Just In Iime Delivery in Construction
(→Strategy for JIT implementation in construction) |
(→Strategy for JIT implementation in construction) |
||
Line 101: | Line 101: | ||
JIT strives to eliminate physical buffers which is material inventories and time, and to obtain a one-piece flow within processes. This can be achieved at a production line, due to the high stability of the flow obtained by the production scheduling. However, such stability can not be obtained with construction scheduling, why it would be hazardous to simply remove all physical buffers, if the source of variation and uncertainty can not be eliminated. Ballard and Howell and proposed the following strategies for the development and implementation of construction JIT. | JIT strives to eliminate physical buffers which is material inventories and time, and to obtain a one-piece flow within processes. This can be achieved at a production line, due to the high stability of the flow obtained by the production scheduling. However, such stability can not be obtained with construction scheduling, why it would be hazardous to simply remove all physical buffers, if the source of variation and uncertainty can not be eliminated. Ballard and Howell and proposed the following strategies for the development and implementation of construction JIT. | ||
− | + | ==== Better location and sizing of schedule buffers ==== | |
Better assessment tools should be developed, to determine project uncertainties and the quantitative relationship between a buffer and the uncertainty they are intended to shield against. I.e. by improving the management of uncertainties and thus eliminating the causes of flow variation, physical buffers can be minimized. | Better assessment tools should be developed, to determine project uncertainties and the quantitative relationship between a buffer and the uncertainty they are intended to shield against. I.e. by improving the management of uncertainties and thus eliminating the causes of flow variation, physical buffers can be minimized. | ||
Revision as of 07:13, 19 June 2017
The construction industry is mainly project based, and renowned to be inefficient with low productivity, and often encounter difficulties with keeping a time schedule, due to delays during the construction period. Concerning the construction management, the introduction of the Just-in-time (JIT) concept can be advantageous, when managing the logistics of the building materials and workforce on the building sites. The JIT philosophy was originally developed for the manufacturing industry, where it is a method of forwarding materiel or work from one process to the next, at the moment where it is required at the succeeding process. Thus, reducing work-in-process inventory, production cycle times since less time is spend on queuing before being processed, and the reduction of flow variation resulting in continuous ongoing improvements. There is a significant difference in how JIT is implemented in the construction industry compared to the manufacturing industry. This is because construction is a different type of production, which can more closely be resembled with product development, than with manufacturing. If not taking into account the industry of ‘assembly line housing’. In general there is a far greater complexity and uncertainty in construction. JIT is a concept from the lean philosophy, and the goal of the JIT concept is to reduce, or ultimately eradicate, variations and waste. In the construction industry this waste is delays.
Contents |
Lean Construction
History
Lean manufacturing was originally pioneered and developed at the Toyota Motors Corporation manufacturing plants in Japan, based on the ideas of the employed Engineer Ohno Taichi [1] . The lean concept JIT, should contribute to the increase of production volume and the productivity, in a mixed small-series-production (lots of many product varieties). Lean and JIT was therefore a response to the production demands arising in Japan after the second world war, where the production machinery should convert to the production of cars and trucks instead of weapons [2].
Lean Philosophy
Lean construction is a management philosophy spun of from the principles of lean manufacturing. Lean is a philosophy that focuses on value instead of cost, and seeks to optimize productivity by removing all non-value adding processes. Ohno specified the following concepts, which became the five governing principles of lean:
- Precisely specify value from the ultimate costumer’s perspective
- Identify the value delivery process (Value stream) – Eliminate non-value adding steps
- Make the value adding steps flow without interruption
- Establish a pull from the costumer. Do not produce until it is needed.
- Pursue perfection
These principles all concerns the problem of waste, or Muda in Japanese, activities or processes that takes up resources without creating value, which should be eliminated in order to deliver things right at the right time. For the good of the producer and the costumer. The different types of waste that can occur in a production, were defined by Wormack and Jones [3]:
- Defects in products
- Overproduction of items no one wants;
- Inventory waiting to be processed;
- Unneeded processing;
- Unnecessary transport of goods;
- People waiting for input to work on;
- Design of goods and services that do not satisfy customer needs.
Just in time (JIT)
JIT is a method of forwarding material or specific manpower or traits, at the exact moment where it is needed, reducing on site inventories and inefficient man-hours (Waiting, and double handling). The following concepts are essential to managing JIT.
One Piece flow: One product on the assembly line at the time. At a car factory several different models in several different colors can be constructed on the same assembly line.
Pull: There is a pull throughout the assembly line and the suppliers.
Tact: Strict timeline. It is required to know at exactly what time a given product is at a certain time.
Kaizen
The lean concept requires a strict set of standards. However, these standards should be continuously improved, to continuously increase the productivity. This philosophy is named Kaizen.
Andon
Andon is a method of keeping the workforce informed of the progress towards their production/involvement by use of information displays such as light boards or post-it boards, making it possible for everyone to be up to date with the status off all operations at any given time.
Stop the Line
It is better to stop the assembly line, or hold the construction flow, and fix any errors as they occur, instead of letting the dysfunctional product proceed throughout the production, to be repaired after the product is finished.
Poka Yoke
A concept from the idea of ‘right the first time’, which is essential. It is a concept that states that at process should not be able to go wrong. This can be implemented by ensuring that the product only can be assembled in one way. This philosophy is termed Poka Yoke.
Last Planner system (LP)
The Last Planner System is a commitment based planning system which integrates ‘should-can-will’ planning with analysis of the constraints of the upcoming process. ‘Should’ is the pull planning, ‘can’ is make ready and ‘will’ is the look ahead planning. All participants in the project agrees on a process plan, but not schedule. There is never detailed plans for more than one week at the time, to ensure a high plan reliability and activity predictability. When keeping the commitments of what is agreed ‘will’ be done, to what ‘should’ be done, but limited by what ‘can’ be done, yields a stable work environment. The manager should only assign work activities which he knows can be done. If the activities do not obey these limitations, uncertainty will be inherited by direct workers, resulting in a high percentage of non-productive time and a demotivated work force [4]. The work is continuously evaluated, by monitoring how much was actually done, compared to previously commitment to what ‘will’ be done. This notion is termed PPC, or the Percentage of Planned Activities Completed [5].
Cho and Ballard [6] has shown that there is a significant correlation between the implementation of LP and project performance – The sum of cost and schedule reduction percentages.
Kanban
Kanban, which translates to ‘signboard’ or ‘billboard’, is a scheduling system that controls the production inventory. The system insures, that whatever is produced is throughput, i.e. needed for the production of an order.
Towards JIT in Construction
The Purpose of JIT is to reduce cost by eliminating waste related to material storage, but also labor time and transportation. There is a significant amount of value to gain by doing so, Hammerlund [7] have previously shown that approximately a third of the time a worker spends on the building site, is regarding the procurement of materials needed by him, which adds up to ten percent of the total building cost. The optimum concept that JIT is, will only increase supply cost marginally compared to the waste eliminated, thus increasing productivity [8]. The waste in the construction industry is somewhat identified and the introduction of JIT can be justified. However, the application of JIT in the construction industry is substantially different to that of the manufacturing industry, due to their different types of production, and because of the greater complexity and uncertainty in construction. Construction is best conceived as a product development process. The construction industry consists of building projects, that are scheduled driven. A smooth work flow and a high work performance is achieved if the schedule is kept. However, that is often not the case with large scale projects. There might occur design modifications or slips in the deliveries etc. At the Toyota plant, Ohno successfully minimized inventories between any process, thus also reducing the safety stock that allows the continuity of a process downstream, should any deliver variation occur. What buffers are there in a construction project, that conceal variation and ensures a safety stocks, but also act as waste?
Construction Buffers
Ballard and Howell [9] defines two inventory types, that might shield, or buffer, downstream construction processes from flow variations, together with suggestion rules for how to utilize them optimally.
- Schedule buffers: Piles of stuff: Materials, tools, equipment, manpower, etc. May originate in decisions to insert time intervals between scheduled activities. Act as added time to the project duration.
- Plan buffers: Inventories of workable assignments, made by planning processes that make work ready for downstream production. Buffer by enabling a reliable and predictable flow output from a given process.
In general, increasing the schedule buffers between supplier and construction, leads to an increased shielding from late deliveries, but does not address the cause to the problem of flow variation. This is obviously an expensive shielding application, both regarding time and money.
Thus, it is suggested to implement schedule buffers after processes with variable output. In general, fabrication and delivery can be considered to be very reliable and predictable, why the buffers with advantage should be placed between engineering and fabrication, instead of between fabrication and installation. This ensures that engineering completes its work correctly, increasing the chance that the design is final. However, this is obviously difficult to incorporate in fast-track projects. An additional rule states that schedule buffers should be sized to the degree of uncertainty and variation to be managed.
Plan buffers are required, and not to be replaced by schedule buffers. E.g. having a stock of an item, does not provide a working crew with workable assignments to install the items, and operate any transportation vehicle. At the site, assembling of components, determining optimum sequencing etc. is most optimal done before making assignments and committing to the work that will be done in the plan period, which is often one week, i.e. The Last Planner system. The plan buffers here determine what ‘can’ be note compared to what ‘should’ be done. Finally, the commitment to what ‘will’ be done, is governed by what ‘can’ be done. The future planning can now be improved by monitoring the PPC.
Thus, if considering a construction process as a complex of work processes, a manager in charge of a downstream process can optimize piles of stuff he might have scheduled with as shielding from unreliable inflow, if he has knowledge regarding the PPC of the previous process.
Strategy for JIT implementation in construction
JIT strives to eliminate physical buffers which is material inventories and time, and to obtain a one-piece flow within processes. This can be achieved at a production line, due to the high stability of the flow obtained by the production scheduling. However, such stability can not be obtained with construction scheduling, why it would be hazardous to simply remove all physical buffers, if the source of variation and uncertainty can not be eliminated. Ballard and Howell and proposed the following strategies for the development and implementation of construction JIT.
==== Better location and sizing of schedule buffers ====
Better assessment tools should be developed, to determine project uncertainties and the quantitative relationship between a buffer and the uncertainty they are intended to shield against. I.e. by improving the management of uncertainties and thus eliminating the causes of flow variation, physical buffers can be minimized.
Place plan buffers and make ready processes in front of each production processes
The hypothesis is that production can indeed be shielded from upstream uncertainty through planning, why the use of the last planner system should be increased. Thus, the last planner method of detailed production planning shields production from uncertainties upstream. This will ideally result in the revealing of sources of variation and uncertainty, enhancing the productivity while releasing resources for further improvement of the performance of the process shielded, and provide a highly predictable work flow in the near-term to processes downstream.
Progressively replace schedule buffers with plan buffers
The ultimate goal in the construction industry here is to obtain a predictability and reliability, so it can be totally independent of the need of piles of stuff, and time between production processes. The Hypothesis here is that work flow variations can indeed be reduced. If so, the following benefits will be implied. The buffer sizes can be reduced if flow variations are reduced. A reduction of these buffers between the event driven process chain (EPC) functions will yield a reduction of the total project duration. Furthermore, if work flow is more predictable, material, labor and other resources can be better matched at the right time to the work flow, and therefore increasing the productivity. Thus, the implementation of plan buffers will propagate certainty throughout a given project.
Benefits of JIT in construction
In addition to the previous discussed benefits of utilizing JIT, Pheng and Shang reports the following possible benefits [10]:
- Increasing the competitive advantage of firms in terms of consistently and continuously meeting costumer’s requirements.
- Improving quality of construction materials and components
- Increase in productivity.
- Reduced costs due to minimized inventories
- Improved relationship with supplier
- Work completed ahead of time schedule
- Improving the tidiness of the construction site
- Elimination of site congestion and reduced inconvenience experienced by neighbors
However, these possible benefits can not be achieved without initial investments. For example, more advanced equipment and more skilled employees are required, if the setup time is to be reduced.
Annotated Bibliography
TowardsJIT : Bertelsen, S. ; Nielsen, J. (1997). Just in time Logistics in the supply of building materials. 1st international Conference on Construction Industry Development: Building the future Together. [C] : BYGGELOGISTIK. Byggelogistik is characterized by careful planning, daily management executed from the building site - not the head office - and immediate and direct feed back of all mistakes.
References
- ↑ Ohno, Taichi. Toyota Production System. Productivity Press, 1987
- ↑ “Just-In-time – visioner og erfaringer” , Samfundslitteratur, 1990
- ↑ Wormack, J. P. & Jones, T. D. : Lean thinking: Banish waste and create wealth in your corporation.
- ↑ 4.0 4.1 Ballard, G. & Howell, G. (1994), Implementing Lean Construction: Stabilizing Work Flow. 2nd Annual Conference on Lean Construction at Catolica Universidad de Chile Santiago, Chile September
- ↑ Simonsen, R. (2017): Lean Construction & Last Planner System. Slideshow.
- ↑ Cho, S. & Ballard, G. (2011): Laster Planner and integrated Project Delivery. Lean construction Journal 2011 pp 67-78 .
- ↑ Hammarlund, Y & Rydén, R (1989), Effektivitetet i VVS-branschen, Arbetstidens utnytjande, (1989), Svenska Byggbranschens utvecklingsfond, Sweden.
- ↑ Bertelsen, S. ; Nielsen, J. (1997). Just in time Logistics in the supply of building materials. 1st international Conference on Construction Industry Development: Building the future Together.
- ↑ 9.0 9.1 Ballard, G. & Howell, G. : Toward Construction JIT.
- ↑ Sui Pheng, L. & Shang, G. (2011): The Application of the Just-In-Time Philosophy in the Chinese construction industry. Journal of construction in developing Countries.