The Gantt chart and the usage nowadays
(→Throwback) |
(→Throwback) |
||
Line 13: | Line 13: | ||
The first form of the <span class="plainlinks">[https://en.wikipedia.org/wiki/Gantt_chart Gantt chart]</span> was invented in 1890 and the man behind it was <span class="plainlinks">[https://en.wikipedia.org/wiki/Karol_Adamiecki Karol Adamiecki]</span>. Adamiecki was not widely known for his contribution to the Gantt chart because his work was published in Polish. However, 15 years later it was the turn of <span class="plainlinks">[https://en.wikipedia.org/wiki/Henry_Gantt Henry Gantt]</span> to develop a new version of this chart which took his name. The popularity of the new type of chart was so intensive in western countries that any other chart similar to this, tended to be associated with Henry Gantt by taking also his name. The main reason of why this chart was so well known is because of its use during the <span class="plainlinks">[https://en.wikipedia.org/wiki/World_War_I World War I]</span> by the <span class="plainlinks">[https://en.wikipedia.org/wiki/United_States United States]</span>. | The first form of the <span class="plainlinks">[https://en.wikipedia.org/wiki/Gantt_chart Gantt chart]</span> was invented in 1890 and the man behind it was <span class="plainlinks">[https://en.wikipedia.org/wiki/Karol_Adamiecki Karol Adamiecki]</span>. Adamiecki was not widely known for his contribution to the Gantt chart because his work was published in Polish. However, 15 years later it was the turn of <span class="plainlinks">[https://en.wikipedia.org/wiki/Henry_Gantt Henry Gantt]</span> to develop a new version of this chart which took his name. The popularity of the new type of chart was so intensive in western countries that any other chart similar to this, tended to be associated with Henry Gantt by taking also his name. The main reason of why this chart was so well known is because of its use during the <span class="plainlinks">[https://en.wikipedia.org/wiki/World_War_I World War I]</span> by the <span class="plainlinks">[https://en.wikipedia.org/wiki/United_States United States]</span>. | ||
− | |||
− | |||
[[File:Figure_0.png|300px|thumb|right|alt text]] | [[File:Figure_0.png|300px|thumb|right|alt text]] | ||
Revision as of 11:35, 19 September 2015
Introduction
This article has been created on behalf of the course 42433 Advanced Engineering Project, Program and Portfolio Management E15 and the assignment that all the students have been enrolled to the course have to deliver before 29/09/2015. The article has been defined and it should follow the following structure:
- Big Idea: In this chapter a description about Gantt chart will be given. More detail, a throwback about this project management tool and the fields that it is used. In addition to that, the theory that this tool is based on will be described and finally how this theory reflects on the use of Gantt chart.
- Application: This is the second chapter of the Wiki article and here it will be explained how to use the Gantt chart. To be more effective the illustration of the methodology, an exercise with the whole solution is going to be provided and explained step by step. Moreover, the usage of the tool nowadays and how it has been changed with the passage of time will be explained while finally a discussion about how Gantt chart is related with other methods will be listed.
- Limitations: This is the final chapter of the Wiki article and here it will be explained the limitations and the drawbacks by using the Gantt chart. However, except these disadvantages, there are lots of benefits by the usage of this chart which are considered relevant to be in the same chapter.
- Annotated bibliography: This is the literature that the article is based on. All the references (3-10) have to be reported and regarding this, a small abstract per reference should be written in order to explain where each of it has contributed for this article to be written.
Contents |
Big Idea
Throwback
The first form of the Gantt chart was invented in 1890 and the man behind it was Karol Adamiecki. Adamiecki was not widely known for his contribution to the Gantt chart because his work was published in Polish. However, 15 years later it was the turn of Henry Gantt to develop a new version of this chart which took his name. The popularity of the new type of chart was so intensive in western countries that any other chart similar to this, tended to be associated with Henry Gantt by taking also his name. The main reason of why this chart was so well known is because of its use during the World War I by the United States.
