Management of remote project

From apppm
(Difference between revisions)
Jump to: navigation, search
(Technical issues)
Line 30: Line 30:
 
Then, people from different countries use different technologies. Americans will prefer Microsoft Office and the Chinese more open-source software.When the team are in the same building, those problems generally will be resolved by day-to-day communication<ref name=Monica> </ref> but for remote project it will be impossible. Therefore, a clear definition of which programs should be used must be done before starting the remote project.
 
Then, people from different countries use different technologies. Americans will prefer Microsoft Office and the Chinese more open-source software.When the team are in the same building, those problems generally will be resolved by day-to-day communication<ref name=Monica> </ref> but for remote project it will be impossible. Therefore, a clear definition of which programs should be used must be done before starting the remote project.
  
=== Project management ===
 
 
= One solution: a cluster approach =
 
= One solution: a cluster approach =
  

Revision as of 20:21, 15 September 2016

Coordination of Remote Project on Dangerous site: a cluster approach

Aid workers are subject to multiple attacks. Acting in insecure area could mean for the NGO (Non-Governmental Organization) huge expenses in security management. Thereby more of them prefer use remote management to secure their international staff in a secure place. However, the remote control or remote management can lead to risk transfer to local team, wrong accountability or monitoring. Generally, whole those consequences are due to a bad planning and remote control was implemented in emergency situation. However, if it’s implemented and correctly planned in the early stage of the project it could really help the NGO to still provide aid to highly insecure area.

Moreover, all the lessons learned from the aid remote project can be adapted to general companies. The cluster approach could be one of the method to introduce a more predictable and accountable means for coordination by formalising the lead role to some specific organisation. Cluster management cycle is important to understand and implement in order to achieve the common aim. Indeed, with our virtual and globalized world companies tend to have more geographically dispersed teams. Moreover, some companies are working with university in knowledge clusters. Those teams face some of the same problems of the local aid workers. Some recommendations will be described in order to learn from the lessons of the NGO who have faced similar problems.


Contents


Remote Project Management

Remote project management or remote control is defined as reducing or restricting movement or withdrawing internationals (or any other staff at particular risk) while shifting responsibilities for programme delivery to local staff or local partners. [1]. It was first adopted in the conflict in early 1980s. However, only few documents explained the good practice of this kind of management and how to succeed. ‘Remote control’, ‘remote support’ and ‘remote partnership’ and ‘limited access programming’ are different concept for remote management that it could be find in the literature [2]

Key Challenge in the Coordination of dispersed teams

The key challenge for international NGO's is to deal with geographically dispersed team and all the consequences. They would prefer to be on the field for a more effective action but due to insecurity reasons they have to oversee the activities from another location. Thereby to continue to pursue a humanitarian imperative principle [3]: getting aid to those in need as the first priority-even if it must be done from a distance. This kind of management has several negative side as risk transfer on local team or poor quality and coordination. But those are due to a short-term decision-making attitude. The cluster approach that will be explained latter resolve some of these drawbacks.

Trust

As local NGO should have trust in their international management, dispersed teams should have the same behavior with the Head Offices. It enforces the formation of cohesiveness between team members. If there is not enough trust between the teams, they will have some difficulties to face challenge and even sometimes blame each other. Moreover, the local NGO has a better understanding of the problem but international headquarters have experience from different and previous experience, Therefore, scattered teams should understand the skills of everyone and use them with trust.

Difference in Time zones, language and cultural barriers

An American NGO operating in Afghanistan with a local supplier will have some issue with the communication. Indeed, because of the difference in time zones that impose some delay in the reaction mostly in emergency situation. Moreover, there could be some misunderstanding because of the difference in language.

Technical issues

First, an easy solution to resolve the different in time zones could be using low bandwidth communication channels, such as emails or documents, which generates large amounts of lost or misunderstood information[4]. Therefore, video and deskopt sharing should be use instead to promote face-to-face communications.

Then, people from different countries use different technologies. Americans will prefer Microsoft Office and the Chinese more open-source software.When the team are in the same building, those problems generally will be resolved by day-to-day communication[4] but for remote project it will be impossible. Therefore, a clear definition of which programs should be used must be done before starting the remote project.

One solution: a cluster approach

As it has been described, remote management can lead to coordination issues. In order to resolve that, the cluster approach was introduced in 2005 [1]. Thereby the lead role was more formalized among the different organisations. The cluster approach is defined by a Cluster lead, the lead coordinator for a specific area of response which is responsible for organizing coordination at global and country level, prepare global planning, guidance and acting as a last resort [5]. Then, there are the lead agencies for each area of activities/clusters: logistics, camp management, etc. The cluster approach is now used in 43 countries to respond to any kind of emergency project [6]

Notable Benefits

Even if this approach is still to be improved, notable benefits have been identified in different fields like gap identification, coordination or information sharing.

Gap identification and Coverage

Thanks to a better collaboration between the agencies, it was possible to reduce the humanitarian efforts on site. Moreover, it was possible to identify the missing services inside the cluster and correct it. [7]. Indeed, the cluster approach allows to have a collective response to a specific problem. Before that, the origin of the gap will be defined thanks to the information sharing.

Coordination and leadership

This double managing structure with on one side the Cluster lead and on the other side the cluster agencies responsible for one sector, allows to clearly understand the responsibilities of everyone. This sectorial agencies are in charge of ’’ ensuring response capacity in place and that assessment, planning and response activities are carried out in collaboration with partners and in accordance with agreed standards and guidelines” [6].What make the cluster approach working is the fact that all the team members are working for the same common humanitarian objectives [6].

Monitoring,evaluation and Information sharing

Before the implementation of cluster approach in the humanitarian response, each member collected information but they are not sharing between the agencies. Trough cluster they can now share valuable information, analysis, strategic planning and evaluation. <ref=boom></ref>. Thereby this system improves the understanding of an pressing issue and let easy to find an appropriate response.

Cluster management cycle

The cluster approach is a way to implement in aid project but it can be also implemented in conventional companies who are dealing to international partners or teams. Cluster management is defined as a perpetual cyclic activity. It’s a complex, interactive and non-linear process. [8]. There is so a need in an adaptive management structure. Five stages can be looked at:

  1. Define
  2. Design
  3. Implement
  4. Monitor
  5. Evaluate
  6. Revise

Define

In order to have clearly defined objective, the first step is to define the expected results for the cluster. A clear vision of the long term future of the cluster should be defined. It represents the strategic planning. For example, the WHO (World Health Organisation) cluster defines is vision as promoting health in the world. Another important recommendation is to identifying key uncertainties. As in insecure environment, the cluster manager is working in a highly uncertain environment and should act despite unpredictability. Key uncertainties for NGO or companies could be: [8]

  • continuity of commitment of the key stakeholders
  • finance instability
  • change in technological and regulatory field

In order to succeed in cluster management, the vision and strategy should be developed with all clusters members. Moreover, the goals even in emergency situation should be measurable and feasible. Then, each clusters member should understand what are the benefit of this type of coordination.

Design

After defining objectives, they have to be performed. As it has been seen, one key challenge is to maintain a clear communication between the different stakeholders. Because of the difference is technologies, language it can become a hard task to manage. Therefore, two different plants should be presented. First, an action plan has to be implemented in order to highlight the activities, the responsibilities related, planning and allocation of the resources [8] For each objective there has to be indicator for success and measurement. Thereby, a data collection could be performed afterwards. However, those indicators should be well chosen in order to avoid an overload of information. Then, a communication plan in order to promote positive association, behaviour between the members. Several questions should be answered in this plan like “Who are the Stakeholders?” the communication mechanisms, etc. As in emergency situation is important to maintain a regular contact with the local suppliers. The frequency will differ following the role of the cluster member in the crisis as in the project for the companies. However, the communication mechanisms (software, etc) have to be clearly characterize with all the stakeholders. Finally, all the cluster members should accept a governance agreement for the decision making and communication.

Implement

Once the design approved, the implementation has to start. Here also a similarity could be seen between the operational actions of NGO and companies: the networking, providing information, collaboration, training, etc. [9]

Monitor

Monitoring is extremely important to gather crucial information on the different projects. To have useful information the members must know which kind of info should be collected, their form and the involved people. To have a good monitoring it should be done on a systematic way and regular basis. [8] There are two ways for monitoring the activities or on a process-related indicator (that should be defined in step 1) or continuously collect information on the outputs[10]. However, this last method requires a big involvement of the cluster member to share uninterruptedly their information. For emergency case, it could very interesting but in other case it could impede the correct working of the sectorial group. The goal of monitoring is to adapt and check if the cluster is acting in the right way. Moreover, it allows to identify problems in planning and/or implementation.

Evaluate

Comparing the actual effects with the decided strategies at a define moment is called evaluation[8]. It differs from monitoring in the way is done. Monitoring is continuous and evaluation is at a precise moment. Moreover, the evaluation report if the objectives were reached, the strong and weakness of the cluster. Nevertheless, if there is a correct monitoring, the evaluation should be right as well. Two types of evaluation could be highlighted: the formative and the summative. They form together the complete evaluation.

  • Formative

The purpose is to analyse the organisation of the cluster.

  • Summative

The goal is to look at the improvement of the development of the cluster and its local impact. Then, another purpose of the evaluations is for decision policy. The evaluations are a way to justify certain decisions certainly in difficult contexts. Finally, it is extremely important for the experience and the development afterwards. Lessons could be learned and the action plan established in step 2 could be changed

Revise

The final step of this cyclic process is to review objectives and uncertainties taking into account the previous stages. After that the lessons learned and results must be spread with the stakeholders or in the company.

Conclusion

References

  1. 1.0 1.1 [ Once Removed, Stoddard, Lessons and Challenges in remote management of humanitarian operations for insecure area]
  2. [Hansen, 2008; Stoddard, Harmer & Renouf, 2010]
  3. [ Once Removed, Stoddard, Lessons and Challenges in remote management of humanitarian operations for insecure area]
  4. 4.0 4.1 Monica Yap, Successful Distributed Agile Team Working Patterns, https://www.solutionsiq.com/docs/successful-distributed-team-working-patterns.pdf
  5. [ Logan, BOOM , The Cluster Approach: working towards best practices in Humanitarian Response, 2012]
  6. 6.0 6.1 6.2 [Cluster Approach, One Response. http//oneresponse.info/coordination/clusterApproach/pages/ClusterApproach.aspx]
  7. [ Steets,Julia.Office of the Coordination for Humanitarian Affairs. Inter-Agency Standing committee. IASC Cluster Approach Evaluation, 2nd Phase. 2010, http://ochanet.unocha.org/p/Documents/Inception_Report_CE2_Final.pdf]
  8. 8.0 8.1 8.2 8.3 8.4 [JAn-Hendrik Schretlen, Uncovering excellence in cluster management, 2011, https://www.pwc.com/gx/en/psrc/pdf/cluster_management.pdf ]
  9. [Biotechnology Cluster (1999). Report of a team led by Lord Sainsbury, Minister fro Science, United Kingdom]
  10. Shapiro, J. (2001) Monitoring and Evaluation. CIVICIUS/ World Alliance fro citizen Participation
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox