Implementing Target Value Design
Line 46: | Line 46: | ||
===PDCA=== | ===PDCA=== | ||
PDCA (Plan-Do-Check-Act) is a four step model used to carry out change. The PDCA cycle should be repeated repeatedly for continuous improvement. The PDCA cycle is e.g. used when starting a new improvement project, when developing a new/improved design of a process/product/service and when planning data collection and analysis to find the root cause of a problem. Each procedure in the cycle is important: | PDCA (Plan-Do-Check-Act) is a four step model used to carry out change. The PDCA cycle should be repeated repeatedly for continuous improvement. The PDCA cycle is e.g. used when starting a new improvement project, when developing a new/improved design of a process/product/service and when planning data collection and analysis to find the root cause of a problem. Each procedure in the cycle is important: | ||
− | |||
− | |||
− | |||
− | |||
+ | * Plan: Acknowledge an opportunity and plan a change. | ||
+ | * Do: Test the change. | ||
+ | * Check: Review the test, analyze the results and identify what has been learned. | ||
+ | * Act: Action is taken. If the plan was successful, integrate what has been learned to broader changes which can then be used to plan new improvements. However, if the change didn’t go as planned, go through the cycle again with a different plan. | ||
+ | |||
+ | [[File: Politics.png |300px|thumb|right|top|Figure 5: Map of Stakeholders and their Relationship within an Organisation | ||
===The A3 Report=== | ===The A3 Report=== | ||
An A3 report is an orderly document and is so named because it fits on one side of an A3 size paper. The idea behind A3 was developed by Toyota in the 1960’s and has been used since for problem-solving, proposals, plans, and status reviews [1]. It is a tool that is used to achieve successful integrated project delivery (IPD). A3’s are meant to support the initiation, development, sharing and documentation of ideas and information in organizational aspect. A3s are well suited to address the necessity of different disciplines working together. A3 reports follow the PDCA (plan-do-check-act) cycle [2]. There are three main types of A3: | An A3 report is an orderly document and is so named because it fits on one side of an A3 size paper. The idea behind A3 was developed by Toyota in the 1960’s and has been used since for problem-solving, proposals, plans, and status reviews [1]. It is a tool that is used to achieve successful integrated project delivery (IPD). A3’s are meant to support the initiation, development, sharing and documentation of ideas and information in organizational aspect. A3s are well suited to address the necessity of different disciplines working together. A3 reports follow the PDCA (plan-do-check-act) cycle [2]. There are three main types of A3: | ||
+ | |||
1) Problem Solving | 1) Problem Solving | ||
+ | |||
2) Proposal | 2) Proposal | ||
+ | |||
3) Status | 3) Status | ||
+ | |||
Problem Solving A3 report (see figure) is the most common of the A3 reports. | Problem Solving A3 report (see figure) is the most common of the A3 reports. | ||
Revision as of 14:12, 8 March 2020
Target Value Design
Target Value Design (TVD) is a design process involving extensive collaboration between a broad reach of stakeholders; designers, builders, suppliers, estimators and Owners co-located in one place to collaboratively produce a design that provides the best value for the Owner. The Target Value (or budget), is the lead design criterion. The TVD process, is an iterative process where the design is repeatedly optimized to achieve the desired end product, without over running cost and time.
Contents |
Problem scope
The design and construction industry is widely known for having frequent and at times substantial cost and time overruns. This not only hurts the industries public image, but also weakens potential clients trust in projects meeting target values. Especially private clients may be troubled by the financial uncertainties as they will have bigger issues absorbing cost increases than public client will.
TVD is effectively meant to eliminate these overruns, creating an increased level of trust, higher client satisfaction and a better reputation for the company and the industry. As part of the process projects will be subjected to redesign (savings) as they do not meet client expectation in terms of total cost and time. The idea is to manage and steer the cost down to the Target Value. In some cases it may also show that the Target Value is inappropriately low and any real useful project delivery is not feasible within the Target Value, however, this would indicate lack of experience on the client and advisors part.
Irritative Design Process
The design process is an irritative process, which is meant to best optimise and deliver the final value for the client. Below is shown a flow chart of a TVD design process chart.
