Stage-Gate Process

From apppm
Revision as of 15:47, 19 September 2017 by CJJongenelen (Talk | contribs)

Jump to: navigation, search

Contents

Abstract

The Stage-Gate Process (also referred to as Phase-Gate Process) is a project management tool, dividing the time horizon of a project into several information-gathering stages. These stages are separated by so-called gates, which represent go/kill/recycle decisions for the project. The concept was introduced by Cooper (1986) in his book 'Winning At New Products'[1].

The central background of the Stage-Gate Process is rooted in the fact that companies have limited resources (e.g. time, money & capital goods). To make effective use of the available resources and to manage risks, a firm has to develop its project portfolio in a manner that only the most promising/beneficial projects are put through. Regular Stage-Gate Processes include 4 to 8 stages, which can be conducted in parallel or can be skipped depending on the preferences of the company [2][3]. The evaluation criteria at each gate are discussed upfront with the project group and are acted upon by the gatekeeper during a gate meeting. Each gate decision should be a objective process; anybody in the organization should come to the same conclusion.

A Stage-Gate Process is complementary to project evaluation methods that, for example, analyze resource availability, project-related risks or costs and benefits of the project. The method is also frequently used in combination with other project management tools, like Gantt Charts or Concurrent Engineering theory [4] The process can be used in most project-related contexts, but gained a lot attention in the field of new product development as a strategic pacing method [5]

Basic Elements of the Stage-Gate Process

The basic idea of a Stage-Gate Process is that the whole project is divided in a predetermined set of stages. These stages consist of groups of related activities that end in so-called gates. Gates are characterized as containing a set of deliverables or inputs, a set of criteria, and an output [6].


Stages

Stages often consist of activities that roughly follow the same trajectory, where first the data is collected, integrated and analysed[3].

Cooper (2008) mentions several key characteristics that need to be taken into account when identifying stages[7]:

1. Each stage should strive to reduce key project uncertainties and risks. For the stage information requirements guide the team in their way-of-working.

2. Each stage is more costly than the preceding one, but risks and uncertainties are lower.

3. Activities within stages are undertaken in parallel and by a team of people from different backgrounds

4. Each stage is cross-functional; so no departmental focuses are present


Gates

Where stages represent a longer period of time (weeks or months); gates represent meetings with a time-span of several hours. At each gate the following elements are relevant to keep in mind [6]:

Inputs: the deliverables that the project leader must bring to the gate

Criteria: which are the items upon the input will be judged.

Outputs: the decisions at the gate, and possible the approval of an action plan for the next stage

Senior managers man the gates, and act as so-called gatekeepers. This group is diverse in nature and each member has the power to approve the resources needed for continuation of the project [6].

During the gate meeting the gatekeepers meet to discuss if a project:

1. Should be terminated (Kill) 2. Should proceed (Go) 3. Should be started over in a new format (Recycle).

This objective decision is fully based at the ability of the team to meet the gate criteria.

Application areas for the Stage-Gate Process

Possible theoretical synergies

Limitations of Using the Stage-Gate Process

References

  1. Cooper, R.G. (1986). Winning At New Products. Addison-Wesley, ISBN 0201136651
  2. O'Connor, P. (1994). From Experience; Implementing Stage-Gate Process: A Multi-Company Perspective. Journal of Product innovation Management. Vol 11. pp 183-200
  3. 3.0 3.1 Cooper, R.G. (2008). Perspective: The Stage-Gate Idea-to-Launch Process — Update What’s New, and NexGen Systems, Product Development & Management Association, Journal of Product Innovation Management. Vol. 25. pp 213–232
  4. Thamhain, H. (1996). Applying stage-gate processes in concurrent engineering. Wescon/96. pp 2-7
  5. Sharma, A. (1999). Central Dilemmas In Managing Innovation in Large Firms. California Management Review. Vol 41. No 3. pp 146-164
  6. 6.0 6.1 6.2 Cooper, R.G. (1990). Stage-Gate Systems: A New Tool for Managing New Products. Business Horizons. pp 44-54
  7. Cooper, R.G. (2008b). Perspective: The Stage-Gate Idea-to-Launch Process — Update What’s New, and NexGen Systems, Product Development & Management Association, Journal of Product Innovation Management. Vol. 25. pp 215