Methodology
The Gantt chart provides a graphical representation of a project that helps the design, the coordination and the specialization of works on a project. A Gantt chart is constructed with a horizontal axis representing the total time span of the project, which is divided into intervals (days, weeks, or months) and a vertical axis representing the tasks that make up the project. The usage of Gantt chart makes necessary the development of a plan. It is very easy to be used because no special design skills are required to be designed and this was one of the reasons that became widely accepted. Designing a project on a chart, helps the involvers easily notice what are their responsibilities of each one of them and in addition to that, when to start the job they are assigned to work and when to have to finish it. The layout is easy to read by all involved on it and not only to its creator. The Gantt chart shows what has been done on a project based on the initial design and at what stage is the execution. Moreover, it records the progress of the project based on time. Even if something is not in parallel with the initial timetable but there are delays, the chart can show which activity is scheduled fault.
Application
Usage
Example
In order to understand how the theory is applied to practice, it is appropriate to cite a virtual example of project of the Technical University of Denmark. This example does not have any relationship with any events or similarities of reality.
Exercise
The Organization and Management Department of the Technical University of Denmark organizes one-day conference on the "Electronic commerce". The organizing committee has set out what needs to be done and the challenge is to identify how many days are needed for the preparation of the conference. Also keen to establish a program of the event, which will help it to carry out its target within accepted timeframes and simultaneously will allow it to control all intermediary activities. The table below shows the immediately foregoing activities required for the organization of the workshop.
Solution
To manage the timing of the project and in order the critical path to be calculated, the applied method is PERT/CPM. The results of calculations appear in the following table.
It is observed that the activities B, C, D, H J and L are critical and they combine the critical path. These activities must be completed as they initially planned, otherwise the organizing of the workshop will be delayed. The sum of the length of the activities of the critical path is 53 days no matter how much is the earlier or the slower time of expiry of the critical activity L. Therefore, the organizing committee should start the preparations at least 53 days before the scheduled day of the event, so they can carry out all the necessary activities.
In the underneath figure is given the Gantt chart for this project. The duration is in days.
On the following table it is described the earliest start of each activity. However, there are tasks which can be delayed without affecting the whole process of the project. This figure is lying below. The duration is in days.
Finally, in order to be understood the difference between the earlier and the slower starting time, a figure with four different colours is given. Black colour is for the earlier start of a task, red colour is for the latest start, orange colour is when the ending of the earlier start matches with the beginning of the slower start of an activity, while the green colour is the critical path where the activity cannot be delayed. This snapshot is given beneath. The duration is in days.
Usage Nowadays
Nevertheless the Gantt chart withstood the test during the passage of time. Changes were made and weaknesses improved. Milestones were added showing specific points in time (mainly six months) during which, tasks have to be completed and indexes showing when this activity had started and when it ended. Over on solid rods, signs are placed indicating the importance of each task (critical controls, revisions). In this case, the units of time are placed by dates. The relations of interdependence of individual operations may be displayed with arrows connecting rods (operations) making by that the Gantt chart a network. However, there are lots of times that it is simpler to have separately the Gantt chart from the relationship network of the project.
Software
Technology is changing at a very fast pace and graphs which were displayed manually in sheets of paper before, have been replaced by programs nowadays. Such programs are the followings:
Using this kind of software, users' lives have been facilitated and in principal, they can save time and control better the outcome of a plan. In the past, it was very time consuming for managers to draw a project and the whole processes of it, mainly because of the changes happened during this, since the project should be drawn from the beginning.
The following video shows how Gantt chart is constructed using the smartsheet.
Discussion
discuss how other project management methods related to Gantt charts (e.g. how it needs a WBS, relationship to network plans, critical path etc.)
Limitations
Cons
- Gantt charts do not have great intelligence capabilities, so commonly they are used in less complex projects. That is happening because they are insufficient in project planning, because the interdependencies of individual works are not shown. In other words, it is not evident which tasks should be completed to allow the start of execution of a certain work which is linked with the previous one. Moreover it does not show the effect of a delay or acceleration in some phase of the project.
- Another drawback is the difficulty in the adjustment when changes occur in the period of execution of some actions or activities. In addition to that, there is the difficulty of implementing them in projects with a large number of actions, because of the considerable space required by the portrayal.
- Even there is weakness in the depiction of the interdependencies among the activities of the projects.
- The final disadvantage is the inability for the presentation of critical actions or activities for the successful completion of the entire project.