Monte Carlo Simulation of Risk
Line 16: | Line 16: | ||
Risk management is the identification of risks, evaluation. Risk management involved the following phases according to (Tysiak & Sereseanu, 2010) | Risk management is the identification of risks, evaluation. Risk management involved the following phases according to (Tysiak & Sereseanu, 2010) | ||
− | '''Risk management planning''' | + | ''''Risk management planning''': |
This phase involves the structuring and the detailing of how risk management should be conducted during the course of the particular project in context. Subjects such as methodology, roles and responsibilities, time span and risk categories are pertained to risk management planning. | This phase involves the structuring and the detailing of how risk management should be conducted during the course of the particular project in context. Subjects such as methodology, roles and responsibilities, time span and risk categories are pertained to risk management planning. | ||
=== Risk identification === | === Risk identification === |
Revision as of 00:27, 25 November 2014
Contents |
Abstract
”To dare is to lose one’s footing momentarily. To not dare is to lose oneself” - Søren Kierkegaard
Staying dynamic is a means of survival in today’s modern society, thus the expression the burning platform. In order for companies to stay competitive and sustain their businesses, they have to either become cost leaders or product leaders i.e. innovative. In order to realize this, companies have to dive into new areas of business, explore new possibilities in terms of evolving their products and/or processes. During the process of exploring and maintaining dynamism, uncertainty is inevitable due to the respective volatile nature of the markets within which the diverse companies operate in. Companies can’t foresee the future, hence don’t know how their respective markets will react to their new ways of doing business, new products or on the other hand if they are resilient enough to sustain unexpected drawbacks when exploring new paths. Thus it can be concluded that risk is incorporated in the DNA of any project, program or portfolio management, therefore “Risk Management” is a necessity for companies to continuously embark when exploring new dimensions in order to mitigate risk and suppress their corresponding consequences. There are several ways in which risk management can be conducted. This article provides a profound description of how to conduct a quantitative risk assessment by means of utilizing Monte Carlo simulations. Risk is random since its uncertain thus Monte Carlo Simulations are utilized to simulate it by means of a probability distribution.
- not complete*
Risk
It is basically inevitable not to associate risk and uncertainty to any human activity (Hertz & Thomas, 1983) although they can vary from activity to activity, depending on what’s at stake. In management, risk is the probability (chance) of an event occurring, which could eventually result (uncertainty) into a negative impact (consequence) on a particular project in context (Attrup & Olsson, 2008) thus risk is an expected loss over time. Risk can be categorized as either pure or speculative (Hertz & Thomas, 1983). Regarding pure risk, there is no benefit or gain pertained to it thus loss is the only possible outcome e.g. companies exposed to fraud or damage of assets etc. On the other hand, speculative risk can result into an uncertain degree of loss or gain e.g. a company can either gain or lose on investing in a new product, since there is a risk of market rejection. In this article emphasis is laid on speculative risk.
Risk Management
When dealing with a project, program or portfolio management it is crucial to understand that a lot of uncertainties are pertained to them since their eventual benefits are projected into the future. A lot of uncertainties can occur within a specific time period which can delay, stop or increase the cost of a project thus the importance of risk management. Risk management is the identification of risks, evaluation. Risk management involved the following phases according to (Tysiak & Sereseanu, 2010)
'Risk management planning: This phase involves the structuring and the detailing of how risk management should be conducted during the course of the particular project in context. Subjects such as methodology, roles and responsibilities, time span and risk categories are pertained to risk management planning.
Risk identification
This phase involves the pinpointing of potential risks that might eventually affect a particular project in context and their causes.
Qualitative risk analysis
This phase involves prioritizing and evaluating the initially identified risks in the previous phase, since risk can have different severity degrees (fig-risk matrix). Furthermore, a description of the different consequences pertained to the different risks and means by which they can be mitigated is given.
Quantitative risk analysis
This phase involves the utilization of probability distributions to model the individual risks