Risk management strategy

From apppm
(Difference between revisions)
Jump to: navigation, search
m
m
Line 34: Line 34:
 
== Definition of Risk ==
 
== Definition of Risk ==
 
PMBOK defines a risk as:
 
PMBOK defines a risk as:
"An uncertain event or condition that, if it occurs has a positive or negative impact on one or more project objectives such as scope, schedule, cost and quality" <nowiki><ref>1<ref></nowiki>.
+
"An uncertain event or condition that, if it occurs has a positive or negative impact on one or more project objectives such as scope, schedule, cost and quality" <ref>["A Guide to the Project Management Body of Knowledge ( PMBOK® Guide )—Fifth Edition"]<ref>.
  
 
== Risk identification ==
 
== Risk identification ==
Line 43: Line 43:
 
=== Identification methods ===
 
=== Identification methods ===
  
Instead of relying on experience and common sense, when determining the possible risks, taxonomy-facilitated brainstorming <nowiki><ref>1<ref></nowiki> could be used.
+
Instead of relying on experience and common sense, when determining the possible risks, taxonomy-facilitated brainstorming <ref>[NASA "NASA Risk management handbook"]<ref> could be used.
 
Brainstorming techniques includes:
 
Brainstorming techniques includes:
 
* Check-lists
 
* Check-lists
Line 51: Line 51:
 
These exercises should help the brainstorming and thought processes to identify risks.
 
These exercises should help the brainstorming and thought processes to identify risks.
  
Another method is to ask "What could go wrong?", and answer it when relating to the following subjects:
+
Another method<ref>[Department of Defence "Risk management guide for DOD acquisition]<ref> is to ask "What could go wrong?", and answer it when relating to the following subjects:
 
* Current and proposed staffing, design, process, resources, suppliers, dependencies, operational employment, ect.
 
* Current and proposed staffing, design, process, resources, suppliers, dependencies, operational employment, ect.
 
* Monitoring test results
 
* Monitoring test results
Line 86: Line 86:
  
 
{| class="wikitable collapsible"
 
{| class="wikitable collapsible"
! style="background:#d0e5f5" | Level
+
! style="background:#d0e5f5" | Probability level
 
! style="background:#d0e5f5" | Likelihood
 
! style="background:#d0e5f5" | Likelihood
 
! style="background:#d0e5f5" | Probability
 
! style="background:#d0e5f5" | Probability
Line 99: Line 99:
 
|-
 
|-
 
| 5 || Near certainty || ~90%
 
| 5 || Near certainty || ~90%
 +
|-
 +
|}
 +
 +
 +
{| class="wikitable collapsible"
 +
! style="background:#d0e5f5" | Impact level
 +
! style="background:#d0e5f5" | Technical performance
 +
! style="background:#d0e5f5" | Schedule
 +
! style="background:#d0e5f5" | Cost
 +
|-valign="top"
 +
| 1 || Minimal or no consequence to performance || Minimal or no impact || Minimal or no impact
 +
|-
 +
| 2 || Minor reduction in performance or supportability  || Able to meet key dates || Budget or unit production cost increases. '''<1% of budget'''
 +
|-
 +
| 3 || Moderate reduction in performance or supportability with limited impact in objectives.|| Minor schedule slip. Able to meet key milestones woth no schedule float. || Budget or unit production cost increases. '''<5% of budget'''
 +
|-
 +
| 4 || Significant degradation in performance or major shortfall in supportability. May jeopardize succes. || Critical path affected ||Budget or unit production cost increases. '''<10% of budget'''
 +
|-
 +
| 5 || Severe degradation in performance. Will jeopardize succes || Cannot meet key milestones ||Exceeds threshold '''>10% of budget'''
 
|-
 
|-
 
|}
 
|}

Revision as of 00:18, 28 November 2014

“When trouble is sensed well in advance in can be easily remedied; if you wait for it to show itself any medicine will be too late because the disease will have become incurable. As the doctors say of a wasting disease, to start with it is easy to cure but difficult to diagnose; after time… it becomes easy to diagnose but difficult to cure.” (Machiavelli, 1514) [1]

When dealing with a project, uncertainties are to be expected, whether the project is influenced by external or internal factors. If an unexpected event turns out to be harmful to the project it is in general terms considered to be a risk. A risk can be defined as the product of the probability of the risk and the impact of the risk. Should a problem be very likely to happen, but have a little or no impact on the project there is little reason in prioritizing the mitigation of the problem. For a problem having a high impact, but very low probability the need to mitigate this problem is likewise not a priority. The impact of a risk is however more severe than the probability. For instance are smaller injuries, which happen often, easier to accept than heavier injuries, which happen more seldom. The probability of a problem should however not be neglected. A common way to illustrated this is by playing a small game:

In the construction business many factors must by in order for the project to move forward. Six people are given a dice and a problem. Whenever a person rolls a 1 a problem has occurred which delays the project. Thus the probability of a problem happening is 1/6. The probability of no problem happening is:

5/6*5/6*5/6*5/6*5/6*5/6=(5/6)^6=0,33

This means that only a third of the time, the project will progress.

A useful risk management strategy comprises of the following steps:

  • Identify - Potential risks are identified.
  • Analyze - Identified risks are rated, related to probability and impact.
  • Assess - Analyzed risks are ranked and compared to each other to determine which risk to handle first.
  • Process - Solutions are found to counter effect the risks.
  • Monitor - During the project lifetime, identified risks are monitored and new, potential risks are identified.

This article will examine ways to do a successful risk management.

To help understanding the risk management processes a example has been made to illustrate each chapters subject.


Example

Hidden text



Definition of Risk

PMBOK defines a risk as: "An uncertain event or condition that, if it occurs has a positive or negative impact on one or more project objectives such as scope, schedule, cost and quality" Cite error: Closing </ref> missing for <ref> tag