taken throughout the competitive tendering and contract prices are fixed, there is little chance to reduce costs - the process being one of cost control, rather than cost reduction.
[edit] The dynamic of over-engineering
The dynamic of adversarial relations interacts with a second dynamic of over-engineering. Clients have developed a natural tendency to pass the complete liability for the design to their professional advisers. Designers can face the possibility of opportunistic behavior from contractors and wish to protect themselves from possible litigation for the defects in their design. The worry to reduce to a minimum the opportunistic behavior of the contractors pushes designers to define the product completely. Yet, the increased complexity and uniqueness of newer and newer projects combined with their inevitable lack of experience of site processes means that their specifications are not reflected on site conditions or the qualifications of the contractors. This is reflected through a rigidity in the design which is not optimized in relation to the problems of construction. The designers are encouraged to allow high safety margins in their design that lead to over-engineered thus costly, designs.
The contractors on the other hand, in the absence of the ability to change the specification to better fit their capabilities, try to maximize their flexibility. This in turn ceases the construction technology, preventing contractors to innovate in order to reduce the pressure on their margins. As a result, further opportunistic behavior occurs.[3].
[edit] Challenges
Competitive tendering despite its priority on lowest price, was not delivering as a matter of fact low production costs instead was generating very high transaction costs. The requirement that the designs would be fully specified at tender, meant that extensive assumptions had to be made regarding:
- the capability of architects and expertise other designers in the technical details of a wide range of construction technologies.
- the ability of the client to keep requirements fixed over a period of years.
In real life, designs were rarely fully specified and changes were inevitable, and thus complex contracts had to be refined to enable such changes to be negotiated. Quantity surveyors became guardians of the contract on behalf of the client, trying to minimize the possibility of opportunistic behavior by contractors. Professionals paid on a fee, calculated as a proportion of the construction budget, are given no motivations to reduce budget, while contractors have no encouragement to offer a reduced budget. This is determined because there is no instrument in the lowest price tendering to share potential savings between those that can offer them and the client. The professional system slowly became a risk-shedding rather than a risk-sharing system[1].
[edit] From adversaries to partners
By the early 1990s a considerable drive for change had built up. A series of reports raised serious questions about the organization of the professional system. An increasing number of renown international comparative studies of construction costs and methods, which are reviewed in Edkins et al. (1999) [4] contributed to an awareness that there were serious performance problems.
One advancement that was persistenlty supported was that of partnering [5], [6], [7]. Broadly, we can identify two forms of partnering:
- single project partnering, where the parties commit themselves to tolerance in dealing with each other, together with the use of different forms of dispute resolution.
- multi-project partnering, which extends this even more in order to realize the benefits of longer term relationships between clients and their suppliers.
The new tradition of appointment rather than the old once defined by competitive tendering for the supply of design services has meant that repeated relationships - even if never specified as partnering arrangements - have become the norm for architects and consulting engineers. While multi-project partnering is a major shift in the nature of the relationships between clients and their suppliers of site-related services. Partnering and the transformation of standard contracts focus on transaction governance, and by simply reducing transaction costs, important gains can be made as costs are reduced. Differences are resolved before they become conflict, and conflicts can be settled without expensive litigation.
However, an important additional gain of partnering is that it can provide the motivational context for innovation, and thus a direct attack on production costs. The vicious circle of audit and control and the focus on the lowest price, set up in the competitive tendering process largely removes the motivation for tenders to offer alternative ways of meeting client needs. Beneficial effects are strongest with multi-project partnering, but important benefits can also be realized in the single-project context.[3].
The evidence comes from the number of partnering agreements, which is rising rapidly, while some leading contractors are reporting that more than half of their work is obtained through partnering arrangements or negotiations.
[edit] References
- ↑ 1.0 1.1 1.2 1.3 Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition "
- ↑ Curtis, B., Ward, S. and Chapman, C., CIRIA, (1989) "Roles, Responsibilities and Risks in Management Contracting. "
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 Winch, Graham M., Routledge, (2014) "Institutional reform in British construction: partnering and private finance. "
- ↑ Edkins, A.J. and Winch, G.M. (1999) The Performance of the UK Construction Industry: An International Perspective,Bartlett Research Paper 4, London.
- ↑ Barlow, J., Cohen, M., Jashapara, A. and Simpson, Y. (1997) Towards Positive Partnering Policy Press, Bristol.
- ↑ Bennett, J. and Jayes, S. (1998) The Seven Pillars of Partnering, Thomas Telford, London.
- ↑ Cox, A. and Townsend, M. (1998) Strategic Procurement in Construction, Thomas Telford, London.
[edit] Annotated bibliography
(1) Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition."
In chapter 6 of this book, "Motivating the project coalition", a detailed overview of the problem of moral hazard, how to manage the problem of moral hazard, contractual uncertainty and risk allocation and the dynamics of adversarial relations is presented. The reference was used in order to present the dynamics of adversarial relations and the dynamics of over engineering.
(2) Curtis, B., Ward, S. and Chapman, C., CIRIA, (1989) "Roles, Responsibilities and Risks in Management Contracting."
The reference was used to present how adversarial relations are created.
(3) Winch, Graham M., Routledge, (2014) "Institutional reform in British construction: partnering and private finance."
The British construction industry is presented and how it is presently going through a period of rapid change. This reference was used to present the history behind the development of the professional system.
(4) Edkins, A.J. and Winch, G.M. (1999) "The Performance of the UK Construction Industry: An International Perspective" ,Bartlett Research Paper 4, London.
This paper synthesizes some of the information that exists around international construction industry productivity and competitiveness metrics as well as innovation strategies in order to help inform strategic planning for improving the U.S. construction industry. This reference was used in order to present a solution to the problem of adversarial relations.
(5) Barlow, J., Cohen, M., Jashapara, A. and Simpson, Y. (1997) "Towards Positive Partnering." Policy Press, Bristol.
The report contains a huge amount of useful information about partnering. It presents case studies, research about partnering as well as benefits and pitfalls of partnering. This reference was used in order to provide with a solution to the adversarial relations dynamics.
(6) Bennett, J. and Jayes, S. (1998) "The Seven Pillars of Partnering: A Guide to Second Generation Partnering", Thomas Telford, London.
This book presents partnering as a set of strategic actions that deliver vast improvements in construction performance. It is driven by a clear understanding of mutual objectives and cooperative decision making by a number of firms, who are all focused on using feedback to continuously improve their joint performance. This reference was used to emphasize the importance of partnering.
(7) Cox, A. and Townsend, M. (1998) "Strategic Procurement in Construction: Towards Better Practice in the Management of Construction Supply Chains", Thomas Telford, London.
This book explores the appropriateness of procurement strategies in certain situations. It provides a framework to help organisations develop segmented approaches in the management of their construction supply chains built on fit-for-purpose relationships.