Net Present Value (NPV)

From apppm
Revision as of 15:32, 19 March 2022 by DeepthiTharaka (Talk | contribs)

Jump to: navigation, search

Written by Deepthi Tharaka Parana Liyanage Don- s203116

Contents

Abstract

Financial appraisal is a method used to evaluate whether a proposed project or portfolio of investment projects is worthwhile by considering the benefits and costs that result from its execution [1]. Investment decisions of the management are critical to a company since it decides the future of the company. This article discusses the net present value (NPV) method which is widely used in the financial appraisal. NPV is a dynamic financial appraisal method that considers the time value of money by applying discounting to all future payment series during the investment period [1]. In simple terms, the NPV is the difference between the project's future incoming and outgoing cash flows at present time. The calculation of the NPV starts by determining the net cash flows from the difference of future incoming cash flows and outgoing cash flows for each period of an investment. After the net cash flow for each period is calculated, the present value (PV) of each one is achieved by discounting using a suitable discount rate. NPV is the cumulative value of all the discounted future net cash flows [1] [2].

Firstly, this article discusses the idea behind the NPV method. Then this introduces the NPV calculation method [1] and describes the importance of choosing the suitable discount rate [3]. Also, it discusses the other NPV formula for special cases such as annuity and perpetuity. Then it highlights the decision criteria behind NPV and explains it with real-life applications. Finally, it critically reflects on the limitations [4] of this method and briefly highlights the key references used in this article.

Big Idea

According to ISO 21502, a business case is a documented justification to support decision making about the commitment to a project, program or portfolio (cite). It is a critical point in the initial stage of a project, program, or portfolio where it uses to obtain the approval for investment by presenting the benefits, cost, and risk associated with alternative options [5] [6] [7]. The business case is produced by the client or the sponsor of the project, program or portfolio and the directorate of an organization uses this document to accept or reject the case. [8]. In a business case, financial appraisal plays a key role to answer the fundamental economic questions of whether an investment should be made and which project should be chosen among a selection of different alternatives. Because the task of financial appraisal is to predict the financial effects of planned investment and to present the data in order to get critical investment decisions [1]. NPV method is one of the most frequently used approaches in the financial appraisal of a project [1] [9].

What is NPV?

NPV is the present value of the future net cash flows of an investment. [1]. In other words, NPV is the difference between the present value of all future incoming cash flows and the present value of all future outgoing cash flows. The NPV of a project is calculated based on different assumptions [3] [4] [10] such as:

  • Money in the future will not be worth the same amount of money today. Therefore, all the future cash flows are translated to present value by discounting them using a suitable discount rate.
  • The discount rate remains the same throughout the life of the project.
  • The incoming or outgoing cash flows other than the initial investment occur at the end of each period.
  • The cash generated by a project is immediately reinvested at the discount rate.

NPV is a widely used method in the financial appraisal that has the following benefits [4] :

  • NPV considers the concept of the time value of money by obtaining the present value of future net cash flows.
  • NPV calculation considers the complete life cycle of an investment using the expected future cash flows in different periods of time.
  • It has the additive property. That means the possibility to sum the NPV of individual projects to evaluate the project portfolio.
  • Reflects the return on capital investments in the best and clearest way.
  • NPV method enables the decision-making process for companies by identifying whether a particular investment is profit-making or loss-making.

Time value of money

NPV considers the time value of money in the analysis, which makes the NPV more precise than other financial appraisal methods. Time value of money means that a sum of money is worth more now than the same sum of money in the future [4] [11]. That is because the money you have now can use to make more money by buying something now and selling it later for more, running a business or depositing it in the bank, and earning interest. Since money can grow only through investing, investment delay is an opportunity cost. That means not having the money right now also includes the loss of additional income, which could be earned by having money earlier. Future money is also less valuable because inflation erodes its buying power. Moreover, receiving money in the future rather than now may involve some risk and uncertainty regarding its recovery. For these reasons, future cash flows are worth less than the present cash flows. NPV assesses the profitability of a given project on the basis that cash flow in the future is not worth the same as a cash flow today. The time value of money is recognized in NPV by applying discounting to all future cash flows generated during the investment period using a suitable discount rate[9].

Discount Rate

Figure 3: NPV vs. Discount rate (i). Own creation inspired from [2].

The discount rate is the rate used to determine the present value of future cash flows in NPV calculation. The discount rate is a crucial component in determining NPV and the selection of discount rate will be company specific since it is related to how the company finds its funds [3]. If an investment is financed completely with equity, the discount rate can be obtained from a cost of equity. Completely Debt-financed investments can be analyzed using the cost of debt. If an investment depends on both equity and debt financing, the discount rate is the weighted average cost of capital (WACC) and can be calculated as the weighted average of the cost of equity and cost of debt [3]. The weighted average cost of capital is often used in companies as the discount rate [1]. For small projects, where it is hard to identify the equity and debt used for financing a single project, the weighted average cost of capital of the whole company is usually assumed as the discount rate [3].

However, it is appropriate to use higher discount rates to reflect other factors such as risk, the opportunity cost of money invested in the infrastructure and etc [2]. An NPV calculated using variable discount rates may better reflect the situation than one calculated from a constant discount rate for the entire investment duration [1].

The choice of the discount rate can dramatically change the net present value since the NPV is an inverse function of the discount rate (i). Higher the discount rate, the smaller the net present value. The discount rate where the NPV is zero is called the internal rate of return (IRR).

Formula

The following formula use these common variables [1]:

Variable Meaning
P V Present Value
t Time of the cashflow
C I _{t} Cash inflows in period t
C O _{t} Cash outflows in period t
{\left(C I _{t}-C O _{t}\right)} = N C _{t} Net cash flow in period t
I_{o} Investment in t=0
L_{n} Liquidation proceeds in t=n
i The discount rate
n Total number of periods
Figure 1: Projection of a future net cash flow in time t into a present value. Own creation inspired from [10].

In order to consider the time value of money, the NPV method considers the value of an investment at the present time by projecting all future cash flows into a key figure at the time today. This projection of the value that a future cash flow has in the present is called present value (PV). To get the present value (PV) of a future net cash flow in period t, it is discounted using a discount rate (i) as follows:

P V=\frac{\left(C I _{t}-C O _{t}\right)}{(1+i)^{t}} [1]

Example:

If a project is expected to receive $5,000 with 10% discount rate after 4 years, its present value (PV) can be calculated as:

P V=\frac{\left(C I _{t}-C O _{t}\right)}{(1+i)^{t}} [1]

P V=\frac{5000}{(1+0.1)^{4}} = $3415


NPV combines these projections of net cash flows to assess the overall value of a project from the present view. In simple terms, the NPV is calculated from the difference of the present value of all future incoming cash flows(revenues/benefits) and the present value of all future outgoing cash flows(costs) [1]. Therefore the NPV is given by:

N P V=\sum_{t=0}^{n} \frac{\left(C I _{t}-C O _{t}\right)}{(1+i)^{t}} [1]

Figure 2: Illustration of calculation procedure of NPV. Own creation inspired from [10]

The difference between the cash inflows and cash outflows, {\left(C I _{t}-C O _{t}\right)} gives the net cash flow, N C _{t} of the corresponding period. For normal investments which are characterized by initial investment, I_{0}, subtracting the initial investment outlay, I_{0} from the present value of the net cash flows gives the net present value. If a possible final payment, L_{n}, for the liquidation of the investment in t = n is also considered, the calculation of the NPV can be written as follows [1]:

N P V=-I_{0}+\sum_{t=1}^{n} \frac{N C _{t}}{(1+i)^{t}}+\frac{L_{n}}{(1+i)^{n}} [1]


As a summary, the following steps are recommended for the calculation of the net present value [1]:

  1. Determination of the initial investment, I_{0} .
  2. Estimate the expected net cash flows, N C _{t} from the investment for each period of the planning period.
  3. Selection of the uniform discount rate, i.
  4. Determination of the present value through discounting of the expected net cash flows, N C _{t} with the discount rate.
  5. Subtraction of the initial investment, I_{0} from the present value. This gives the net present value.

Example:

A company decides to invest $100,000 for a project which is expected to give the following cash flows. Assume the discount rate is 10%. Calculate the NPV of the project.

Now Year 1 Year 2 Year 3
Initial Investment $100,000
Running costs $60,000 $90,000 $90,000
Revenues $80,000 $100,000 $120,000
Liquidation proceeds $140,000

Using NPV formula, NPV can be calculated as follows:

N P V=-I_{0}+\sum_{t=1}^{n} \frac{N C _{t}}{(1+i)^{t}}+\frac{L_{n}}{(1+i)^{n}} [1]

N P V=-100,000+ \frac{(-60,000+80,000)}{(1+0.1)^{1}}+ \frac{(-90,000+100,000)}{(1+0.1)^{2}}+\frac{(-90,000+120,000)}{(1+0.1)^{3}}+\frac{140,000}{(1+0.1)^{3}}

N P V=-100,000+ 18182+ 8265+ 22539+ 105184 = $54170

Other NPV Formula

NPV of an annuity

If the net cash inflows are uniform and equidistant and occur at the end of each period, the series of net cash flows can be interpreted as an annuity [1]. The payments or receipts occur at the end of each period for an ordinary annuity while they occur at the beginning of each period for an annuity due. Using the formula for the present value of an ordinary annuity, NPV can be calculated as follows [1]:

N P V=-I_{0}+N C  \cdot\left[\frac{(1+i)^{n}-1}{i \cdot(1+i)^{n}}\right]+\frac{L_{n}}{(1+i)^{n}} [1]

Example:

If a company decides to invest $100,000 for a project which is expected to give the following cash flows. Assume the discount rate is 10%. Calculate the NPV of the project.

Now Year 1 Year 2 Year 3
Initial Investment $100,000
Net cash flows $60,000 $60,000 $60,000
Liquidation proceeds $140,000


Using NPV of an annuity formula,

N P V=-I_{0}+N C  \cdot\left[\frac{(1+i)^{n}-1}{i \cdot(1+i)^{n}}\right]+\frac{L_{n}}{(1+i)^{n}} [1]

N P V=-100,000 + 60,000 \cdot\left[\frac{(1+0.1)^{3}-1}{0.1 \cdot(1+0.1)^{3}}\right]+\frac{140,000}{(1+0.1)^{3}}

N P V=-100,000 + 149211 + 105184 = $154395

NPV of a perpetuity

For the special case that, net cash flow is considered as perpetuity, which is given for an infinite and constant stream of identical cash flows the NPV can be expressed as follows [1]:

N P V=-I_{0}+\frac{N C}{i} [1]

Example:

A company decides to invest $100,000 for a project which is expected to give a net cash flow of $60,000 in perpetuity with a discount rate of 10%. Calculate the NPV.

Using The NPV of a perpetuity formula,

N P V=-I_{0}+\frac{N C}{i}

N P V=-100,000+\frac{60,000}{0.1}

N P V=-100,000+ 600,000 = $500,000

Decision rule

Net present value is used to assess the attractiveness of the investment and it shows how much value an investment or project adds to the firm and the decision to accept or reject the investment is taken based on the following decision rule [2].

Condition Idea Decision
If NPV > 0 Investment increase the value (profit) of the company in the amount of the net present value. Investment can be accepted.
If NPV = 0 The investment just returns the cost of capital. No increase or decrease in wealth results. This project adds no monetary value. Difficult to get the decision whether to accept or reject the project. Decision should be based on other criteria.
If NPV < 0 An implementation would destroy value (profit) in an amount equal to the negative NPV. The investment can be rejected.

As a summary, the following two profitability criteria must be met for the economic viability of an investment [2]:

Absolute profitability: NPV of an investment option must be positive or at least zero (NPV≥ 0).

Relative profitability: The option with the highest positive NPV is the most profitable and usually the preferred option, provided that the investment risk is the same.

Applications

For businesses, the NPV method facilitates decision-making in the investments of projects, programs, and portfolios since it helps to determine whether a given investment is profitable or loss-making. As explained in previous examples in the above sections, NPV can be calculated simply using the corresponding formula. Generally, NPV is widely used to evaluate the financial viability of different types of investments such as independent projects, mutually exclusive projects, contingency projects and etc [4].

  • Independent Projects:

An Independent project is a project where the acceptance or rejection does not depend on the acceptance or rejection of other projects. If the organization has the capacity to run several projects at once, in the case of independent projects, all profitable projects will be accepted and ranking is not really important [4].

Example:

A company has an opportunity to invest in the construction of a new production line and at the same time the reconstruction of a factory currently used to produce one of its products. Net cash flows of the two projects are as follows and assume that the discount rate is 10% for both projects.

Now Year 1 Year 2 Year 3 Year 4 Year 5 NPV
Construction of a new production line -$1,000,000 $75,000 $275,000 $450,000 $500,000 $525,000 $198,350
Reconstruction of a factory -$1,000,000 $600,000 $575,000 $75,000 - - $250,000

Since both NPV > 0, the company can accept the investment in both projects since it has the ability to invest in both.

  • Mutually Exclusive Projects:

Investment projects are said to be mutually exclusive when the selection of one will exclude the acceptance of the other. In simple terms, the acceptance of one prevents the acceptance of an alternative proposal. Because two or more projects cannot be pursued simultaneously due to different constraints in projects, programs, or portfolios. In the case of mutually exclusive projects; NPV is a widely used method to select which project or program is important to invest and the one with the higher NPV should be selected [4].

Example:

A company has a place, which can be used to build a food manufacturing business or a steel manufacturing plant. The company cannot implement both projects due to financial constraints. The expected net cash flows associated with the two projects are as follows and assume a 10% discount rate.

Now Year 1 Year 2 Year 3 Year 4 Year 5 NPV
Food manufacturing business -$5,000,000 $4,000,000 $1,000,000 $800,000 $600,000 $300,000 $489,590
Steel manufacturing plant -$5,000,000 $1,000,000 $1,000,000 $1,900,000 $2,200,000 $2,300,000 $745,660

Even though both projects give positive NPV, the company cannot invest in both since they are mutually exclusive. Therefore it has to select the project which gives the highest NPV. In this case, it is the steel manufacturing plant.

  • Contingent Projects:

Contingent projects are dependent projects where the acceptance or rejection of one project necessitates acceptance or rejection of one or more other projects. For Example, the decision to invest in a medical testing laboratory may depend on the decision to build a private hospital nearby. The cash inflows of the medical testing laboratory will be enhanced by the presence of a nearby hospital and vice versa.

Limitations

  • NPV calculation is based on several estimates such as future cash flows and discount rate, therefore there is a high chance for errors that can drastically affect the end result of the calculation. Since every project has a unique set of processes there is lots of room for errors in estimating cash flows and the actual figures can have great variance. NPV often takes an optimistic approach to future cash flow calculations by overestimating benefits (incoming cashflows) and underestimating costs (outgoing cashflows). These problems can be mitigated by double-checking estimates, performing sensitivity analysis or Monte Carlo analysis after doing the initial calculations [11]. On the other hand, Investment decisions based on the NPV method are highly sensitive to the selected discount rate. Using a discount rate that is too low will make suboptimal investments and using too high will result in rejecting good investments. Moreover, the NPV is calculated based on the assumption that the discount rate remains the same throughout the life of the project. Therefore, it does not account for the fluctuation of discount rates according to the market situation [4]. To remove this limitation NPV can be calculated using variable discount rates if they are known for the duration of the investment [1].
  • The NPV is expressed in absolute terms rather than a relative term. Therefore it does not useful for comparing projects of different sizes as the largest projects typically generate the highest returns [4]. The size of the NPV output is determined mostly by the size of the input. A higher NPV does not necessarily mean a better investment. If there are two investments or projects up for decision, and one project is larger in scale, the NPV will be higher for that project as NPV is reported absolute terms and a larger investment will result in a larger NPV number. It is important to assess the returns from an investment in percentage terms to get an accurate picture of which investment provides a better return.
  • It does not consider the non-cash benefits generated from a project into consideration while making decisions. NPV method is purely quantitive in nature and does not consider qualitative factors. Some elements of the costs and benefits of the projects are not quantitative, so there is great difficulty in taking them into consideration. NPV method gives financial feasibility of different projects, but often, other qualitative factors exist that must be considered.

Annotated Bibliography

Häcker J. and Ernst D., Ch. 8 - Investment Appraisal. In: Financial Modeling. Global Financial Markets(2017), pp.343-384

The investment appraisal chapter in Financial modeling book by Häcker J. and Ernst D. introduces the concept of investment appraisal and provides a good overview of methods and approaches in investment management. The book introduces the static & dynamic approaches of investment appraisal and provide a comprehensive discussion on different methods under each approach & describe why dynammic approaches such as NPV, IRR are superior than the static approaches like payback. The writers introduce the net present value as one of the main methods of dynamic approach and it clearly describes the NPV calculation method and the importance of underlying variables of NPV formula. The book was the ideal source to provide a good explanation of the concept of financial appraisal, the concept of NPV, how to calculate NPV & its applications. Also, this was useful to get idea about the other methods such as payback, IRR etc.

