Risk Breakdown Structure (RBS)
CrewMember (Talk | contribs) (→Risk identification) |
CrewMember (Talk | contribs) (→Risk identification) |
||
Line 18: | Line 18: | ||
Risk identification is the process of systematically and continuously identifying, categorizing, and assessing the initial significance of risks associated with a project <ref name="Systematic Risk Management Approach for Construction Projects">Al-Bahar, J.F. and Crandall, K.C. (1990), "Systematic Risk Management Approach for Construction Projects", Journal of Construction Engineering and Management</ref>. Risk identification describes risks that can potentially affect the project. | Risk identification is the process of systematically and continuously identifying, categorizing, and assessing the initial significance of risks associated with a project <ref name="Systematic Risk Management Approach for Construction Projects">Al-Bahar, J.F. and Crandall, K.C. (1990), "Systematic Risk Management Approach for Construction Projects", Journal of Construction Engineering and Management</ref>. Risk identification describes risks that can potentially affect the project. | ||
− | + | Participants in risk identification activities can be the following: project manager, project team members, risk management team (if assigned), experts that are not member of project, customers, end users, other project managers, stakeholders, and risk management experts | |
+ | <ref name="Project risk identification and assessment simultaneously using multi-attribute group decision making technique", Mojtahedi, Mohammad & Mousavi, Sana & Makui, Ahmad. (2010). "Project risk identification and assessment simultaneously using multi-attribute group decision making technique", Safety Science</ref> | ||
Revision as of 16:28, 19 February 2022
Developed by Dimitrios Machairas
A Risk Breakdown Structure is a tool that depicts in the form of a graph the risks a project might face as it develops. Commonly, this tool's structure follows a hierarchical representation of risk, starting with the top levels and consequently moving down to more specific risks. The scope of this tool is to help project managers map out the possible risk exposure of the project - every parameter that might affect the regular progression of the project.
Risk Breakdown Structure (RBS) is a tool developed by Dr. David Hillson and he describes it as: "A Source-oriented grouping of project risks that organize and defines the total risk exposure of the project. Each descending level represents an increasingly detailed definition of sources of risk to the project."
Contents |
Introduction
Risk management is a systematic process of identifying, assessing and responding to project risk [1]. The overall goal of the risk management process is to maximize the opportunities and minimize the negative consequences of risk threats [1]. Project Risk Management aims to identify and prioritize risks in advance of their occurrence and provide action-oriented information to project managers. This orientation requires consideration of events that may or may not occur and are therefore described in terms of likelihood or probability of occurrence in addition to other dimensions such as their impact on objectives [2]
Risk identification
A risk cannot be managed unless it is first identified. Consequently, after risk management planning has been completed, the first process in the iterative Project Risk Management process aims to identify all the knowable risks to project objectives [1].
Risk identification is the process of systematically and continuously identifying, categorizing, and assessing the initial significance of risks associated with a project [3]. Risk identification describes risks that can potentially affect the project.
Participants in risk identification activities can be the following: project manager, project team members, risk management team (if assigned), experts that are not member of project, customers, end users, other project managers, stakeholders, and risk management experts Cite error: Closing </ref> missing for <ref> tag
Project Risk Management is defined as: “Project Risk Management includes the processes concerned with conducting risk management planning, identification, analysis, responses, and monitoring and control on a project.”[1] “The objectives of Project Risk Management are to increase the probability and impact of positive events, and decrease the probability and impact of negative events in the project.”[1]
In the PMBOK® Guide – Fourth Edition, “project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives.”[1]
Project Risk Management (PRM) is a systematic process of identifying, assessing and responding to project risk. The overall goal of the risk management process is to maximize the opportunities and minimize the negative consequences of risk threats.
Relation with Work Breakdown Structure (WBS)
Risk Breakdown Structure Template Example
How to Use the RBS
Risk identification aid
Risk assessment
Risk reporting
Drawbacks of the RBS
References
Hillson, David. (2003). Using a Risk Breakdown Structure in project management. Journal of Facilities Management. 2. 85-97. 10.1108/14725960410808131.
Munier, Nolberto. (2014). Risk management for engineering projects: Procedures, methods and tools. 10.1007/978-3-319-05251-9.
Project Management Institute. (2008). A Guide to the Project Management Body of Knowledge
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 Project Management Institute, (2009),"A Guide to the Project Management Body of Knowledge - Fourth Edition"
- ↑ Project Management Institute. (2009). "Practice standard for project risk management. Newtown Square"
- ↑ Al-Bahar, J.F. and Crandall, K.C. (1990), "Systematic Risk Management Approach for Construction Projects", Journal of Construction Engineering and Management