Earned Value Management

From apppm
(Difference between revisions)
Jump to: navigation, search
(The Metrics)
Line 24: Line 24:
 
* '''Earned Value (EV)''' or Budgeted Cost of Work Performed (BCWP)
 
* '''Earned Value (EV)''' or Budgeted Cost of Work Performed (BCWP)
 
: This is the cumulative earned value for the work completed up to a point in time. It represents the amount budgeted for performing the work that was accomplished by a given point in time. The EV equals the total budget at completion (BAC) multiplied by the percentage activity (or project) completion (PC) at the particular point in time (= BAC * PC)
 
: This is the cumulative earned value for the work completed up to a point in time. It represents the amount budgeted for performing the work that was accomplished by a given point in time. The EV equals the total budget at completion (BAC) multiplied by the percentage activity (or project) completion (PC) at the particular point in time (= BAC * PC)
 +
 +
 +
===Performance Measurements===
 +
By comparing the three key parameters, PV, AC and EV, it is possible to determine the cost performance and schedule performance.  The variances are based on cumulative data (also called inception-to-date data and project-to-date data).
 +
 +
====Variances====

Revision as of 08:51, 20 September 2015

Earned Value Management (EVM) is a method for measuring a project’s performance. Earned Value Management is a complex task of controlling and adjusting the baseline project schedule during execution, taking into account project scope, timed delivery and total project budget. The method is useful during execution of a project because it tells us where we are going with schedule and costs, indicating any variance to plan.

Contents

Introduction

An important part of successful project management is to have accurate and reliable information and the current performance is the best indicator of future performance. By using trend data, it is therefore possible to forecast cost and schedule overruns early in the project.

Background

The Earned Value Management method was introduced in the 1960s as a financial analysis specialty in United States Government programs, but has since been a significant branch of project management. In the late 1980s and early 1990s, it was no longer used by EVM specialists only. The EVM was emerged as a project management methodology to be understood and used by managers and executives also, and today EVM has become an essential part of every project tracking.

The method can be used to measure the real progress of a project, and combines the measurements of the project management triangle: scope, time and cost. Thereby the EVM method provides early indications of expected project results based on project performance and highlights the possible need for corrective action. These indications become available to management as early as 20 percent into the project (Fleming).

Bum

With the EVM method we can measure the expected total project time and cost and calculate the deviation between the current performance and the planned performance. The method uses some basic EVM metrics, which will be introduced.

The Metrics

EVM uses three key parameters to measure project performance:

caption
  • Planned value (PV) or Budgeted Cost of Work Scheduled (BCWS)
This is the time-phased budget baseline. It is the approved budget for accomplishing the activity or work related to the schedule. PV can be viewed as the value to be earned as a function of project work accomplishments up to a given point in time. The total PV is equal to the Budget at Completion (BAC). This is the total budget baseline for the activity or work package. It is the highest value of PV and the last point on the cumulative PV curve. The graph of cumulative PV is often referred to as the S-curve, because (with a little imagination) it looks like the letter S.
  • Actual Cost (AC) or Actual Cost of Work Performed (ACWP)
This is the cumulative actual cost spent to a given point in time to accomplish an activity or work (and to earn the related value).
  • Earned Value (EV) or Budgeted Cost of Work Performed (BCWP)
This is the cumulative earned value for the work completed up to a point in time. It represents the amount budgeted for performing the work that was accomplished by a given point in time. The EV equals the total budget at completion (BAC) multiplied by the percentage activity (or project) completion (PC) at the particular point in time (= BAC * PC)


Performance Measurements

By comparing the three key parameters, PV, AC and EV, it is possible to determine the cost performance and schedule performance. The variances are based on cumulative data (also called inception-to-date data and project-to-date data).

Variances

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox