Femern
From apppm
Revision as of 08:48, 3 March 2020 by Luis John Casares (Talk | contribs)
Contents |
Collection of tools
Plan Quality Management
Manage Quality
Control Quality
Schedule Management
Estimation of Activity Durations: Three-Point Estimating[1]
Three-point estimating is a tool used to estimate the duration of an activity. It is used primarily when there is insufficient historical data available to produce an estimate. The tool considers a most likely time (tM), optimistic time (tO) and pessimistic time (tP) to produce the best estimate via the following equation:
tE = (tM + tO + tP)/3
Using this triangular distribution estimation uncertainty and risk can be reduced with respect to single-point estimating.
References
Cite error:
<ref>
tags exist, but no <references/>
tag was found