The aim of this article is to provide the reader with crucial information about the differences of Programme and Project Portfolio Management.
+
As consequence of globalisation of markets for goods, capital and labor, it became common to use internationally recognised terms in many companies and organisations. Specially in the field of project Management it can be hard to understand the background and relevance of different methods and terms. Programme and Project Portfolio Management are mentioned often in the context of the overall topic of Project Management. It can be confusing to understand the differences. The objective of this article is to wrap up distinctions according to existing literature and best practices, by the determination of fundamental key factors and thereby clarify the differences.  
As consequence of globalisation of markets for goods, capital and labor, it became common to use internationally recognised terms in many companies and organisations.
+
It can be confusing to understand the differences. The objective of this article is to wrap up distinctions according to existing literature and best practices, by the determination of fundamental key factors and thereby clarify the differences.  
+
  
 
== What is a standard ==
 
== What is a standard ==

Revision as of 19:49, 1 December 2014

As consequence of globalisation of markets for goods, capital and labor, it became common to use internationally recognised terms in many companies and organisations. Specially in the field of project Management it can be hard to understand the background and relevance of different methods and terms. Programme and Project Portfolio Management are mentioned often in the context of the overall topic of Project Management. It can be confusing to understand the differences. The objective of this article is to wrap up distinctions according to existing literature and best practices, by the determination of fundamental key factors and thereby clarify the differences.

Contents

What is a standard

This section seek to give the reader a understanding of what a standard is. Further it will explain the definition of a standard and how the numerous standard setting organizations (SSO) are related. It is often mentioned that a certain project management method is a standard, which is developed by a specific organisation such as ISO, CCTA or PMI. The clarification of the meaning and relation of those terms can be crucial, in order to understand the overall topic of this article.

Definition

A standard is in general defined as something considered by an authority or by general consent as a basis of comparison; an approved model. [1] . According to the International Organisation for Standardization a standard is defined as a document that provides requirements, specifications, guidelines or characteristics that can be used consistently to ensure that materials, products, processes and services are fit for their purpose. [2]

International Standards

Internationally there are many standards organizations. The three mostly established and largest of them are the International Organisation for Standardization (ISO), the International Electrotechnical Comission (IEC), and the International Telecommunication Union (ITU). Both ISO and IEC are composed of national standard bodies. ITU is a treaty based organisation established as permanent agency of the United Nations, were governments are the primary members. In 2001 the World Standards Cooperation was established by the International Electrotechnical Comission, the International Organisation for Standardization (ISO), and the International Telecommunication Union (ITU). The aim of WSC is to strengthen and advance the voluntary consensus-based International standards systems of IEC, ISO and ITU.

  • ISO promotes worldwide proprietary, industrial and commercial standards
  • IEC promotes standards for all electrical, electronic and related technologies
  • ITU promotes standards for the telecommunication sector

National Standards

National standard bodies are in general existent in each country or economy. These standard bodies may either be public or private sector organizations, or a combination of the two.

Standard in the context of Programme Vs. Project Portfolio Management

The Project Management Institute (PMI) is a non-profit professional organisation for the project management profession. PMI participate in a number of standard activities at the international level in order to promote the project management profession and played a leadership role in the development of ISO21500 (global management standard), serving as secretariat of the ISO committee during the five-year process. Thus this article is based on the definitions of the standard for Programme and Portfolio Management of PMI.

Programme Management

Definition

Program Benefit Management, Project Management Institute 2006

The definition of a Programme is, that a Programme contains a group of related projects which are managed in a coordinated way to obtain benefits and control of the overall outcome. This approach would not be possible by managing these projects individually, without the umbrella of a program. Programmes may include elements of related work (e.g., ongoing operations) outside the scope of the discrete projects in a Programme. [4] When a large project is splittet into multiple related projects with explicit management of the benefits, then the effort becomes a Programme. [4] In General Programme Management is used for the creation of portfolios of projects [8], implementation of strategies [9] and change generation in products, business or ways of working. [10]

The distinction between a Project and a Programme is given by the benefits which a Programme provides over and above those that projects can archive on their own, such as exposure, prioritisation, more efficient use of resources and better alignment with other projects [10]

Key Factors

The following Key factors are determined throughout the literature and best Practice of Programme Management:

  • A Programme contains a group of related projects
  • A Programme has a overall benefit which can be measured in terms of return of investments, new capabilities and/or benefit delivery
  • Programmes have a Wide Scope which may change to meet benefit expectations of the organisation
  • Programme Managers have to expect change
  • Leadership style focuses on managing relationships and conflict resolution
  • Programme Managers manage Project Managers
  • Programme Managers create high level plans providing guidance to projects where detailed plans are created

Project Portfolio Management

Definition

The term Portfolio is widely used throughout many different organisations and has come to represent different meanings. Thus the focus of this article lies on Project Portfolio Management.

Portfolios, Programs, and Projects - High Level View, Project Management Institute 2006

The origins of Project Portfolio Management are found in the application of modern portfolio theory to the project selection problem and first mentioned in the work of Markowitz [7] The definition of a Project Portfolio is a collection of projects and/or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. The Projects or Programs of the portfolio (components) may not necessarily be interdependent or directly related. [1] Project Portfolio Management is defined as a dynamic decision process, which constantly updates and revises active projects. [2] Thus Project Portfolio Management enables the organization to align the Project Portfolio to strategic objectives, thereby approving only the components that directly support business objectives, and considering the portfolio risk as a result of the mix of components in a Project Portfolio at any time. [3]

It is stated that a Project Portfolio most likely is one of the truest measures of an organisation´s intent, direction, and progress. Thereby the organisation can reasonably question components of a Project Portfolio , when they are not alligned to the strategy. [3] Hence, Project Portfolio Management as a dynamic decision making process includes the collection, identification, categorisation, evaluation, selection, balance and review of components according to the organisation´s specific key indicators and the strategic plan.

Key Factors

The following Key factors are determined throughout the literature and best Practice of Project Portfolio Management:

  • A portfolio is a collection of projects and/or Programs and/or other work that are grouped together to facilitate effective management of that work to meet strategic business objectives
  • The scope of a Portfolio is a business scope, that can change with the strategic goals of the organisation
  • Succes is measured by the performance of Portfolio components
  • The focus of the Portfolio Management lies within that programs and projects are viewed in priority for resource allocation
  • The projects and/or programs may not necessarily be interdependent or directly related
  • Project Portfolio Management is a dynamic decision process
  • Project Portfolio Management enables the organisation to align the Project Portfolio to strategic objectives
  • The portfolio risk is a result of the mix of the components


Interface

This section seek to define the interface between Program and Portfolio Management. The Interface and correlation between Program and Project Portfolio Management may be the reason for confusion when one is trying to understand the differences. The key factors stated in the previous sections should give the reader an idea of the distinction of the terms, which now will be more detailed by the definition of the interface.

Cross-Company Portfolio Management Process Relationships, Project Management Institute 2006

It is important to understand the responsibilities according to the different components of a Project Portfolio. As described in the section above about Project Portfolio´s : A project Portfolio is a collection of Projects and/or Programs and/or other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. Thus the role of the Project Portfolio Management is the collection, identification, categorisation, evaluation, selection, balance and review of components. That means that once a component (Project and/or Program) is authorized for the perspective Project Portfolio, it becomes the responsibility of the Program/Project Management to take control of the component and apply the correct management processes to ensure that the work is done effectively and efficiently. It is now the responsibility of the Program/Project Management to monitor planned-to-actual performance (time, budget, resources, quality, and scope) of the component and provide the Project Portfolio Management with consolidated information.[5] This information is used in Portfolio reviews to determine required actions. Program and Project Management may work together with Portfolio Management to determine "go/no go" criteria for proposed and current components, including "termination criteria" (phase gates). Program and Project Management may also work together with Portfolio Mangement in capacity planning by inputting resource requirements (e.g., human resources, financial and physical assets). [11]



Perspective

This section seeks to perspectivate the viewpoints of Best Practices according to the mentioned terms in the previous sections. Best Practices of Project Portfolio, Program and Project Management are normative collections of tools and methods. Thus they only fit in most certain situations in which complete requirements are available at the beginning of the project. For Example is the irrelevance of traditional risk management techniques demonstrated by Christoph Loch and his colleagues in a project which is confronted with "unknown unknowns". [13]

The general Project Management approach has gained very little historical research, which means that the field is young and still under development. As stated by Soderlund & Lenfle (2011) “With the notable exception of Peter Morris’ work (1994) we actually do not know of any history of project management. Most textbooks in project management begin with a short historical section and then turns to the classical description of project management, its organization and techniques, most of which is notoriously disembodied, almost without taking context into account. The tendency is to produce a very shallow view on the history of project management. More sobering for the discipline of project management, the rare famous case study comes from political scientists (Sapolsky, 1972), historians of technology (Hughes, 1998; Johnson, 2002), historians (Hewlett & Anderson, 1962; Brooks et al, 1979) or journalists (Kidder, 1981; Rhodes, 1986). The problem for scholars in project management is that these contributions, even if they provide valuable empirical data, are not oriented toward the specific analysis of project management and project organizing as such, and thus rarely reflect on the process of project organizing or the act of project management." [14]

References

[1] Project Management Institute. The Standard for Portfolio Management: The Portfolio Management Framework. Project Management Institute, Inc, 2006.

[2] Cooper et al., 1998a, b; Griffin, 1997; Graves et al., 2000; Ringuest et al., 1999; Roussel et al., 1991

[3] Project Management Institute. The Standard for Program Management: The Relationship between Program Management and Portfolio Management. Project Management Institute, Inc, 2006.

[4] Project Management Institute. The Standard for Program Management: What is a Program. Project Management Institute, Inc, 2006.

[5] Project Management Institute. The Standard for Program Management: Portfolio Management Process Overview. Project Management Institute, Inc, 2006.

[6] Shao et al., 2012

[7] Markowitz, H.M. Portfolio selection 77–91 J. Financ. 7 (1), 1952.

[8] Gray, R.J., 1997. Alternative approaches to programme management 5–9. Int.J. Proj. Manag. 15

[9] Partington, D., Pellegrinelli, S., Young, M., 2005. Attributes and levels of programme management competence: an interpretive study 87–95. Int. J. Proj. Manag. 23

[10] Pellegrinelli, S., 1997. Programme management: organising project-based change 141–149. Int. J. Proj. Manag. 15

[11] Project Management Institute. The Standard for Portfolio Management: The The Links between Portfolio Management and Program and Project Management. Project Management Institute, Inc, 2006.

[13] Loch C, DeMeyer A, Pich M. Managing the unknown. A new approach to Managing High Uncertainty and Risks in Projects. John Wiley ™ Sons, Inc.: Hoboken, New Jersey

[14] Lenfle S, Soderlünd J. Special Issue: Project History. Call for Paper : pp. 491-493. International Journal of Project Management 29, 2011