Estimations: Basic Techniques

From apppm
Revision as of 16:27, 10 August 2017 by Admin (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Contents

Estimation Techniques

Historical data

Parametric estimating

  • Based on parameters, e.g. square meters, tons of steal, etc. This can vary in levels of detail, from 1 parameter to several
  • Projects are rarely totally unique, often repetition of activities at lower levels of WBS
  • Break down project into units that can be readily estimated based on considerable experience of a particular type of project
  • Can be used at different levels of the product breakdown

Expert judgement

People are asked to make rough estimates, but the estimate becomes the target time

  • One or more experts in the application area use their experience to predict costs or time. Process iterates until some consensus is reached. (Also called Delphi studies)
  • Advantages: Relatively cheap estimation method. Can be accurate if experts have direct experience of similar projects
  • Disadvantages: Very inaccurate if there are no experts!

Analogy or As… but…s

  • Experience of similar projects
  • Use previous cost as base line (assuming validity) and proportion up or down
  • The time or cost of an project is computed by comparing the project to a similar project in the same application domain
  • Advantages: May be accurate if project data available and people/tools the same
  • Disadvantages: Impossible if no comparable project has been tackled. Needs systematically maintained cost/time database
  • Note: make sure you use the real cost and not the budget of your reference project

Forecasts

  • A ‘best guess’ under uncertainty (e.g. exchange rates)
  • Use parametricsor proxies
  • Differentiate between fixed (firm/known) and variable costs (fluctuate, estimate)
  • Provide series of estimates to see impact on budget
  • Factor in element for risk

Synthetic estimating

  • Based on practices of work measurement
  • If large number of repetitive actions, work rate can be analysed to provide generic actions, timings and costs
  • Deconstruct new activities into similar actions and add timings

Using learning curve effects

  • Often repetitive elements at lowest level of WBS
  • Time taken for a task if repeated will decrease as the person becomes familiar with the method
  • Subsequent improvement is speed becomes smaller over time

"missing formulas"

Wishful thinking

  • Optimism bias –over-optimistic on how much can be achieved and how little it will cost
  • Politics –large figures likely to be unacceptable, the objective is placed above costs
  • Improper use of estimates –ball park figures become official without checking or further development
  • Failure to be systematic about planning –complacency, certainty will not have to do work, vagueness, unqualified estimate to ‘get the request off the desk’
  • The best techniques are still only estimates
  • Errors at this stage can be multiplied many times

Things to consider

  • Rapid, rough and right (roughly right over precisely wrong) –detail over time
  • Three point estimate, qualitative understanding, thinking of alternatives
  • The best techniques are still only estimates
  • One size does not fit all! Level of precision depends on the project

Bottom Up and Top Down Estimation

Any of these approaches may be used top-down or bottom-up.

Top-Down

  • Start at the system level and assess the overall system functionality and how this is delivered through sub-systems.
  • Usable without knowledge of the system architecture and the components that might be part of the system.
  • Takes into account costs such as integration, configuration management and documentation.
  • Can underestimate the cost of solving difficult low-level technical problems.

Bottom-Up

  • Start at the component level and estimate the effort required for each component. Add these efforts to reach a final estimate.
  • Usable when the architecture of the system is known and components identified.
  • This can be an accurate method if the system has been designed in detail.
  • It may underestimate the costs of system level activities such as integration and documentation.

Top-Down Estimates

  • Are usually are derived from someone who uses experience and/or information to determine the project duration and total cost.
  • Are made by top managers who have little knowledge of the processes used to complete the project.

Bottom-Up Approach

  • Can serve as a check on cost elements in the WBS by rolling up the work packages and associated cost accounts to major deliverables at the work package level.
Bottom up estimation technique.jpg
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox