FMEA
Abstract
The Failure Mode and Effect Analysis.
A tool used for analyzing how potential events can occur doe to failure within the company or project team. The elements analyzed with use of the FMEA tool, can be separated in a matrix and consists of failure events, how they can occur, why they occur and how the failure can be avoided. The different scenarios then get graded with regard to impact-fulness and chance of occurrence, the multiplied score is the used to rank each risk failure event according to their importunateness. The reason for the FMEA tool to have influence on the project management, is because the tool is strictly guiding the PM and his/her team to what topics to focus on in order to get a successful project result. The following report will include:
Contents |
General introduction to Risk Management
Risk management is the general term for managing unforeseen threats and opportunities. This includes identifying and analyzing risks as well as reacting or preparing appropriately to the identified potential scenarios of a project, program and portfolio. Furthermore, risk management can be applied on a verity of levels and scenarios, but the purpose remains to be a focus on minimizing, eliminating or taking advantage of unknown situations. Managing risk are to some extend essential as a proper risk management strategy can ensure a more optimal resource allocation as well as lowering the effects from an identified situation occurring all of which will improve a company's performance. However, to master risk management, the organization has to structure their approach depending on the particular stage of the project, program, portfolio and importantly use tools and methods of which align with a scope defined by the organization. [1] An example would be if a company are about to end a construction project. As the risk management is less uncertain, a tool like the Post Project Review (PPR) [2] would become attractive to use as it focusing on structuring the experience within the risk management of the project, for future projects exceed the previous performance with regard to the risks. In other words, the PPR tool is useful to a risk manager who has existing data of an ended project to apply to similar future projects. Another scenarios within risk management, and perhaps the most common scenario, is regarding the risk management of a new strategy, project, system or product. A scenario where the existing organization has limited knowledge of what risks to asses and how to asses them. Such scenario could be a new investment project within a new portfolio area. A project that has limited similarities to the existing projects within the portfolio. In order to asses the risk properly another type of risk management tool is to applied such as the FMEA risk assessment tool. [3]
Introduction to the FMEA tool
In a world where failure makings are assessed to be increasingly important with growing expectations from customers, clients, managers, investors and organizations, the importance of projects initialized on precise estimations and assessments becomes the backbone of business. [1] In this world, the risk assessments methodologies makes the main arguments for how the outcome of a project, system or strategy may be derived. Investing in a project without assessing the potential risks would be similar to walking out of the front door barefooted not knowing if it's going to rain, snow or be 45 degrees celcius. It is possible, but the outcome could be very unpleasant. This makes for the use of risk assessments and the Failure Mode and Effect Analysis (FMEA) methodology.
Invented to systematically test and analyze different ways in which a system can fail and with what following consequences that might occur. The tool was originally developed for military purpose in the 1950s but has become a more recognized failure mode assessment tool within the healthcare, public and private industry. The FMEA tool is a datadriven brainstorm where to potential failures are listed and the consequences of the failures ranked for a clear overview of which elements to perform damage control or potentially change entirely. This makes a project manager or team able to improve their initial risk assessments. [3] Furthermore, being a techniques first used more than 50 years ago it has been continuously improved and is now recognized as a key element of many quality management systems and general project, program and portfolio management scenarios. [4]
The FMEA tool and how it works
The FMEA tool is matrix based tool structuring information gathered and scenario created from a team within the organization. The purpose of this is to create as much intel and experience as possible from within the organization to use in the FMEA context. The tool in itself consists of a matrix with seven predefined columns off which the risk manager can insert information based on what was gathered and calculate the Risk Priority Number (RPN). It is important to note that a FMEA matrix can easily be modified, but in general the matrix would consist of seven columns. [4]
1 | 2 | 3 | 4 | 5 | 6 | 7 |
---|---|---|---|---|---|---|
Establish service journey | Possible failures | Consequence of failures | Impact (1-10) | List potential causes | Likeliness (1-10) | RPN (Impact x Likeliness) |
Elements of assessment | Potential failures connected to the stage |
The consequences from each failure |
How much the failure impacts the organization or project |
The reason(s) behind the failure |
The probability of the failure occurring |
The Risk Priority Number Indicating what to prioritize |
Each stage in the FMEA has an individual role in establishing an overview of the potential failures or risks that the organization could encounter. The first stage is establishing the scope of which the assessments is based on. This would preferably be a listed timeline if looking at a continuous event, an example could be a service journey or it could be a list of identified all uncertain events or areas of a project not time-dependent to each other, an example could be a construction project. Following is an example of a scenario with a flight journey, with the listed sequential stages:
Flight journey:
- Greed customer in the airport
- Receive luggage and print tickets
- Ensure that the customer knows of where and when the plane leaves
- Retrieve the ticket at the gate
- Seat the customer on the plane
- Serve food and beverages while in flight
- Ensure that the plane lands safely
- Retrieve the luggage to the customer.
All the listed stages are only to be listed in the first column (Establishing service journey). After identifying all stages of the journey, the second step in in using the FMEA tool is to describe the potential failure mode for each state meaning to gather as much quantitative or qualitative data, depending on the particular failure mode, in order to thoroughly asses the potential failure modes. The second column (Possible failures) is then used to list all potential failures connected to each stage in the flight journey. This part requires a team member(s) with great knowledge or experience to ensure the correct failures to be listed. The third column (Consequence of failures) requires an analysis of each possible failure listed and what outcome that could potentially occur if such failure where to happen. This process can be time-consuming and implicates precise estimations to ensure all consequences are listed with regard to the project scope. The fourth column (Impact) is a column used to notate how impactful the consequences are to the organization or project based on a scale from 1 - 10 where 10 is the highest impact. It is important that this stage is performed in a transparent manner and without implicating too much subjective biases. This stage is well affected be the knowledge within the risk management team and the quality of the output depends on how objective the team can perform this scoring. The fifth column (List potential causes) requires a back-tracing problem finding analysis, an example could be the use of a Fishbone Diagram[5] or 5 Why's[6] root cause problem seeking tool. both of which have the purpose of identifying what the potential causes of what the failure mode could be. The sixth stage (Indicate likeliness) is used to indicate the probability of the failure happening on a scale from 1 - 10 where 10 is the highest probability of the failure taking place in comparison to the rest of the identified failures. The estimation of this stage is best supported be data of previous scenarios to ensure a objective objective scoring, but for some scenarios without any historical information to how often the failure could take place, a subjective guesstimate based on the skillsets and knowledge within the risk management team can be the only solution.
The last stage (RPN) is a multiplication of the Impact scores and the Likeliness scores to create a Risk Priority Number for the risk manager to prioritize which failure modes to focus on for mitigation actions.[3]
An example of how a full FMEA matrix is performed can be followed bellow. More so, the table can (by the authors permission) be copied and used for any risk management scenario requiring a failure mode and effect assessment.
1 | 2 | 3 | 4 | 5 | 6 | 7 |
---|---|---|---|---|---|---|
Establish service journey | Possible failures | Consequence of failures | Impact (1-10) | List potential causes | Likeliness (1-10) | RPN |
#1 Greed customer in the airport. |
Missing the costumer and the customer not checking them in. |
The customer won't make the flight at all |
1 | - Lack of service education. - Lack of signs and guidance towards the counter. |
2 | 2 |
#2 Receive luggage and print tickets. |
Not receiving all luggage or printing the wrong ticket(s). |
The customer is not able to go trough security. Delayed flight departure or the customer missing the flight and becoming unsatisfied |
5 | - Lack of service education. - Bad position to identify all luggage at the counter. |
4 | 20 |
#3 Ensure that the customer knows of where and when the plane leaves. |
Not informing the customer correctly about the flight information. |
Leaving the customer confused and unable to find the correct gate in time of departure. Delayed departure. |
4 | - Lack of service education. - Stressed situation. |
3 | 12 |
#4 Retrieve the ticket at the gate. | Missing a customer at the gate counter. | Risk of boarding the wrong customer resulting in a delayed flight departure |
7 | - Stressed situation. - Bad gate structure. - Not identifying. a confused passenger or a passenger with bad intentions. |
2 | 14 |
#5 Seat the customer on the plane. | Seating the passenger in a wrong seat. | Risk of passengers having to sit on the same seat and needing to discuss which seat to be replaced at. Delaying the departure. |
2 | - Miss-communication from flight attendants. - Over-booked plane. |
8 | 16 |
#6 Serve food and beverages while in flight. |
Missing a passenger and their chance to get serviced in flight. |
Missing opportunity of earning money or leaving passenger unsatisfied. |
2 | - Communication among flight attendants. - Bad service practice. |
9 | 18 |
#7 Ensure that the plane lands safely. |
A rough landing or crashing the plane. | Unsatisfied customers or having to deal with big financial consequences due to expenses connected to a flight crash. |
10 | - Missed maintenance. - Un-experienced officers. - Bad pilot practice. |
1 | 10 |
#8 Retrieve the luggage to the customer. |
Missing the luggage on the way to the luggage pick-up-area. |
Unsatisfied customer and potentially having to compensate financially for the lost luggage. |
7 | - Bad practice from on-ground staff. |
5 | 35 |
This example shows how the FMEA tool is visual structured. The output from this example consists of a clear structure and failure mode ranking for the risk manager to attend. It shows how step #8 in this customer journey is the most important element to attend, being the overall most likely and impactful risk within the service journey. Furthermore, the FMEA result shows how the Ensure that the plane lands safely mode has a low priority from a risk management perspective even though it has the absolute highest impact.
How does the tool work
Before using the FMEA matrix, it is important for the project manager to clearly understand if his/hers project is a system, product or process. To get the most from the tool, it is however important to apply it in an early stage of a project, this could be in the initialization of the risk assessments of a project or particular part of the project. This means that what ever result made from the assessment can potentially help avoiding a potential failure, before it happens.
Limitations of the tool
The FMEA has some clear limitations. Firstly, when using the tool, the output is very much defined by the quality of the input. To get the absolut bedst from the FMEA, the project manager needs to gather a lot of information, data and experience. However, if the quality of the out put is not as important as the result of the ranking, then the FMEA might still be a genuinely good tool for a project manager to manage risks and potential risks.
Theory and purpose
The FMEA tool is considered a part of a risk assessment. The tool is considered a "what could happen" or "What would happen" situation assessment tool and is useful after gathering an overview of risks from I.e. a risk matrix assessment or similar tools. [3] The purpose of the tool is to avoid biased decisions based on limited analysis of dept or assumptions based assessments. The methodology consists of assessing each and every element of identified risks fully from the initial defined risks and trough to the absolute end of potential secondary impacts. This helps to create a more accurate assessment of the impact in particular the impact of a potential risk occurring with regard to the side effects and rebound effects depending on the particular usage. Furthermore, the tool does not exceed in assessing the probability of an instance occurring as this is out side the scope of the tool. This can however be assessed with a simulation approach, depending of the event of topic.
Application of the tool in Risk Management
Application in general
The step by step approach of the FMEA tool can be considered more circular with regard to the general risk assessment of a project, system or service. In this application description, the tool will be considered in combination with a classic risk matrix used by many companies when assessing the impact and chance of occurrence of risks on projects.
Risk Matrix
The risk matrix consists of two axis. One tells the probability of occurrence and the other tells the magnitude of the impact when occurring. the x,y coordinates are then used for plotting the identified risks. Here is an example of how on could apply the risk matrix.
identifying the risks:
- Misinformation given to customers
- Fail to check in customers
- Losing a customer's luggage
- Fail to place luggage on the plane
- Fail to leave on time (air port)
- Fail to serve customers in flight
- Damaging luggage
- Fail to retrive luggage to customer
Placing risk in a risk matrix:
These placements would typically be allocated based on simple based decisions and even though they can be realistic at first glimt, the reality is typically much different. This makes for the benefit of using the FMEA tool.
FMEA and Risk Matrix
The application of the FMEA is useful for assessing the initial risk assessment from the Risk Matrix, and can be further investigated trough data quantitative or qualitative investigations depending on the particular element. Here is an example of how the FMEA tool is applied in combination with the Risk Matrix and its initial identified risks.
As seen, some of the initial rankings might have changed due to more thorough investigations and the result from the FMEA model can then be re applied to the Risk Matrix, as well as used for ranking the importance of addressing for each risk.
Application by PM on a project
The FMEA tool would be applied by a project manager when looking into new projects. The PM should then gather the most experienced team within the project team and maybe even some prominent stakeholders, in order to get as many failure modes as possible. Then the PM could prioritise due to different sets of focuses on the project result. For instance, if a particular stakeholder has highly important needs from what the project delivers, then the potential failure modes affecting those needs would become relevant to encounter. [7]
Alternative applications
On an existing project, then the Project Manager could use the FMEA as an evaluation tool for current as well as previous incidents. The important difference here is that the tool would now be used with a focus on solutions to the failure modes rather than a pinpointing of which failure modes to analyze.
Final notes
Annotated Bibliography
3 key references.
References
- ↑ 1.0 1.1 Project Management Institute, Inc. The Standard of Risk Management in Portfolios, Programs and Projects, Year 2019
- ↑ Project Management Procedures, High Voltage Power Network Construction By Keith Harker, Published by The Institution of Engineering and Technology, London, United Kingdom, Year 2018
- ↑ 3.0 3.1 3.2 3.3 Innovation Portal: FMEA tool and how it works , http://www.innovation-portal.info/wp-content/uploads/FMEA.pdf/ , By Joe Tidd and John Bessant, October 21st, Year 2014
- ↑ 4.0 4.1 Applying FMEA in risk management, Risk Management Using Failure Mode And Effect Analysis, By D.H. Stamatis, Year 2019
- ↑ Introduction the root cause analysis tool Fishbone diagram, Fishbone diagram for technological analysis and foresight, By Mario Coccia, Year 2020
- ↑ Introduction to the problem identification method 5 Why's, The Five Why's Technique, By ASB, Year 2009
- ↑ General information about the FMEA tool, FMEA from Theory to Execution, Second Edition, By D. H. Stamatis, Year 2003