Ferrari, C., Bottasso, A., Conti, M. and Tei, A., Ch. 5 - Investment Appraisal. In: Economic role of transport infrastructure: Theory and models (2018), pp. 85-114

Chapter 5 of Economic role of transport infrastructure: Theory and models book by Ferrari, C., Bottasso, A., Conti, M. and Tei, A. introduce the importance of investment appraisal in large projects such as transport infrastructure. It critically highlights the different financial appraisal methods and it especially highlights the importance of Net present value in the context of large projects. Especially it points out the relationship of discount rate & time period with NPV and the importance of selecting the correct discount rate when the projects are appraised based on net present value. It provides different approaches to determine the discounting rates. This chapter also highlights the NPV calculation method & how to treat when project are mutually exclusive. Additionally it introduces the importance of performing sensitivity analysis when calculating NPV. This is a good reference to get overall picture behind the financial appraisal methods and its applications.

Poggensee K. and Poggensee J., Ch. 3 - Dynamic Investment Calculation Methods. In: Investment Valuation and Appraisal (2021), pp. 85-140

The book Investment Valuation and Appraisal by Poggensee K. and Poggensee J. was a useful reference to get a thorough idea about the appraisal of projects using different financial appraisal methods. Chapter 3 of this book introduces the dynamic investment appraisal methods such as net present value, Internal rate of return, annuity method, etc. It critically argues the assumptions of dynamic investment appraisal methods. It highlights the net present value as the most widely used method in the dynamic approach and introduces the NPV and discounting concepts. This was a good source to get the idea of discounting where projecting the future net cashflows into present time and NPV calculations based on different scenarios such as annuity, perpetuity etc.


References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 Häcker J. and Ernst D., Ch. 8 - Investment Appraisal. In: Financial Modeling. Global Financial Markets, (Palgrave Macmillan, London, 2017), pp. 343-384, https://doi.org/10.1057/978-1-137-42658-1_8
  2. 2.0 2.1 2.2 2.3 2.4 Ferrari, C., Bottasso, A., Conti, M. and Tei, A., Ch. 5 - Investment Appraisal. In: Economic role of transport infrastructure: Theory and models, (Elsevier, 2018), pp. 85-114, https://doi.org/10.1016/C2016-0-03558-1
  3. 3.0 3.1 3.2 3.3 3.4 Žižlavský, O., Net present value approach: method for economic assessment of innovation projects. Procedia-Social and Behavioral Sciences, 19th International Scientific Conference, Economics and Management, 156 (2014), pp. 506-512.
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 Bora, B., Comparison between net present value and internal rate of return, International Journal of Research in Finance and Marketing, (2015), 5(12), pp.61-71
  5. AXELOS, Managing Successful Projects with PRINCE2, 6th Edition, (The Stationery Office Ltd, 2017).
  6. AXELOS, and Office Cabinet., Managing Successful Programmes, 2011 Edition, (The Stationery Office Ltd, 2011).
  7. AXELOS, Office of Government Commerce, Kilford, C., Management of Portfolios, 2011 Edition, (The Stationery Office Ltd, 2011).
  8. Ing E. and Lester A., Ch. 5 - Business case and Ch. 6 - Investment Appraisal. In: Project Management, Planning and Control. 7th Edition, (Elsevier, 2017), pp. 25-36, https://doi.org/10.1016/B978-0-08-102020-3.00006-1
  9. 9.0 9.1 Konstantin P. and Konstantin M., Ch. 4 - Investment Appraisal Methods. In: Power and Energy Systems Engineering Economics, (Springer, Cham, 2018), pp. 39-64, https://doi.org/10.1007/978-3-319-72383-9_4
  10. 10.0 10.1 10.2 Poggensee K. and Poggensee J., Ch. 3 - Dynamic Investment Calculation Methods. In: Investment Valuation and Appraisal, (Springer, Cham, 2021), pp. 85-140, https://doi.org/10.1007/978-3-030-62440-8
  11. 11.0 11.1 LOCK, D., Project management. 10th edition, (Farnham, Surrey, England, Gower Pub., 2013).
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox