Balanced Scorecard in Project Portfolio Management
Contents |
Abstract
The Balanced Scorecard (BSC) is a strategic planning and management system that organizations use to connect the strategy elements such as vision, mission and core values with more operational elements such as objectives, measures and targets.
It was introduced by Robert S. Kaplan in 1992 (“The Balanced Scorecard – Measures that drive performance”, Harvard Business Review) after observing that managers focused their attention only on aspects of performance that were measurable, with the primary measurement system in most organizations being based on financial accounting. In their view, these financial reporting systems fail to measure or provide a basis for managing the value created by the organization’s intangible assets.
In order to connect the daily work practices with the strategic goals of a company, the Scorecard approach enables managers to review performance from four different perspectives: Financial perspective, Customer perspective, Internal Process perspective, and Learning and Growth perspective.
Nowadays, BSCs are used extensively in business and industry, government, and nonprofit organizations worldwide. BSC has been selected by the editors of Harvard Business Review as one of the most influential business ideas of the past 75 years and was listed fifth among the top ten most widely used management tools around the world in a recent global study by Bain & Co. (reference, site)
The Idea behind the Method
Robert S. Kaplan observed that, as companies around the world transform themselves for competition that is based on information, their ability to exploit intangible assets has become far more decisive than their ability to invest in and manage physical aspects. (reference, usage)
Based on this observation, Kaplan introduced the Balanced Scorecard. The latter augments traditional financial measures with benchmarks for performance in three key nonfinancial areas: a company’s relationship with its clients, its key internal processes, and its learning and growing. “When performance measures for these areas are added to the financial metrics, the result is not only a broader perspective on the company’s health and activities, it is a powerful, organizing framework. A sophisticated instrument panel for coordinating and fine-tuning a company’s operations and businesses, so that all activities are aligned with its strategy.”(1, Using the Balanced Scorecard as a Strategic Management System)
Therefore, BSC enables companies to track financial results while simultaneously monitoring progress in building the capabilities and acquiring the intangible assets they would need for future growth. In other words, it is not a replacement for financial measures but rather their complement.
The Four Perspectives
The BSC translates an organization’s vision into a set of performance indicators distributed among four perspectives: Financial, Customer, Internal Business Processes, and Learning and Growth.The financial perspective: Focuses on financial performance of an organization and it mainly covers the revenue and profit targets as well as the budget and cost-saving targets. It is important to note that financial performance is usually the result of good performance in the other three scorecard perspectives.
The customer perspective: Focuses on performance targets as they relate to customers and the market. It usually covers customer growth and service targets as well as market share and branding objectives. Typical measures and KPIs in this perspective include customer satisfaction, service levels, net promoter scores, market share and brand awareness.
The internal process perspective: Focuses on internal operational goals and covers objectives as they relate to the key processes necessary to deliver the customer objectives. At this perspective, companies outline the internal business processes goals and the activities the organization has to do really well internally in order to push performance. Typical example measures and KPIs include process improvements, quality optimization and capacity utilization.
The learning and growth perspective: Focuses on the intangible drivers of future and is often broken down into the following components:
• Human Capital (skills, talent, and knowledge)'
• Information Capital (databases, information systems, networks, and technology infrastructure)
• Organization Capital (culture, leadership, employee alignment, teamwork and knowledge management).
The Balanced Scorecard in Project Portfolio Management (PPM)
PPM aligned to Organization’s Strategy:(http://www.balancedscorecard.org/BSC-Basics/About-the-Balanced-Scorecard)]] PPM-BSC.PNG One of the main issues when selecting the projects to be executed as part of the organization's portfolio is if the project is aligned to the organization's strategic objectives. If this is not the case, there is a valid chance the organization and its stakeholders will not get a proper return on their investment. The project portfolio is defined as a collection of projects and/or programs and other related work, grouped to facilitate effective management of that work to meet strategic business objectives. Within the organizational context, PPM establishes the proper actions to accomplish strategic goals and objectives which means that it requires direct inputs from the strategic planning.
Strategic Planning:
Strategic planning is the process whereby the organization's vision and mission, plus the approach that will be adopted to achieving them during a certain period of time, are established by upper management. This process continues with the establishment of strategic objectives and goals, which are the intended achievements of the organization in terms of business results, interpreted from various perspectives—financial, customer, infrastructures, products and services, or by cultural outcomes. All this information is set into a strategic document termed “Strategic Plan.”
BSC bridges PPM with Strategic Planning:
In order to place all the initiatives proposed during the Strategic Planning process, the Balanced Scorecard (BSC) is applied. What matters most from the perspective of project portfolio management is that the BSC provides a record of the strategic initiatives that are the strategic projects to be, and from there it is possible to start analyzing, evaluating, prioritizing, planning, and depending on the case, executing the projects that will make the mission and vision of the organization something tangible (Kaplan & Norton, 2008). Figure 3 shows how this “strategic leap” happens. Processes and other sources affect the organization's mission and vision; they provide guidance in deciding the types of initiatives (strategic initiatives) that will likely succeed in accomplishing that mission and that vision for the organization. Those initiatives are translated into projects and programs, most likely embedded into a project portfolio where proper management for effective performance and results delivery is performed (Kaplan & Norton, 2000; Kaplan & Norton, 2008; PMI, 2008a, p. 8; PMI, 2008b, p. 10).
Limitations
In practice, despite widespread use and practitioner-oriented literature suggesting the BSC has beneficial values especially in enhancing organizational performance and strategy achievement, a large body of academics is skeptical about the relationship between BSC and organizational outcomes. In fact, a leading criticism asserts the widespread practice of the BSC in itself does not demonstrate the BSC is beneficial to organizations (Kraaijenbrink, 2012). In support of this assertion, BizShifts (2010) espouse that, within a decade of its inception, an estimated 44% of organizations worldwide had implemented the BSC; however, only 22% to 50% of these organizations achieved higher return on asset and higher return on equity while an estimated 85% of the organizations experienced problems during implementation. Based to academics, the problems can be related to:
1. Rigidity
Voelpel et al. (2005) observe rigidity in the conception of the BSC as a performance measurement tool. While Kaplan and Norton (1992), and Casey and Peck (2004) contend performance measurement is a significant benefit of the BSC, Voelpel et al. (2005) agree and disagree. The BSC enables an organization to transform strategy into tangible performance measures but by limiting performance measures to four categories and this fact introduces rigidity. Rigidity is evident when the four performance measurement categories form the basis of defining key success factors. The BSC thus forces managers to put success indicators into one of the four categories. The result is the BSC limits the view of an organization by leaving no room for cross-perspectives that have combined effect on strategy execution. Further, there is the danger of an organization neglecting success indicators that do not fall into any of the four categories.
2. Confirmation Bias
The four categories also risk creating confirmation bias, a situation where managers only take interest in what they want to measures but ignore changes in the external business environment as evident in the case of Encyclopedia Britannica, which almost went out of business because of sticking to its once successful success factors.
3. Complexity & resource intensive nature
The final limitation in the practice of the BSC is the complexity and resource intensive nature of its implementation. According to Antonsen (2010), implementing the BSC requires an organization to gather new data, which could create work overload for some departments. It could potentially lead to employee resistance and cynicism as well as to managerial resistance due to increased availability of information with the potential to upset the current power balance.
4. Limitations in Learning & Growth
Rillo (2004) observes the limitation of the BSC in dealing with knowledge creation, learning and growth. Although the BSC has a learning and growth perspective that deals with knowledge creation and innovation, the perspective adopts the traditional logic of innovation, where research and development (R&D) deals with innovation but conceals both the process and the innovation itself from competitors. The only difference is the BSC extends the innovation concept from R&D to the entire organization. However, the traditional logic of innovation is changing from closed to open innovation influenced by increasingly inter-linked and networked nature of today’s businesses. In fact, in the present knowledge economy increased mobility of knowledge workers, advancement in information and communication technology, and improved accessibility to venture capital places a greater emphasis on the open nature of innovation. The practice of the BSC does not take into account the changing nature of innovation and does not provide for performance measures and interlink ages with external partners in developing innovative ideas and products and the implementation of the innovative ideas. The limitation of the BSC is therefore to include and to measures distributed innovation in a highly interlinked and networked market.
5. Insufficiency in describing the business complexity
BizShifts (2010) claims that BSC is becoming increasingly deficient since one-way linear cause-and-effect relationships are insufficient to describe the complex nature of today’s business. For instance, customer perspective is inter-linked with various perspectives such as employee satisfaction, delivery time and product quality. In turn, customer satisfaction could influence employee satisfaction. Thus, the complex and interlinking nature of the business process suggests the way the success indicators are linked in the BSC requires revision to consider the entire system rather than the direct and visible success factors alone.