Earned Value Management (EVM)

From apppm
Revision as of 20:11, 18 February 2021 by S202041 (Talk | contribs)

Jump to: navigation, search

Contents

cheatsheet

re-cite: [1]


Abstract

When managing projects, it is of greatest interest to make sure that the project delivers what has been agreed upon. In order to improve the odds to fulfill the expectations, performance measurements can be used. Performance measurements allows the project manager and other stakeholders to closely monitor the project and easier decide when it is necessary to take actions, if the project is running out of line. Projects that are not monitored properly run the risk of being late, overrun the budget and end up being out of scope, which often can lead to unsatisfied stakeholders. [1] Earned value management is a method used in project management to evaluate the performance of a project at any point to monitor whether the project is proceeding according to plan or not. This is done by comparing the expected outcome of the three constraints cost, time, and scope. In addition, earned value also evaluates what has been accomplished in the project so far.[2][3] The result of the performance measurement is a value which indicates how much the current state of the project varies from the expected progress with cost, time, and scope taken into account. This value can later be used to forecast when the project will be finished and at what cost, if it proceeds at the current pace. [4]

This article aims to explain the purpose and concepts of earned value management and how it can be applied in order to improve projects. Further, the concept will be analysed where the advantages and disadvantages of the concept will be explained. Finally, the article will discuss the limitations of the concept, what it does and does not do.

Big idea

Earned value management (EVM) is a method used throughout the entire project life cycle to manage projects, programs, and portfolios to visualize the current status. The use of (EVM) dates back to the 1960s when the United States Department of Defense implemented a similar system, to control cost and schedule. It was first implemented as many projects had become more expensive and delivered later than anticipated. [5] EVM mainly consists of the three elements that often play a big role in project management; budget of cost, project schedule as well as scope of work. The main idea of EVM is to use these elements to develop a baseline which can be used and compared to the actual outcome of the project at a certain point. It is thereby important that these elements are established with care when the project is planned. The difference between the traditional cost management and earned value is the additional component earned value measuerement which is used to measure the actual accomplishment, for example, "after spending 50 percent of the budget, is 50 percent complete?" [6]

EVM allows project managers to integrate these already organized components to forecast the end date and final cost of the project, which then can be used to visualize the project status. Visualization is often very powerful within projects as it can be used to make sure that all stakeholders in a project have the same picture. Visualization also makes it easier to identify issues which allows the stakeholders, such as the project manager, to make efficient decisions based on objective data. [1][7][5] Due to the characteristics of EVM it can be used in various key areas within projects such as cost management, schedule management, scope management, risk management and integration management.[1] EVM can be seen as a critical method when it comes to project planning, execution and control as these areas often are related to measuring, analyzing and forecasting. [2]

Application

Förklara planned, earned och actual, kanske ska ligga under big idea? Förklara olika begreppen BAC, EV, PV osv (hör lite till den ovan). Göra en figur över earned value under big idea?

How is it used? Setting baselines - Deciding the planned values

In order to successfully apply earned value management there are a few requisites that should be fulfilled where the most crucial is to define the different baselines of the project. The baselines that need to be decided are the scope baseline, schedule baseline and budget baseline.[6] In the planning phase it is important to the convert the scope of work into a more distinct component which can be done systematically by using the Work Breakdown Structure (WBS). A well defined WBS is a core component in EVM as the different baselines are developed with the WBS used as the base. The lowest level of the WBS, also known as the work package, usually consists of a small number of measurable acticities such as a product, service or action that needs to be delivered.[5][2] In addition to the WBS the WBS dictionary is also developed, this is a document that explains each activity in the WBS more in detail. At this step the scope of work, WBS and WBS dictionary can be approved and form what is known as the scope baseline for the project.[1] Assign resposible person?. Further, the schedule of the project can be decided with the scope baseline and resource breakdown stucture as a base. When the project schedule is approved the schedule baseline for the project is set. When applying EVM the schedule baseline will work as a base to compare the actual outcome of the project from a time perspective. [2] The final baseline that needs to be set is the budget baseline. In order to set this baseline the budget itself first has to be decided which is done by assigning costs to each element in the WBS. However, the budget also needs to include a lot of other elements such as the management reserve - a pot of money reserved for unknown management control purposes, and the contingency reserve - a pot of money reserved to manage risk.[5][2]


Cite error: <ref> tags exist, but no <references/> tag was found
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox