The Rolling-Wave planning technique

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 6: Line 6:
 
The aim of this article is to contribute to the profession of project, program and portfolio management in:
 
The aim of this article is to contribute to the profession of project, program and portfolio management in:
 
#Understanding the purpose, importance and principles of The Rolling-Wave technique.  
 
#Understanding the purpose, importance and principles of The Rolling-Wave technique.  
#Identifying the key characteristics and major aspects.
+
#Identifying its key characteristics and major aspects.
#Recognizing the boundaries and limitations.  
+
#Recognizing its boundaries and limitations.  
  
  

Revision as of 12:37, 12 February 2023

Innovation and product development projects have environments characterized by many unknowns and rapid change. Recently, an emerging set of practices termed agile product development has caused traditional orthodox product developers and project managers to rethink their approach to creating fast and flexible projects [1]. As stated in The PDMA ToolBook 3 for New Product Development, flexibility is one of the most important corner stones whenever considered the project planning. Moreover, in new-product development, most management approaches presume a high ratio of knowns to unknowns , and most planning defines prescribed pathways through developmental stages and decision gates [2]. At the same time, project environments reflect a very low amount of information at the beginning of the project, when the decisions importance is more relevant, while it increases as the project lifecycle is developed.

To counter with this paradox, the Rolling-Wave technique is one of the newer agile tools that has been widely adopted as it yields benefits of improved speed, flexibility and customer value. Rolling wave is a robust, sophisticated way to manage the risks of innovation, to adapt to change, to align the organization, and to align the team towards breakthrough reults [1]. Recognizing that not all the aspects of a project can be fully defined or known at the starting stage, the Rolling-Wave planning allows the progressive elaboration of all the details as far as the project go on. The project management profession has used the term rolling wave referring to the expression "plan a little, do a little" to characterize its use of iteration along the project lifecycle[1].

The aim of this article is to contribute to the profession of project, program and portfolio management in:

  1. Understanding the purpose, importance and principles of The Rolling-Wave technique.
  2. Identifying its key characteristics and major aspects.
  3. Recognizing its boundaries and limitations.


Developed by Gianluca Santinon

Contents

Overview of the Rolling-Wave technique

The Rolling-Wave technique: three main principles

Principle One: Project and Product Architecture

Principle Two: Uncertainty and Ambiguity

Principle Three: A functioning team with good leadership

Implementation of The Rolling-Wave technique

Step One: Get the team and strategy in place

Step two: Perform Top-Down planning, starting with the Level 1 of the Work Breakdown Structure

Step three: Decompose the first set of "Plan a Little" activities

Step four: The baseline

Step five: Execute the planned work

Step six: Iterate through the planning horizons and close the project

Real-life case study

Limitations

Annotated Bibliography

References

  1. 1.0 1.1 1.2 Project Management Institute, Inc. (PMI)., "The PDMA ToolBook 3 for New Product Development", 2008
  2. Mark P. Rice, Gina Colarelli O'Connor, Ronald Pierantozzi,"Implememnting a Learning Plan to Counter Project Uncertainty "], MIT Sloan Management review, Winter 2008