Contractual uncertainty and risk allocation

From apppm
(Difference between revisions)
Jump to: navigation, search
(Abstract)
(Abstract)
Line 1: Line 1:
=='''Abstract'''==
 
 
 
In order to be fulfilled, civil engineering projects usually entail allocation of huge resources of different types. But in the same time, financing large resources for a project means assigning of great responsibilities. So it is common that a single contractor will not take the whole responsibilities corresponding for a big project, but these will be shared through an ample selection from the multitude of existing types of contracts nowadays.
 
In order to be fulfilled, civil engineering projects usually entail allocation of huge resources of different types. But in the same time, financing large resources for a project means assigning of great responsibilities. So it is common that a single contractor will not take the whole responsibilities corresponding for a big project, but these will be shared through an ample selection from the multitude of existing types of contracts nowadays.
  

Revision as of 20:21, 20 June 2017

In order to be fulfilled, civil engineering projects usually entail allocation of huge resources of different types. But in the same time, financing large resources for a project means assigning of great responsibilities. So it is common that a single contractor will not take the whole responsibilities corresponding for a big project, but these will be shared through an ample selection from the multitude of existing types of contracts nowadays.

In the same time, sharing the responsibilities represents sharing the risks corresponding to the specific parts of the civil engineering projects. It is of highly interest how construction business deals with risk management, risk identification, risk quantification and a particular emphasis will subsequently be shown towards the manner of how risks are controlled throughout the project and allocated to different parties by means of contracts.

Analyzing different existing types of contracts, how they serve the involved parties and how responsibilities and benefices are shared in order to achieve a common goal, are very imporant tasks. Hereinafter the choice between basic types of complex contracts (lump sum contract, unit rate contract, guaranteed maximum price contract, pure incentive contract, guaranteed maximum liability contract, percentage fee contract, cost reimbursable contract) will be further discussed.

Contents

Introduction

By definition, a contract is a mutually binding agreement that obligates the seller to provide the specified product and obligates the buyer to pay for it. So, in the same time, a contract can be seen as the foremost documentation that defines the duties and responsibilities of each party of the agreement. Furthermore, to make the connection with risk management in civil engineering, this may be translated to the fact that by means of contracts, the owner will be the one that allocates risks to one of the other parties. Hence, the choice of a contract plan becomes crucial, as it represents the primary step in the control and allocation of corresponding risks of a project. This will further allow focusing the attention of project management on early identification of risk and uncertainty and highlight those areas where further design, work development, or clarification is most needed.

Risk in construction business

Risk is defined as the chance of an adverse event to happen depending on the circumstances. Risk and uncertainty are part of all construction work regardless of the size of the project. Some factors that carry risk include, for example: complexity, speed of construction, location of the project, and familiarity with the work. When serious risks occur on projects the effects can be very damaging. In extreme cases, time and cost overruns turn a potentially profitable project into a loss-making venture. Cost and time targets are often missed due to unforeseen events that even an experienced project manager cannot anticipate. [1]

By means of contractual agreement, it is possible that the inherent risk of a specific job to be assumed by another party that has the competence to fairly assess the risk and the expertise necessary to control or minimize it. Shifting tasks to another subcontractors means transferring or sharing the ownership of the risk with them in the following way [2]:

  • having a stake in the benefit or harm that may arise from the activity that leads to the risk;
  • responsibility for the risk; accountability for the control of risk;
  • financial responsibility for the whole or part of the harm arising from the risk should it materialize.

For a better understanding of possible matters in construction projects, different sources of risk will be presented and grouped, function to their possible allocation: to the contractor, to the owner, shared.

Riskallocation.PNG

Data extracted from a survey in [3]

Basic types of contracts

Having familiarized with the concept of contracts and risk management and how they bond with each other in civil engineering projects, there will be further presented the three basic types of complex contracts existing: fixed-price contracts, cost-reimbursable contracts, incentive contracts.

Fixed price represents a category of contracts that involves a determined total price for a well-defined product. They transfer most of the risk to the supplier, but even so, he is protected against changes generated from sources beyond its control. To the extent that the product is not well defined, both the buyer and the seller are at risk- the buyer may not receive the desired product or the seller may need to incur additional costs to provide it. These contracts are used when a large amount of information is available, being widespread for the procurement of execution work on site. They may include incentives for meeting or exceeding selected project objectives. [4]

Fee based contracts involve payment to the seller for its actual costs, plus a fee representing seller’s profit. They are used in high uncertainty situations, when it is possible to determine the type of needed resources, but not the required amount. These contracts represent usually the base point in procuring architectural and engineering design services.[5] Since there exists place for opportunism of the contractor, usually detailed auditing systems are put in place in case of fee based agreements.

Incentive contracts are hybrid types of contractual arrangement that contain aspects of both fixed price and fee based type of contracts. They are structured so that to limit the risk of one of the parties relative to the other, allocating the responsibilities more equally, but also to keep a linearity between the estimated actual cost of construction plus a percentage fee and the actual outturn.[5] The common feature of all incentive contracts is that they try to provide positive stimulus within the contract to motivate supplier performance.

Some recommendations so that incentive contracts to be as productive as possible are further indicated [5]:

  • The benefit obtained from improving the performance must be greater than the cost of the incentive.
  • The benefit obtained from improving the performance must be greater than the penalties associated with malfunctioning issues.
  • The benefit obtained from improving the performance must be greater than the cost involved in measuring performance.
  • It should be kept track of gain and losses very accurately.
  • Incentive contracts are more suitable for integrated project coalitions.


Figure 1: Basic types of cotracts

Finally, a schematic representation of the abovementioned types of contracts, function of the level of uncertainty at the contract formation and each party responsibilities is depicted in Figure 1. It can be noticed once again how the uncertainty increases from a low level, in case of lump sum contract (which is a fixed price contract) to a high level of uncertainty in case of a cost-reimbursable contract. It is to be observed that the incentive contracts are the ones that tend to give an equilibrium in terms of uncertainty during the contract formation and in terms of each party responsibilities. Another remark would be the fact that fee based contracts implies the most responsibilities from behalf of the client, whilst in case of fixed price contracts the responsibilities are allocated mostly to the supplier.













Choosing the appropriate contract type

Lump Sum Contract

In a lump sum contract, the owner has essentially assigned all the risk to the contractor, who in turn can be expected to ask for a higher markup in order to take care of unforeseen contingencies. Beside the fixed lump sum price, other commitments are often made by the contractor in the form of submittals such as a specific schedule, the management reporting system or a quality control program. If the actual cost of the project is underestimated, the underestimated cost will reduce the contractor's profit by that amount. An overestimate has an opposite effect, but may reduce the chance of being a low bidder for the project.

Unit Price Contract

In a unit price contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has been removed from the contractor. However, some contractors may submit an “unbalanced bid” when it discovers large discrepancies between its estimates and the owner's estimates of these quantities. Depending on the confidence of the contractor on its own estimates and its propensity on risk, a contractor can slightly raise the unit prices on the underestimated tasks while lowering the unit prices on other tasks. If the contractor is correct in its assessment, it can increase its profit substantially since the payment is made on the actual quantities of tasks; and if the reverse is true, it can lose on this basis. Furthermore, the owner may disqualify a contractor if the bid appears to be heavily unbalanced. To the extent that an underestimate or overestimate is caused by changes in the quantities of work, neither error will affect the contractor's profit beyond the markup in the unit prices. [4]

Cost plus Fixed Percentage Contract

For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract.

Cost Plus Fixed Fee Contract

Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time.

Cost Plus Variable Percentage Contract

For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible.

Target Estimate Contract

This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor's estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates.

Guaranteed Maximum Cost Contract

When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. [6]

Note: this chapter is under redaction and rephrasing !

Conclusion

While construction contracts serve as a means of pricing construction, they also define the allocation of risk to the various parties concerned. The owner is the one that has the sole power to decide what type of contract should be used for a specific facility to be constructed and to set forth the terms in a contractual agreement. It is important to understand the risks of the contractors associated with different types of construction contracts and to demonstrate in a systematic way how they are anticipated. Without such a risk analysis, it is difficult to reach an agreement satisfactory to all the parties.

References

  1. Hayes, R.W.,(1986) "Risk Management for Project Managers - Building Technology and Management "
  2. Godfrey, P.S.,(1996) "Control of risk - A guide to the systematic management of risk from construction. "
  3. Roozbeh, K.,(1995) "Journal of Construction Engineering and Management -Risk management perceptions and trends of US construction. "
  4. 4.0 4.1 Project Management Institute, Pennsylvania USA (2000) "A Guide to the Project Management Body of Knowledge "
  5. 5.0 5.1 5.2 Winch, Graham M., Wiley-Blackwell, (2010) "Managing Construction Projects, 2nd edition "
  6. Jensen, P.A., Center for Facilities Management- Realdania Research (2008) "Facilities Management for students and practitioners "
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox