Risk matrix
Line 83: | Line 83: | ||
==Application and use == | ==Application and use == | ||
+ | ===Application=== | ||
− | + | Generally, the risk matrices have two main applications: | |
+ | * decision making regarding the acceptance of risk | ||
+ | * prioritization which risk needs to be addressed first. | ||
− | + | ====Decision making regarding the acceptance of risk==== | |
+ | In terms of risk acceptance, at least three levels of risk have to be isolated as illustrated in figure 04: | ||
+ | [[File:rm3.png|right|450px|thumb|'''Figure 4:''' Example of a risk matrix with color risk levels . <ref name="defenition"> ['' Definition of risk matrices''] http://www.cgerisk.com/knowledge-base/risk-assessment/risk-matrices </ref> ]] | ||
− | |||
− | + | ||
+ | [[File:colortable.png|center|500px|thumb|'''Figure 4:''' Three color levels of risk in terms of risk acceptance within riskmatrix<ref name="defenition"> </ref> ]] | ||
+ | |||
− | + | Prioritization which risk needs to be addressed first. | |
+ | In cases where the risk matrix is used for ranking, a larger number of risk levels may be necessary in order to obtain sufficient resolution to rank events or hazards in order of priority as shown in figure 04 | ||
+ | Consequences Categories | ||
+ | C1 | ||
+ | '''No impact''' C2 | ||
+ | '''Minor impact''' C3 | ||
+ | '''Medium impact''' C4 | ||
+ | '''Major impact''' C5 | ||
+ | '''Extensive impact''' | ||
+ | Probability categories P5 '''Very likely''' 5 10 15 20 25 | ||
+ | P4 '''Likely''' 4 8 12 16 20 | ||
+ | P3 '''Possible''' 3 6 9 12 15 | ||
+ | P2 '''Unlikely''' 2 4 6 8 10 | ||
+ | P1 '''Highly unlikely''' 1 2 3 4 5 | ||
− | + | However, the risk matrix have one important implications during the ranking of events those have a very low probability, but an extensive severity and in contrary the events with highest probability and lowest impact. | |
+ | The user and designer of a risk matrix have to be aware about major risk aversion or major hazard aversion. Major risk aversion means that events with the lowest probability – highest severity should always assigned with higher priority than events with the highest probability and lowest severity, even the risk value for both events is the same. Those implication based on the nature of risk that originally includes aversion to the probability rather than consequence severity. (Niis refernce) | ||
− | |||
+ | '''Usage of Risk matrix''' | ||
+ | It is it is worth to mentioning the main aim of risk matrix: classification and prioritization the list with already identified risks in order to make decision whether the certain risks can be tolerated. Frequently, in some cases it may be enough merely to rank risks against each other to identify relative prioritisation (ref. http://www.jakeman.com.au/media/whats-right-with-risk-matrices) | ||
+ | In order to concretize how an application of risk matrix can be carried out, an illustrative example of risk matrix is provided below. The example is based on a case project regarding potential threats which may cause new entrepreneurs during launching new start-up.(Project Management, Fourth Edition, Harvey Maylor) and consist 5 steps. | ||
− | + | 1. Estimate the probability of each risk occurring, and assign it a rating as portrayed in figure xx | |
+ | FREQUENCY | ||
+ | Verbal Numeric Description | ||
+ | '''Highly unlikely''' 1 Unlikely risks, which have a rare level occurrence such as less than 10%. | ||
+ | '''Unlikely''' 2 Seldom risk contains low probability of occurrence however cannot yet excluded entirely. | ||
+ | '''Possible''' | ||
+ | 3 Hazard, which have occasional (50/50) likelihood of occurrence harm | ||
+ | '''Likely''' 4 Risks that lies among 60-80% chances of occurrence can be grouped as likely. | ||
+ | '''Very likely''' | ||
+ | 5 A definite hazard that has highest frequency (generally more than 80 %) of reveal during certain project stages. | ||
− | |||
− | |||
− | + | 2. Identify and assess the severity of the impact of an adverse event caused by the risk as illustrated in figure xx. | |
+ | SEVERITY | ||
+ | Verbal Numeric Description | ||
+ | '''No impact''' 1 Limited hazard that will cause a near insignificant amount of harm to the overall progress of the project. | ||
+ | '''Minor impact''' 2 A minor hazard which lead to less significant extent of harm which in its turn not cause of a difference to the overall progress of the project are classified as minor risk. | ||
+ | '''Medium impact''' 3 Moderate hazard which do not imply a huge harm, though yet a considerable harm portrayed as medium. | ||
+ | '''Major impact''' 4 Critical risks with significantly large impact that may lead to a huge amount of loss or harm identified as major. | ||
+ | '''Extensive impact ''' 5 The most adverse hazard that lead to a catastrophic consequences such as high amount of lives losses or harm that totally destroyed a project (for example tsunami) is outlined as extensive impact. | ||
− | |||
− | |||
− | |||
− | |||
− | |||
+ | 3. Establish the list of risks with relevant consequence and probability as shown in table 1 | ||
− | + | Risk event Probability Imapct | |
+ | Brochure not ready in time for business launch | ||
+ | '''Very likely''' '''Medium impact''' | ||
+ | Website not ready in time for business launch | ||
+ | '''Very likely''' '''Major impact''' | ||
+ | Banking facilities not ready | ||
+ | '''Unlikely''' '''Extensive impact ''' | ||
+ | Initial stock not ready | ||
+ | '''Possible''' '''Medium impact''' | ||
+ | Group cannot agree on items to be sold | ||
+ | '''Possible''' '''Minor impact''' | ||
+ | Loss of one of group members | ||
+ | '''Highly unlikely''' '''Extensive impact ''' | ||
− | |||
− | |||
− | |||
− | + | 4. Explore and map list of risk on the Risk Matrix as shown in figure xx | |
+ | Consequences Categories | ||
+ | C1 | ||
+ | '''No impact''' C2 | ||
+ | '''Minor impact''' C3 | ||
+ | '''Medium impact''' C4 | ||
+ | '''Major impact''' C5 | ||
+ | '''Extensive impact''' | ||
+ | Probability categories P5 '''Very likely''' 5 10 15 | ||
+ | Brochure not ready in time for business launch | ||
+ | 20 | ||
+ | Website not ready in time for business launch 25 | ||
+ | P4 '''Likely''' 4 8 12 16 20 | ||
+ | P3 '''Possible''' 3 6 | ||
+ | Group cannot agree on items to be sold 9 | ||
+ | Initial stock not ready 12 15 | ||
+ | P2 '''Unlikely''' 2 4 6 8 10 | ||
+ | Banking facilities not ready | ||
+ | P1 '''Highly unlikely''' 1 2 3 4 5 | ||
+ | Loss of one of group members | ||
− | + | 5. Develop a response to each risk, according to its position in the chart. Remember, risks in the bottom left corner can often be ignored, while those in the top right corner need a great deal of time and attention | |
+ | 6. Based both on the level of risk and color the user makes decision which certain risks must be addressed first. For example, in shown on the risk matrix above all ‘red’ risks need to be treated as high priority. | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
Revision as of 03:37, 25 September 2016
To successfully execute its projects, especially in surrounding unstable environment, the companies, need to be aware about significant uncertainties, which will undoubtedly face projects during different stages of its life cycle regardless its complexity and time completion.
The uncertainties imply risks of (generally adverse) events those effect on the outcome or/and objectives of projects. In order to understand the variety of risks that a project face Risk Management activities in a project need to be performed. Effective project management need to identify what types of risk may influence particular stage of project. Furthermore, the management have to analyze and prioritize risks in terms of most severity and perform decision making in order to treat the risk and finally treat relevant risks in a structured way in order to avoid or at least mitigate any harm that may cause this certain risk.
However, how to decide and prioritize which risk is more dangerous and need to be treat first?
The one of the useful risk assessment tool supports project management to decide which risk need to be consider at first called “Risk Matrix” or also known as “Probability and Impact Matrix”.
Risk Matrix (Probability and Impact Matrix) is a broadly used risk assessment tool to define the different levels of risk as the product of the harm probability categories and harm severity categories. [1]
It is a common graphical tool used to simply and quickly visualize and categorize already identified risks, source of risks or risk treatments based on its probability and impact on a project. [1]
The aim of current article is to give an overview and summary of Risk Matrix. At the beginning, the article will provide briefly introduction to the risk management with its important elements. and the core idea of the risk matrices. Furthermore the article will defined the applications of presented tool as well as a practical usage within Project Management activities. Finally, the strengths and limitations of presented tool will determined and outlined.
Contents |
Introduction and main idea
Any projects during its different lifecycle stage are facing a variety of risks, defined as state of uncertainty where some possible outcomes have an negative effects on objectives, significant loss or other adverse or unwelcome circumstance.
Effective project manager need to be aware about potential types of risks in order to response and prevent unexpected event. This can be achieved by risk assessment process (shown in figure 1) which “aims to improve decision making process by identifying, assessing and mitigating relevant risks in a structured way” [2] The detailed description of Risk Assessment process is beyond the scope of this article, but for the deeper insight please follow the link Risk Assessment where the all relevant information can be found). Each of these activities is very comprehensive and takes a huge amount of resources, money and time consumption. Thus, in order to balance cost, time and resource of particular project, the management have to prioritize risks instead of trying to address each and every risk that particular project might face.
The one of the very useful risk assessment tool supports project management to decide which risk need to be consider at first called “Risk Matrix” or also known as “Probability and Impact Matrix”.
Risk Matrix (Probability and Impact Matrix) is a broadly used risk assessment tool to define the different levels of risk as the product of the harm probability categories and harm severity categories.
The main aim of risk matrix is to classify and prioritize hazard of adverse events based on the level of risk in order to facilitate management to make decision whether certain risks can be admit or whether not. [3]
According to ISO 31000 [4]the definition of risk outlined as combination of two basis criteria:
- The consequences or the severity of the impact of an adverse event caused by the risk.
- The probability or likelihood that this event may occur
In its turn the level of risk or risk value is defined as multiplication of these two criteria
"Level of Risk=Probability x Consequence”[3]
The combination of these parameters created risk matrix as two-dimension grid with consequence/impact on one axis (commonly X-axis) and probability or likelihood on the other (Y-axis) as shown on figure 2.
The severity or consequences scale describes the range of different types of impact of the adverse events that, if it occurs, will have an effect on the objectives and/or values such as physical health, social status, emotional well-being or financial wealth [5]
The consequence scale are commonly extended from the lowest potential impact to the highest as illustrated in figure 02 and can comprise any number of criteria with nominal or textual description such as ““No impact”, “Minor”, “Medium”, or “C1”, “C2”, “C3” and etc.
The example of possible consequences criteria can defined as follows:
1. No impact: Limited hazard that will cause a near insignificant amount of harm to the overall progress of the project.
2. Minor impact: A minor hazard which lead to less significant extent of harm which in its turn not cause of a difference to the overall progress of the project are classified as minor risk.
3. Medium impact: Moderate hazard which do not imply a huge harm, though yet a considerable harm portrayed as medium.
4. Major impact: Critical risks with significantly large impact that may lead to a huge amount of loss or harm identified as major.
5. Extensive impact : The most adverse hazard that lead to a catastrophic consequences such as high amount of lives losses or harm that totally destroyed a project (for example tsunami) is outlined as extensive impact.
The other dimension of risk matrix is the likelihood scale describes the range of probability of the occurrence of a risk. As the consequence scale, the probability scale is also extended from the lowest potential likelihood to the highest as portrayed in figure 02 and comprised variety numbers of criteria with nominal or textual description such as ““High unlikely”, “Unlikely”, “Possible”, or “P1”, “P2”, “P3” and etc.
The example of possible probability criteria can outlines as follows:
1. Highly unlikely: Unlikely risks, which have a rare level occurrence such as less than 10%.
2. Unlikely: Seldom risk contains low probability of occurrence however cannot yet excluded entirely.
3. Possible: Hazard, which have occasional (50/50) likelihood of occurrence harm
4. Likely: Risks that lies among 60-80% chances of occurrence can be grouped as likely.
5. Very likely: A definite hazard that has highest frequency (generally more than 80 %) of reveal during certain project stages. [6]
The definition of both criteria consequence and probability scales could vary in different organization and project areas, thus it is worth mentioning that mentioned above descriptors is recommended as a guide only. Finally, based on combination of probability and impact the level of risk can easily counted and ranked by placing adverse event into risk matrix according to assigned consequence and probability as shown on figure 3
As example the undesired event R25 displayed on the figure 3 has the highest risk value equal to “25”, or the risk R22 and R10 have the identical risk value ”10”.
Application and use
Application
Generally, the risk matrices have two main applications:
- decision making regarding the acceptance of risk
- prioritization which risk needs to be addressed first.
Decision making regarding the acceptance of risk
In terms of risk acceptance, at least three levels of risk have to be isolated as illustrated in figure 04:
Prioritization which risk needs to be addressed first.
In cases where the risk matrix is used for ranking, a larger number of risk levels may be necessary in order to obtain sufficient resolution to rank events or hazards in order of priority as shown in figure 04
Consequences Categories
C1
No impact C2
Minor impact C3
Medium impact C4
Major impact C5
Extensive impact
Probability categories P5 Very likely 5 10 15 20 25
P4 Likely 4 8 12 16 20
P3 Possible 3 6 9 12 15
P2 Unlikely 2 4 6 8 10
P1 Highly unlikely 1 2 3 4 5
However, the risk matrix have one important implications during the ranking of events those have a very low probability, but an extensive severity and in contrary the events with highest probability and lowest impact. The user and designer of a risk matrix have to be aware about major risk aversion or major hazard aversion. Major risk aversion means that events with the lowest probability – highest severity should always assigned with higher priority than events with the highest probability and lowest severity, even the risk value for both events is the same. Those implication based on the nature of risk that originally includes aversion to the probability rather than consequence severity. (Niis refernce)
Usage of Risk matrix
It is it is worth to mentioning the main aim of risk matrix: classification and prioritization the list with already identified risks in order to make decision whether the certain risks can be tolerated. Frequently, in some cases it may be enough merely to rank risks against each other to identify relative prioritisation (ref. http://www.jakeman.com.au/media/whats-right-with-risk-matrices)
In order to concretize how an application of risk matrix can be carried out, an illustrative example of risk matrix is provided below. The example is based on a case project regarding potential threats which may cause new entrepreneurs during launching new start-up.(Project Management, Fourth Edition, Harvey Maylor) and consist 5 steps.
1. Estimate the probability of each risk occurring, and assign it a rating as portrayed in figure xx
FREQUENCY
Verbal Numeric Description
Highly unlikely 1 Unlikely risks, which have a rare level occurrence such as less than 10%.
Unlikely 2 Seldom risk contains low probability of occurrence however cannot yet excluded entirely.
Possible
3 Hazard, which have occasional (50/50) likelihood of occurrence harm
Likely 4 Risks that lies among 60-80% chances of occurrence can be grouped as likely.
Very likely
5 A definite hazard that has highest frequency (generally more than 80 %) of reveal during certain project stages.
2. Identify and assess the severity of the impact of an adverse event caused by the risk as illustrated in figure xx.
SEVERITY
Verbal Numeric Description
No impact 1 Limited hazard that will cause a near insignificant amount of harm to the overall progress of the project.
Minor impact 2 A minor hazard which lead to less significant extent of harm which in its turn not cause of a difference to the overall progress of the project are classified as minor risk.
Medium impact 3 Moderate hazard which do not imply a huge harm, though yet a considerable harm portrayed as medium.
Major impact 4 Critical risks with significantly large impact that may lead to a huge amount of loss or harm identified as major.
Extensive impact 5 The most adverse hazard that lead to a catastrophic consequences such as high amount of lives losses or harm that totally destroyed a project (for example tsunami) is outlined as extensive impact.
3. Establish the list of risks with relevant consequence and probability as shown in table 1
Risk event Probability Imapct Brochure not ready in time for business launch Very likely Medium impact Website not ready in time for business launch Very likely Major impact Banking facilities not ready Unlikely Extensive impact Initial stock not ready Possible Medium impact Group cannot agree on items to be sold Possible Minor impact Loss of one of group members Highly unlikely Extensive impact
4. Explore and map list of risk on the Risk Matrix as shown in figure xx
Consequences Categories
C1
No impact C2
Minor impact C3
Medium impact C4
Major impact C5
Extensive impact
Probability categories P5 Very likely 5 10 15
Brochure not ready in time for business launch
20
Website not ready in time for business launch 25
P4 Likely 4 8 12 16 20
P3 Possible 3 6
Group cannot agree on items to be sold 9
Initial stock not ready 12 15
P2 Unlikely 2 4 6 8 10
Banking facilities not ready
P1 Highly unlikely 1 2 3 4 5
Loss of one of group members
5. Develop a response to each risk, according to its position in the chart. Remember, risks in the bottom left corner can often be ignored, while those in the top right corner need a great deal of time and attention 6. Based both on the level of risk and color the user makes decision which certain risks must be addressed first. For example, in shown on the risk matrix above all ‘red’ risks need to be treated as high priority.
Limitations
The aim of any risk evaluation tool is to ensure that the decision process is transparent, based on best knowledge and reflects the common understanding of stakeholders. When reviewing the application of risk matrices, it becomes obvious that this simple tool has some notable weaknesses. Both users and designers of risk matrices should be aware of these shortcomings and ensure that the risk matrices are used in such a way that correct conclusions are drawn.
The mentioned ISO 31010 [1] also includes an invaluable summary of the advantages and disadvantages of risk matrices, together with recommendations for their usage.
Strengths:
- relatively easy to use;
- provides a rapid ranking of risks into different significance levels.
Limitations:
- a matrix should be designed to be appropriate for the circumstances so it may be difficult to have a common system applying across the range of circumstances relevant to an organization;
- it is difficult to define the scales unambiguously;
- use is very subjective and there tend to be significant variation between raters;
- risk can not be aggregated (i.e. one cannot define that a particular number of low risks or a low risk identified a particular number of ties is equivalent to a medium risk);
- it is difficult to combine or compare the level of risk for the different categories of consequences(impact)
Results will depend of the level of detail of the analysis, i.e. the more detailed the analysis the higher the number of scenarios, each with a lower probability. This will underestimate the actual level of risk. The way in which scenarios are grouped together in describing risk should be consistent and defined at the start of the study. [1]
Annotated bibliography
For further reading on the subject or related subjects, the reader is encouraged to check out the following:
- Nijs Jan Duijm (2015), Recommendation on the use and design of risk matrix, Safety Science 76, DTU, Denmark .[3]
- “The article explore the weakness of risk matrices and provide recommendation for the use and design of risk matrix
- ALARP [8]
- “The wiki-article describes a term often used in the milieu of safety-critical and safety-involved systems.
- Risk Management [9]
- The wiki-article describes the concept of the identification, assessment, and prioritization of risks followed by coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of unfortunate events or to maximize the realization of opportunities
- Risk Management - Risk assessment techniques, Dansk Standart DS/EN ISO 31010, 2010
- The international standard (ISO) 31010 contains guidance on selection and application of systematic techniques for risk assessment. .
Videos
A short video to visualyse the usage and benefits of Risk Matrix as explained in the article.
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 [Risk Management - Risk assessment techniques] Dansk Standart DS/EN ISO 31010, 2010
- ↑ [How to Do Projects”] “JoanaGeraldi, Chrisitan Thuesen, JosefOehmen, Textbook DTU 2016
- ↑ 3.0 3.1 3.2 3.3 [Recommendation on the use and design of risk matrices'] Nijs Jan Duijm, Safety Science 76, p.21-31, DTU, 2015
- ↑ [Risk Management – Principles and Guidelines] Dansk Standart DS/EN ISO 31000, 2009
- ↑ [Risk Definition'] https://en.wikipedia.org/wiki/Risk
- ↑ [A Critical Tool for Assessing Project Risk] http://www.brighthubpm.com/risk-management/88566-tool-for-assessing-project-risk/#imgn_0
- ↑ 7.0 7.1 [ Definition of risk matrices] http://www.cgerisk.com/knowledge-base/risk-assessment/risk-matrices
- ↑ Cite error: Invalid
<ref>
tag; no text was provided for refs namedalarp
- ↑ Cite error: Invalid
<ref>
tag; no text was provided for refs namedRM