Most software development projects apply either the Waterfall or Agile methodology. A development methodology is a procedure used by an engineering team in order to create the desired product. The Waterfall methodology represents the traditional approach, where the development process is conducted in a linear series of events. On its way toward the conclusion, the progress flows continuously through the phases of a project (analysis, design, development, testing, release) like a waterfall. The entire project is planned in advance. Agile is a more recently developed software development methodology, where the linear approach is replaced by an incremental, iterative one. Instead of planning the whole project in advance, Agile enables the adaption of requirements during the whole project. This article provides an introduction to each methodology, a comparison, and examples of use, in order to facilitate the decision whether Agile or Waterfall is more suitable for the next project.
Contents |
Waterfall Methodology
The lifecycle model which is today known as traditional or Waterfall model was first described by Royce in 1970.[1] It is called Waterfall model because of its sequential and down-flow characteristic where the phases analysis, design, implementation, testing and release are processed consecutively downwards.[2] Each phase of the Waterfall model is processed in order without any overlapping and within a specified time period. Once a phase is completed there is no going back to a previous phase as it will be frozen.[3]
Analysis
In this phase, all the requirements and customer needs of the desired system or product are gathered and recorded in detail in a specification document.[2] This document will be used as input in the design and implementation phase. The requirements of the product should be clear before moving to the next phase as changes in requirements cannot be adapted later in the process.[3]
Design
The outcome of the design phase is a specified hardware and a virtual overview of the desired system or software.[3]
Implementation
The actual development of the system starts in the implementation phase. The system is therefore divided into small subunits which are tested by the developers before forwarding them to the testing phase. A quality gate checklist helps to control if there is a deviation from the requirements, planned timeline and product scope.[4]
Testing
In this phase, the subunits are integrated into one working system which is tested regarding quality and functional aspects. The collected measures of performance are used for the decision whether the system is ready for the release. In order to ensure that the outcome of the project meets the customers' requirements, the tested system is reviewed according to a checklist. [4]
Release
The product gets prepared for being released into the market or delivered to the customer (including installation instructions of the system for customers and user-guides). There is another quality gate in order to check if the final product meets the customer and quality requirements and whether it is delivered in time. [4]
Maintenance
After releasing the product in the customer environment there can occur problems in the performance of the product. Hence, the company must provide maintenance in order to solve this issues.[4]
Pros
- All requirements are clearly documented before the development of the product starts
- Each phase is finished in a specified period of time before moving to the next phase
- Waterfall is simple to implement as it is a linear model
- The amount of resources needed for implementing the waterfall methodology is minimal
- Each phase follows appropriate documentation in order to ensure the quality development [3]
Cons
- You cannot return to a previous phase. If the design phase fails the project might become very complicated in the implementation phase
- If a customer wants to change requirements of the product they cannot be implemented in the current development process
- Even small changes or errors in the finalized product might be very costly and cause a lot of problems [2]
Agile Methodology
The Agile methodology uses an incremental, iterative approach instead of a linear and sequential one. Instead of extensive planning in advance, it provides practices, tools and a culture that enable close collaboration of a team in a quickly changing environment. During several successive iterations with a predetermined duration, the team develops working products in order to get continuous feedback from the customer.[5] Every iteration consists of a planning and analyzing phase followed by a fast design, build and test phase and results in deployment.[6] This procedure enables the team to improve the product with every iteration by adapting the backlog, a list of prioritized requirements for every iteration. An agile approach encourages selforganized cross-functional teams (incorporating planners, designers, developers and testers) with empowered members to create high-quality outcomes.[5]
Scrum, Kanban, Lean, Extreme Programming (XP) and Feature Driven Development (FDD) are popular methods of the Agile methodology that provide concrete agile practices and comprise the following characteristics:[6]
- Responsiveness: being able to provide an appropriate response to any changes
- Flexibility: being able to adapt to changes at every time
- Speed: enable rapid and iterative development of a product
- Leannes: focus on cost saving, high quality and a short time frame
- Learning: ability to improve before and after product development
Generally, the different methods of Agile differ slightly one from the other but contain practices that cover the full range of product development. In some cases, it is recommendable to combine different practices in order to create a situation-specific method.[6] All Agile Methodologies have in common, that they are driven by Agile values and principles, which are explained in the Agile Manifesto published in 2001:[7]
- Individuals and interactions over processes and tools
- Working software over comprehensive documentation
- Customer collaboration over contract negotiation
- Responding to change over following a plan
The twelve principles of Agile enlarge on this four value statements.[8]
Pros
- Changing requirements can be implemented at any phase of the process due to short development cycles
- A working product can be developed very quickly [2]
- Continuous improvement enables fast and high-quality delivery
- Continuous dialogue between the customer and the development team ensures immediate user feedback
- The Agile methodology attaches great importance to teamwork as it requires frequent communication and face-to-face interactions. [9]
Cons
- High dependency on collaboration with the customer. Especially in long projects that is not always possible
- Due to lack of documentation, there is an increased dependence of interaction between developers [2]
- Compared to linear and sequential models agile methodologies are more difficult to comprehend [9]
- When used in large and complex projects it is difficult to estimate the costs and schedule
- Knowing that changes are possible the team could take hurried decisions without a proper analysis [5]
Waterfall or Agile?
As a sequential Model, Waterfall works best for simple projects where the requirements are clear and will not change during the development process.[3] A good consensus with the customer and decision-making based on facts are favored conditions.[5]
Methods which follow the Agile methodology are well suited for complex and complicated projects as requirements are not always clear and may change throughout the development process. Therefore, a close exchange with the customer, an immediate customer feedback and the ability to adapt to quickly changing requirements are important properties for a successful conclusion of such projects.[5] Also, projects in a team-oriented environment may prefer an Agile method as it encourages high interaction between all stakeholders and involved designers. [6]
Projects with an even higher level of uncertainty and disagreement with the customer should be rejected or avoided until the conditions change. After exceeding a certain point of complexity there is no adequate method.[5]
Example of Use
The following examples demonstrate the different approaches of each methodology.[10] [11] The project goal is the development of a customer address book.
Waterfall Model
Product Requirements
At the beginning of the development process, the product manager creates a document of requirements:
• Enable user to create new contacts
• Enable user to see his contacts
• Enable user to import contacts from other applications
• Enable user to email his contacts from the address book
• Enable user to add pictures to represent his contacts
The created document will comprise detailed requirements, user scenarios and potential layouts
Timeframe: 2 weeks
Analysis
Engineering team receives the document and analyzes the requirements, asking for clarifications as needed. At the end, all requirements should be clear and the product manager can update document.
Timeframe: 1 week
Design Engineering team creates a design for functionality, including database design, mockups and workflows.
Timeframe: 3 weeks
Implementation Engineering team develops the address book and prepares it for testing.
Timeframe: 1 week
Testing The product team conducts various tests on the developed address book and reviews its entire functionality.
Timeframe: 2 weeks
Release The fully working product is released.
TOTAL elapsed time: 9 weeks
Agile Model
Product Requirements
The product manager creates a document of requirements:
• Enable user to create new contacts
• Enable user to see his contacts
• Enable user to import contacts from other applications
• Enable user to email his contacts from the address book
• Enable user to add pictures to represent his contacts
These requirements documents will be simple and will include user scenarios. As each item is worked on, questions will arise, and there will be opportunities to discuss them as they occur. From this list, the requirements for the first iteration are chosen (starting with the highest priority items).
Timeframe: 1 week
Iteration Nr.1 The team works on the functionality to create new contacts and to view contacts. This includes the design, development and testing for these items. At the end of the iteration, the team demonstrates the functionality to the product manager, where he or she can provide feedback.
Timeframe: 2 weeks
Iteration Nr.2 Team works on the functionality to import contacts, to email and to add pictures to the contacts. This includes the design, development and testing for these items. At the end of the iteration, the team demonstrates the functionality to the product manager, where he or she can provide feedback.
Timeframe: 2 weeks
Iteration Nr.3 Team conducts a regression test and prepares to release the product.
Timeframe: 1 week
Release The product functionality is released.
Total elapsed time: 6 weeks
Note that if any changes to the requirements occur during this project, each iteration would adjust accordingly.
Findings and Conclusion
As already discussed, the Waterfall model is a linear model with a sequential set of processes where the development "flows" from the start point to the delivery of a working product with several stages in between. Waterfall is a plan-driven methodology and hence, the whole project strictly follows a clear plan, which requires extensive planning upfront. That allows an estimation of costs and timeline which can be discussed with the customer in advance. The existence of an elaborated plan and clear documentation also results in a more secure project as everyone exactly knows what to do.
In comparison, the Agile methodology provides flexible models which enable adaptive planning and development. While the product delivery at Waterfall occurs at the very end of the process, Agile methods are divided into small releases which provide the customer with small increments of the final product. During several iterations, the team works on this small packages of the product what allows direct customer feedback at the end of every iteration. Thus, rapid and effective responses to changing customer requirements are possible. But in return, it also requires the permanent availability of the customer.[6]
References
- ↑ Sommerville I., "Software process models," ACM Computing Surveys (CSUR), vol. 28, pp. 269-271, 1996
- ↑ 2.0 2.1 2.2 2.3 2.4 Dubey A.; Jain A.; Mantri A., "Comparative Study: Waterfall v/s Agile Model", International Journal of Engineering Sciences & Research Technology (IJESRT), 2015
- ↑ 3.0 3.1 3.2 3.3 3.4 Balaji S.; Dr. Sundararajan Murugaiyan M., "Waterfall vs V-Model vs Agile: A Comparative Study on SDLC", International Journal of Information Technology and Business Management (JITBM), 2012
- ↑ 4.0 4.1 4.2 4.3 Bomarius F. et al., "Product-Focused Software Process Improvement", 10th International Confernce, Springer, 2009
- ↑ 5.0 5.1 5.2 5.3 5.4 5.5 Boral S.,"Domain I: Agile Principles and Mindset", Ace the Pmi-acp pp. 1-27, 2016
- ↑ 6.0 6.1 6.2 6.3 6.4 Von Rosing M. et al., "Applying Agile Principles to BPM", Complete Business Process Handbook: Body of Knowledge From Process Modeling To Bpm — 2014, Volume 1, pp. 553-577
- ↑ Schwaber K. et. al., "Manifesto for Agile Management", 2001, Retrieved from http://agilemanifesto.org/ 22.09.2017
- ↑ K. Schwaber et. al., "Twelve principles of agile software", 2001. Retrieved from http://agilemanifesto.org/principles.html 22.09.2017
- ↑ 9.0 9.1 Shiotsu Y., "Agile vs. Waterfall: A Side-by-Side Comparison", Retrieved from https://www.upwork.com/hiring/development/agile-vs-waterfall/, 22.09.2017
- ↑ "Product development: The Waterfall methodology (model) in software development", 2009, Retrieved from https://www.marsdd.com/mars-library/product-development-the-waterfall-methodology-model-in-software-development/, 22.09.2017
- ↑ "Product development: Using Agile methodology for software development", 2009, Retrieved from https://www.marsdd.com/mars-library/product-development-using-agile-methodology-for-software-development/, 22.09.2017