Theory of Constraint

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 15: Line 15:
 
Another assumption in TOC states that every business has at least one constraint. A constraint (in manufacture often called a bottleneck) is anything that prevents an organization from making progress towards its goal of earning money. See list of constraints in below table 1
 
Another assumption in TOC states that every business has at least one constraint. A constraint (in manufacture often called a bottleneck) is anything that prevents an organization from making progress towards its goal of earning money. See list of constraints in below table 1
  
Constraint table 1.
+
''Constraint table 1.''
  
  
Line 28: Line 28:
 
From previous sections we know that according to TOC in very process there is a constraint and that the total throughput can only be improved when the constraint is improved / eliminated. Accordingly, Goldratt introduced a “Five Focusing Steps” methodology to identify and eliminate constraints as well as being a tool for continuously improvement in the organization. See figure 1
 
From previous sections we know that according to TOC in very process there is a constraint and that the total throughput can only be improved when the constraint is improved / eliminated. Accordingly, Goldratt introduced a “Five Focusing Steps” methodology to identify and eliminate constraints as well as being a tool for continuously improvement in the organization. See figure 1
  
Figure 1 The Five Focusing Steps methodology
+
''Figure 1 The Five Focusing Steps methodology''
  
Table 2 Description of the steps in the Five Focusing Steps methodology.
+
''Table 2 Description of the steps in the Five Focusing Steps methodology.''
  
 
Goldratt introduced different tools to describe / analyse the process and to develop a constraint schedule to manage buffer inventory in an organization.  One of the most known is “Drum-Buffer-Rope” (DBR), which is a method of synchronizing a production to the constraint while minimizing inventory and work-in-process. Figure 2 illustrates an example of DBR.
 
Goldratt introduced different tools to describe / analyse the process and to develop a constraint schedule to manage buffer inventory in an organization.  One of the most known is “Drum-Buffer-Rope” (DBR), which is a method of synchronizing a production to the constraint while minimizing inventory and work-in-process. Figure 2 illustrates an example of DBR.
  
Figure 2 Example of DBR tool for CT tubes
+
''Figure 2 Example of DBR tool for CT tubes''
  
 
To protect a constraint (bottleneck) which in this example is the chroming process of a special tube (called CT) in a production line a certain buffer (level of inventory) is maintained ahead of this bottleneck. All other operations are subordinate to secure that the buffer is never idle. The drum is the constraint and the speed at which the constraint runs. It sets the beat (pace) of the process which - in the end - determines the throughput. The rope is a signal generated by the constraint indicating that some CTs have been consumed which triggers the start for new CTs to be processed in the flow.
 
To protect a constraint (bottleneck) which in this example is the chroming process of a special tube (called CT) in a production line a certain buffer (level of inventory) is maintained ahead of this bottleneck. All other operations are subordinate to secure that the buffer is never idle. The drum is the constraint and the speed at which the constraint runs. It sets the beat (pace) of the process which - in the end - determines the throughput. The rope is a signal generated by the constraint indicating that some CTs have been consumed which triggers the start for new CTs to be processed in the flow.

Revision as of 23:20, 21 September 2015

Abstract (no WIKI functionalities has been used in this version)

The underlying assumption of Theory of Constraint (TOC) is that the performance of a system constraint will determine the performance of the organization. A constraint is anything that limits or prevents higher system performance relative to the goal. The constraint is the weakest link in the chain. A Five Focusing Steps methodology is used to identify an eliminate constraints of an organization as well as being a tool for continuously improvement in the organization. Primarily we would find TOC and Constraint Management applied in manufacturing and scheduling where the speed of a constraint sets the pace of a process in a production line. However TOC was extended to apply an execution of a project as well.

1. General overview

The methodology Theory of Constraint (TOC) was introduced by E. Goldratt in the book “The Goal” in 1984 (REF5), but the roots of TOC can be traced back to the development of the software Optimized Production Technology OPT in the late 1970s (REF6, page 648).

1.1 Assumptions

A main assumption in TOC is that the primary goal of a business is to “make more money now and in the future without violating certain necessary conditions”. (REF, p 649) To obtain this goal according to TOC an organization can be measured and controlled by three measures: Throughput, operational expense and investment (originally called inventory). Throughput, which is the most important measure according to Goldratt, measures the rate at which an organization generates money through sales. Investment is the money tied up in physical things like inventory, equipment, real estate etc.) Whereas operating expense is money spent to create output other than variable costs (capacity cost, taxes, utilities etc.) Another assumption in TOC states that every business has at least one constraint. A constraint (in manufacture often called a bottleneck) is anything that prevents an organization from making progress towards its goal of earning money. See list of constraints in below table 1

Constraint table 1.


1.2 Two perspectives of TOC

TOC can be seen from two perspectives: the perspective of a business system and the perspective of an ongoing improvement process itself (REF6, p 649).


1.2.1 TOC as a Business System

Seen from a business system viewpoint TOC emphasizes change process implemented in three levels: the mindset of the organization, the measures that drives it and the methods employed within the organization (REF6, p. 649). From previous sections we know that according to TOC in very process there is a constraint and that the total throughput can only be improved when the constraint is improved / eliminated. Accordingly, Goldratt introduced a “Five Focusing Steps” methodology to identify and eliminate constraints as well as being a tool for continuously improvement in the organization. See figure 1

Figure 1 The Five Focusing Steps methodology

Table 2 Description of the steps in the Five Focusing Steps methodology.

Goldratt introduced different tools to describe / analyse the process and to develop a constraint schedule to manage buffer inventory in an organization. One of the most known is “Drum-Buffer-Rope” (DBR), which is a method of synchronizing a production to the constraint while minimizing inventory and work-in-process. Figure 2 illustrates an example of DBR.

Figure 2 Example of DBR tool for CT tubes

To protect a constraint (bottleneck) which in this example is the chroming process of a special tube (called CT) in a production line a certain buffer (level of inventory) is maintained ahead of this bottleneck. All other operations are subordinate to secure that the buffer is never idle. The drum is the constraint and the speed at which the constraint runs. It sets the beat (pace) of the process which - in the end - determines the throughput. The rope is a signal generated by the constraint indicating that some CTs have been consumed which triggers the start for new CTs to be processed in the flow.

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox