Bubble Diagram

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 1: Line 1:
Abstract
+
New title
''I am not really sure how it going to be written yet, so this “abstract” will be fairly loose.''
+
The role of Bubble Charts in Portfolio Management
  
The article will be a critical view on bubble chart (and maybe strategic bucket method) as visual tools in decision making regarding portfolio management.
+
=Introduction to Portfolio Management=
 +
In order to maintain a profitable business in the 21th century, an organisation must excel in countless fields, from strategic management to everyday planning and scheduling. One example of this is the interest that has been put in the area of project management for decades and for good reason []. It is evident that a company that does not have the capability to execute projects swift and efficiently will not be able to maintain a profitable business for long. Constant global competition, ever changing technologies together with shorter life cycles make rivalry even harder and it is not enough to execute projects right, but you also have to execute the right projects.  
  
The article will start with outlining the importance of portfolio management, emphasising on alignment of projects to support the corporate strategy and selection of best projects.
+
==What is Portfolio Management==
Thereafter an in-depth description of the model(s) and the different varieties that exist will be made.
+
Portfolio Management (PoMa) can be defined in many ways, and meaning and benefit of it is also somewhat dependent on in which area of business it is applied [].
A little look will be taken at the history, and why this method (these methods) was developed. (Feedback wanted – include both models or just the bubble chart?)
+
Robert et al. (1999) argues that for a company perspective PoMa is all about how to invest money in order to make more money. In practice this is showed when potential projects often have to compete for the scarce resources available as there usually are not enough resources to fund them all. The few projects chosen must therefore be perfect for the organisation. The use of PoMa can aid top management in the process of choosing the right projects to invest in. Choosing the right projects and building the best portfolio is much more complicated than selecting the most profitable projects based on a cost-benefit analysis, as the most profitable projects do not necessarily create the most profitable business.
 +
One of the most important trades of PoMa tools is how it can assist in making strategic choices. It is of greatest importance that all the projects, small as big, are aligned internally and do not counter work, but instead assist the overall corporate strategy [].
 +
Another trade of PoMa is the overview it can give regarding the current and future projects as well as products. This overview can be used to balance the portfolio in regards to risk in order to have a profile that suits the market that you operate in.
  
The main part of the article will have to do with the implementation and use of this method (these methods) in organisations. Through the description of the usage strengths and weaknesses, will be focused on. And if there are any common pitfalls, they will be emphasized in the end of this section
+
=Bubble Chart/Diagram=
This will lead to a more general discussion with a comparison to alternative models that exist and that maybe should be used instead of.  
+
The Bubble Chart (BC) is one of the tools that exist which can be used to support PoMa.
 +
A BC is a two-dimensional chart where bubbles are plotted instead of dots as in the regular xy-plot.  
 +
As it can be seen in Cooper et al (2001 - Class) the representation of the axes differs depending on which version that it used. However one version of the BC is clearly dominant with more than 44% of the ones using BC using this version. Other varieties can be seen in table…….
 +
In this version the horizontal axis represents the value some years after launch or simple referred to NPV or the rewards of the project. The vertical axis represents the probability of success.
 +
This create a chart that can be defined into 4 quadrant/areas, low-low, low-high, high-low and high-high. This has great similarity to the Boston Matrix made in 1970 by Bruce Henderson which (https://www.bcgperspectives.com/content/classics/strategy_the_product_portfolio/) also works as a tool to assist in portfolio decisions.
  
Lastly a look will be taken at the challenges of tomorrow and if these models can help with them or if new research is needed.
+
Apparent is it that the projects within the high-high area are often desired and opposite projects within the low-low quadrant are unwanted. The more complicated situation arrives of trade-offs are necessary in the low-high and high-low area. What is more attractive? Is it a high chance of success with small rewards or the low chance of success with high rewards?
  
 +
Besides the two axes the size of the bubble represent the resources needed in order to complete the project, or in other words, the total cost. It is important to notice that since the area of a circle grows with the quadrant of the radius, the cost should not be linear to the radius, but to the total size of the circle.
 +
Furthermore the colour of the bubbles might differ and it is therefore possible to distinct certain projects from each other no matter where they are located in the matrix. This can be very important if there is some kind of dependency as the projects and they should not all be compared but at the same time still wanted in the same chart.
 +
This combined gives the user the opportunity to observe four-dimensional information in a very easy and simple two-dimensional chart. This feature is what makes the BC different from many other tools as it provides the user much data in a fast and visual manner.
  
=Background=
+
=The use and implementation of a Bubble Chart=
A Bubble Diagram or bubble chart is a 2 dimensional chart where bubbles representing for example projects are portrayed.
+
The BC can be made on very different foundations from axes with precise numbers to just marking them with low or high. If the BC is just low-high much preparation might not be needed. A little portfolio board could discuss the different project in regard to the needed information and a BC could be made rather fast. However if the chart uses precise numbers, a lot of information needs to be processes before the bubbles can be plotted.  
The horizontal axis often represents NPV, net present value/the size of the rewards of the project.
+
Using the dominant design of a BC, the NPV, the resource requirement and the risk needs to be calculated. This is already a hard task in itself.
The vertical axis represents the chance of success. The interesting part is the actual bubbles that can vary in several ways.
+
Some projects might be tangible, but project that focuses on improving communication flow, can be hard to measure quantitatively. As the NPV then does not seem that impressive, this kind of project can have a tendency to not be prioritized.  
Typically the size of the bubble will represent the resources needed in order to complete the this project.
+
Secondly, the calculations of required resources are often being underestimated. This often connects to unexpected expenses but could also be a conscience choice from the project proposer as the project may seem more attractive. As crazy as this sounds this happens all the time [].  
The bubble can in the same time also vary in color which represents a strategic goals, or department etc.
+
Lastly the chance of success needs to be calculated. This is in practice done by calculating the unknown risk and this is always a tricky process. Some might use their gut feeling where other uses a 25 multi-criterion qualitative analysis as feed for a stochastic Monte Carlo simulation.
This combined gives the user the opportunity to observe 4 dimensional problem in 2 dimensions. This feature is what makes the bubble diagram different from many other tools as it provides much data in a very simple manner
+
  
===What is and How to cope with ineffective portfolio management?===
+
The Bubble Chart is a nice tool to create overview, but is only as good as the information put into it.
PM is to align strategy with the crating of new products or projects
+
Larger companies often experience a gap between corporate strategy and the actual performance
+
=What is a bubble diagram?=
+
A bubble diagram is a 2x2 matrix often with chance of success on one axis and the reward on the other. The size of the bubble then represent the resource cost. 
+
===history===
+
==What is the abundance of it?==
+
Used by 41 % only 8 % use it as their dominant tool.
+
It should maybe not stand alone as it is Supporting tool and cannot by itself alignment strategy.
+
 
+
=Developments and implementation!=
+
The important step in this phase is to figure how this should be used. The upstream processes needs to be in order so the necessary numbers are available for as a source for the diagram
+
 
+
==The use of bubble diagram in the organisation==
+
 
+
===What are the benefits?===
+
…to come
+
===What are the pitfalls?===
+
…to come
+
 
+
=Discussion and comparison to alternatives=
+
The bubble diagram is just one of the options that a company can use.
+
The scoring models seem more popular as it takes several more aspects into account.
+
However the bubble diagram gives a nice and visual representation that cannot be found anywhere else
+
 
+
=Conclusion=
+
Is it too hyped?
+
Is the benefit worth the time used for this?
+
 
+
==Additional reading==
+
 
+
==Bibliography==
+

Revision as of 16:29, 23 November 2014

New title

The role of Bubble Charts in Portfolio Management

Contents

Introduction to Portfolio Management

In order to maintain a profitable business in the 21th century, an organisation must excel in countless fields, from strategic management to everyday planning and scheduling. One example of this is the interest that has been put in the area of project management for decades and for good reason []. It is evident that a company that does not have the capability to execute projects swift and efficiently will not be able to maintain a profitable business for long. Constant global competition, ever changing technologies together with shorter life cycles make rivalry even harder and it is not enough to execute projects right, but you also have to execute the right projects.

What is Portfolio Management

Portfolio Management (PoMa) can be defined in many ways, and meaning and benefit of it is also somewhat dependent on in which area of business it is applied []. Robert et al. (1999) argues that for a company perspective PoMa is all about how to invest money in order to make more money. In practice this is showed when potential projects often have to compete for the scarce resources available as there usually are not enough resources to fund them all. The few projects chosen must therefore be perfect for the organisation. The use of PoMa can aid top management in the process of choosing the right projects to invest in. Choosing the right projects and building the best portfolio is much more complicated than selecting the most profitable projects based on a cost-benefit analysis, as the most profitable projects do not necessarily create the most profitable business. One of the most important trades of PoMa tools is how it can assist in making strategic choices. It is of greatest importance that all the projects, small as big, are aligned internally and do not counter work, but instead assist the overall corporate strategy []. Another trade of PoMa is the overview it can give regarding the current and future projects as well as products. This overview can be used to balance the portfolio in regards to risk in order to have a profile that suits the market that you operate in.

Bubble Chart/Diagram

The Bubble Chart (BC) is one of the tools that exist which can be used to support PoMa. A BC is a two-dimensional chart where bubbles are plotted instead of dots as in the regular xy-plot. As it can be seen in Cooper et al (2001 - Class) the representation of the axes differs depending on which version that it used. However one version of the BC is clearly dominant with more than 44% of the ones using BC using this version. Other varieties can be seen in table……. In this version the horizontal axis represents the value some years after launch or simple referred to NPV or the rewards of the project. The vertical axis represents the probability of success. This create a chart that can be defined into 4 quadrant/areas, low-low, low-high, high-low and high-high. This has great similarity to the Boston Matrix made in 1970 by Bruce Henderson which (https://www.bcgperspectives.com/content/classics/strategy_the_product_portfolio/) also works as a tool to assist in portfolio decisions.

Apparent is it that the projects within the high-high area are often desired and opposite projects within the low-low quadrant are unwanted. The more complicated situation arrives of trade-offs are necessary in the low-high and high-low area. What is more attractive? Is it a high chance of success with small rewards or the low chance of success with high rewards?

Besides the two axes the size of the bubble represent the resources needed in order to complete the project, or in other words, the total cost. It is important to notice that since the area of a circle grows with the quadrant of the radius, the cost should not be linear to the radius, but to the total size of the circle. Furthermore the colour of the bubbles might differ and it is therefore possible to distinct certain projects from each other no matter where they are located in the matrix. This can be very important if there is some kind of dependency as the projects and they should not all be compared but at the same time still wanted in the same chart. This combined gives the user the opportunity to observe four-dimensional information in a very easy and simple two-dimensional chart. This feature is what makes the BC different from many other tools as it provides the user much data in a fast and visual manner.

The use and implementation of a Bubble Chart

The BC can be made on very different foundations from axes with precise numbers to just marking them with low or high. If the BC is just low-high much preparation might not be needed. A little portfolio board could discuss the different project in regard to the needed information and a BC could be made rather fast. However if the chart uses precise numbers, a lot of information needs to be processes before the bubbles can be plotted. Using the dominant design of a BC, the NPV, the resource requirement and the risk needs to be calculated. This is already a hard task in itself. Some projects might be tangible, but project that focuses on improving communication flow, can be hard to measure quantitatively. As the NPV then does not seem that impressive, this kind of project can have a tendency to not be prioritized. Secondly, the calculations of required resources are often being underestimated. This often connects to unexpected expenses but could also be a conscience choice from the project proposer as the project may seem more attractive. As crazy as this sounds this happens all the time []. Lastly the chance of success needs to be calculated. This is in practice done by calculating the unknown risk and this is always a tricky process. Some might use their gut feeling where other uses a 25 multi-criterion qualitative analysis as feed for a stochastic Monte Carlo simulation.

The Bubble Chart is a nice tool to create overview, but is only as good as the information put into it.