The initial five steps of the flow chart all concern establishing or verifying the clients project visualization and funds. It is apparent that the main constraint on a TVD project is the cost. The design is never moved forward with if the cost exceeds the Allowable Cost, and therefore, the design and construction of the project spend a lot of effort developing innovative solutions to make the project cheaper. If at the end of the process the cost have been driven down far enough so that there may be excess money available, the process changes to see if any value can be added for the remaining money. The final result will be an optimised design which costs as close to the target value as possible, but never more than the target value.
Contract Type
To achieve the greatest success in TVD projects, a shared risk contract should be used. A shared risk contract should at least include the client, principal designer and principal contractor as the signing parties. The contract should incentivise completing the project to the target value in the way of bonuses for the designer and contractor. In the instance that the project over runs costs, the designer and contractor should only be paid for their worked hours.
In case where organization may be prohibited to sign shared risk contracts – company/government policy etc. The client should instead create positive incentives in the way that when target milestones are successfully reached a monetary incentive is given/shared with the designers/contractors. The benefit of a shared risk contract is that it enhances the cooperation between designers and contractors to ensure that the design can also be constructed to the cost and time available. As every party is penalized I the project is not delivered contractors should naturally be more involved in the design process and designers in the construction phase.
Managing the Design Process
Research into Target Value Design and Delivery show that a good work and management culture is important to the success. Often used as good reference is LEAN management as first invented and implemented by Toyota. It is further advised to collocate the stakeholders, so that they naturally will cooperate more by being in the same room. The more of the stakeholder who can be present the better. In other words, if consultant designers and sub-contractors can be part of the initial design process as well then the smoother the design process is meant to be. Collocation has been shown to smooth out the design process, and help maximise the work not done, as designers can quickly consult contractors and draw on their expertise and knowledge of the cost to build the different design options.
It is also beneficial to have at least one person which is educated in LEAN management to help direct the colocation offices and meetings held, to ensure that everyone is encouraged to share their knowledge and expertise. Although the concept of irritative design processes to ensure a TVD may seem quite straight forward, there is a need for the project manager to closely steer the projects in the cost optimising direction so as to achieve a true TVD.
Concerns
A common concern regarding a transition to TVD within the AEC industry appear to be linked with quality and innovation. There is a concern that the quality will go down if the cost is kept low, and that there will be no space for innovation. However, people in the field suggest that the need to stick so closely to the target can in fact inspire the need for innovation in order to deliver a design to meet the quality required. Hence, some have found that it creates a larger drive for innovative solutions to cut the cost without demeaning the quality.
The companies who have implemented TVD appeared to meet resistance and scepticism from architects and engineers at first, but then once implemented received positive feedback and TVD.
Tools to implement TVD
SWOT
Fishbone diagram
SBCE
Business Case
Value Proposition Canvas
PDCA
PDCA (Plan-Do-Check-Act) is a four step model used to carry out change. The PDCA cycle should be repeated repeatedly for continuous improvement. The PDCA cycle is e.g. used when starting a new improvement project, when developing a new/improved design of a process/product/service and when planning data collection and analysis to find the root cause of a problem. Each procedure in the cycle is important:
- Plan: Acknowledge an opportunity and plan a change.
- Do: Test the change.
- Check: Review the test, analyze the results and identify what has been learned.
- Act: Action is taken. If the plan was successful, integrate what has been learned to broader changes which can then be used to plan new improvements. However, if the change didn’t go as planned, go through the cycle again with a different plan.
[[File: Politics.png |300px|thumb|right|top|Figure 5: Map of Stakeholders and their Relationship within an Organisation
The A3 Report
An A3 report is an orderly document and is so named because it fits on one side of an A3 size paper. The idea behind A3 was developed by Toyota in the 1960’s and has been used since for problem-solving, proposals, plans, and status reviews [1]. It is a tool that is used to achieve successful integrated project delivery (IPD). A3’s are meant to support the initiation, development, sharing and documentation of ideas and information in organizational aspect. A3s are well suited to address the necessity of different disciplines working together. A3 reports follow the PDCA (plan-do-check-act) cycle [2]. There are three main types of A3:
1) Problem Solving
2) Proposal
3) Status
Problem Solving A3 report (see figure) is the most common of the A3 reports.