Project Schedule development

From apppm
Revision as of 23:03, 18 February 2018 by Radoslaw (Talk | contribs)

Jump to: navigation, search

Contents

Abstract

Soon. Stay tuned.

Motivation

There are many reasons behind Project Schedule development to be taken with appropriate caution, while planning time frame of the project. First of all, it provides in structure way the scheme and toolkit for planned activities. Following the guidelines, it allows to build sufficiently detailed plan of actions with the time frame for each activity, enable tracking the progress and updating the schedule if necessary. Secondly, implemented correctly decrease the risk of delays, helps allocated resources, which may results in minimizing potential costs of the project.

Introduction

Project Time Management

Project Time Management is defined as set of processes with outputs to ensure all the activities throughout the project are accomplished on time.[1].. It is about increasing both efficiency and effectiveness and to control over the time spent on the particular tasks. As one of the key Project Management areas, the process plays a major role in each out of five project phases. It reflects to the overall performance during the project life cycle as well as the individual task consumption.“Control of time is competitive advantage”[2], wisely used can increase benefits and decrease the costs of a project.

Project Management Overview
Figure 1: Project Management Overview, inspired by PMBOK® Guide [3].

As it is shown in Figure 1. according to PMBOK, The Time Project Management consists of :

  • Active Definition- defining particular tasks necessary to accomplished project's goals.
  • Activity Sequencing- defining dependencies between project's tasks.
  • Activity Duration Estimating- estimating the number of work periods that will be needed to execute individual task.
  • Schedule Development- evaluating the sequences of the tasks, its duration and resources requirements in order to prepare the project schedule.
  • Schedule Control- monitoring variations to the project schedule.

(different sources: PMI[4] divides it into 4 areas: Time Planning, Time Estimating, Time Scheduling and Time Control).

The overview is meant to be standardized for general purpose of the all project, however based on close connection between Activity Sequencing,Duration Estimating and Development, they may be treated as one process, especially in small projects.[5].

Schedule Development

As the project has starting and finishing date as the project's activities should have them as well. It is essential to define a beginning and a end time of the individual work during life cycle of the project in Project Management. Therefore, Schedule Development as a one of the core processes in Planning Processes[6] should be proceed with details and after analyzing key activities. With its nature to recognize the realistic time and resources limitations, Scheduling takes both into account while preparing the plan. Since the base line of the schedule is affected by many factors, executing this process, PMs should have in mind that the procedure must be iterated.

The flow of Schedule Development is determined by the steps (see Figure 1.) :

1.Inputs
  1.1 Project network diagram- visual overview of the sequence and dependency(relation) between the activities.
  1.2 Activity duration estimates- estimating the number of work periods that will be needed to execute individual task.
  1.3 Resource requirements- Quantity and type of resources required for each activities from Work Breakdown Structure (WBS)  
  1.4 Resource pool description- Quantitative and type availability of resources during project. 
  1.5 Calendars- Defining periods when work is allowed
  1.6 Constrains- Limitations that affects project's team work. There are two main types :
      1.6.1 Imposed dates,
      1.6.2 Key events and major milestones.
  1.7 Assumptions- hypothesis and beliefs, which are taken for granted for the purpose of the project
  1.8 Leads and Lags- Dependencies between predecessor and successor activities

2. Tools and Techniques

  2.1 Mathematical Analysis- based on theoretical calculations of starts and finishes of the activities (without taking under consideration any constrains) it provides the time windows where particular activity should be proceed. As most known methods includes:
     2.1.1 Critical Path Method (CPM)
     2.1.2 Graphical Evaluation and Review Technique (GERT)
     2.1.3 Program Evaluation and Review Technique (PERT)
  2.2 Duration compression- Process used to shorten duration of the activities without interfering into the scope of the project. Methods included in the process :
      2.2.1 Craching
      2.2.2 Fast Tracking
  2.3 Simulation- Based on assumptions multiple duration of the activities are calculated. The most known simulation is Monte Carlo Analysis.
  2.4 Resource leveling heuristics- based on resources constrains and limitation, starts and ends date of the activities are adjusted.
  2.5 Project Management software- These products allows to speed up above calculation by automating the processes

3. Outputs

  3.1 Project schedule
  3.2 Supporting detail
  3.3 Schedule management plan
  3.4 Ressource requirement updates

Tools & Implementation

Limitation of PSD

Output of PSD

Glossary

References

  1. Page 59, 1996 ed. PMBOK® Guide.
  2. https://www.pmi.org/learning/featured-topics/time. Retrieved 11 February 2018
  3. Page 60, 1996 ed. PMBOK® Guide.
  4. https://www.pmi.org/learning/library/time-management-project-functions-schedules-5283. Retrieved 11 February 2018
  5. Page 60, 1996 ed. PMBOK® Guide.
  6. Page 47, 1996 ed. PMBOK® Guide

Bibliography

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox