Resources loading, leveling and crashing
(→Notes) |
(→Definitions) |
||
Line 8: | Line 8: | ||
Resource leveling is a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply | Resource leveling is a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply | ||
+ | <ref name=PMBOK5th> {{cite book | ||
+ | |title=A Guide to the Project Management Body of Knowledge (PMBOK® Guide) | ||
+ | |page=179 | ||
+ | |chapter=6.6.2.4 Resource Optimization Techniques | ||
+ | |edition=5th | ||
+ | |isbn=978-1-935589-67-9 | ||
+ | |date=2013 | ||
+ | |publisher=[[Project Management Institute]] | ||
+ | }} </ref> | ||
+ | |||
+ | |||
Crashing is a method used to analyze and choose the most cost-efficient measurements of compressing the project duration. <ref> B. Tonnquist & J.Hørluck (2009), ''Project Management - a complete guide'', (Academica,2009), 134.</ref> | Crashing is a method used to analyze and choose the most cost-efficient measurements of compressing the project duration. <ref> B. Tonnquist & J.Hørluck (2009), ''Project Management - a complete guide'', (Academica,2009), 134.</ref> |
Revision as of 18:06, 12 February 2018
Contents |
Abstract
This article will examine what are the resources loading, levelling and crashing. The application of each of these methods in the project scheduling will be discibed to highlight the key benefits and differences between them. The goal is to provide a reliable guideliness that can be used in the process of allocating the resources into the project schedule.
Definitions
Resource loading (or resource allocation) identifies the amount of project resources required over the project baseline. It mainly involves project manpower or employees and is a process that assigns such resources as required to each project activity.
Resource leveling is a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply [1]
Crashing is a method used to analyze and choose the most cost-efficient measurements of compressing the project duration. [2]
Notes
- ↑ Template:Cite book
- ↑ B. Tonnquist & J.Hørluck (2009), Project Management - a complete guide, (Academica,2009), 134.