Application of Balanced Scorecard in Portfolio Management
Contents |
Abstract
In this article, the application of Balanced Scorecard (BSC) will be investigated in relation to Project Portfolio Management (PPM). BSC is a strategic planning tool, which addresses the strategic objectives and often measures them in form of Key Performance Indicators which is evaluated, reported and incorporated into a strategic feedback-loop[1]. Each executed project within a portfolio should be aligned with the strategic objectives of the organization. To ensure the linkage between each project and the strategic objectives, a strategic balanced scorecard can be applied and provide the PPM with a set of initiatives and measures, which would indicate if the outcomes from a given project provides the expected returns or growth to the portfolio and organization.[2][3][4]
To facilitate the merger between strategic management and portfolio management this article will present an argumentation of why BSC benefits PPM, including a definition of both PPM and BSC, the direct linkages in between and reasoning for application based on theory. This will be followed by a step by step guidance on the implementation of BSC in PPM and how it should be initiated. Also, the limitations and risks derived from the implementation of BSC will be identified and elaborated, these will shortly be discussed. To inspire further reading an annotated bibliography will be conducted, to enhance the understanding of the tool and core literature.
Definitions
In this section, all theories and definitions will be outlined and discussed. The purpose is to give the reader an enhanced understanding of the BSC and the linkage to PPM.
Balanced Scorecard
BSC is a framework and tool which enable the opportunity for a company to describe its intangible and tangible assets. It does not try to valuate the intangible assets but to provide measures to evaluate these. [1] Furthermore, BSC differentiate from traditional balance sheets[5], through its description of intangible assets and not only tangible assets, such as materials, lands, equipment etc.[1]
The definition of BSC by Kaplan and Norton (2001) together with the definition by Abernethy et al. (2005) used as the baseline of reasoning to application into PPM:
- "The Balanced Scorecard describes how intangible assets get mobilized and combined with intangible and tangible assets to create differentiating customer-value propositions and superior financial outcomes."[1]
- "...it [balanced score card] articulates the links between leading inputs (human and physical), processes, and lagging outcomes and focuses on the importance of managing these components to achieve the organization's strategic priorities" [6]
Strategy Maps
In the article by Tharp (2007), she addresses some of the current weaknesses which is identified in the executive management. One of the major weaknesses she identifies is: "Many companies fail to distinguish between operational effectiveness and strategy."[2] This distinction is very important to ensure a future perspective and to achieve an excellent, effective and efficient operational culture. [4]
In relation to BSC, it is very important that the strategy defined by the executive management is perceived and translated into operational targets and measures. [2] [4] Also BSC is an excellent framework to realize this and closing the gap that often exists. BSC contains both a high-level strategic view and works as an enabler to translate the strategy into measures and targets, which directly relates to PPM and initiatives [4]
A highly recommended approach to ensure that the strategy is sufficiently developed and transparent is to apply the framework of the "Strategy Maps". Strategy maps are a logical and comprehensive architecture to describe the strategy, through all its elements and linkages to the organizational strategy. [1][4] An example of the framework can be seen in Figure 1. The strategy maps in interplay with the BSC provide a common and understandable reference point of the strategy for all organizational units and employees. [1] Which will help to minimize the "Vision Barrier" which result in 95% of the workforce not understanding the strategy and their contribution to it, resulting in ineffective and inefficient project management across the entire portfolio. [7]
With a well defined and transparent strategy, the PPM will be able to define actions to accomplish the strategy and objective goals, while managing all programmes and projects, which will result in an increase in value creation and production capabilities. [8]
The Four Perspectives
Both the BSC and the strategy maps framework is based on the four perspectives in which strategic objectives can be organized. [1][2][7]
The Financial Perspective concern the aspects of the strategy which directly impact the shareholder value.[1][2] Its a critical perspective in business which operate to increase value and generate value to the shareholders. Also, it measures the very bottom-line of the company. [7] It is an easy perspective to measure, but the perspective is very limited, in the horizon and is only able to look backward and therefore is more likely to determine short term strategic decisions. [2] In relation to PPM, measures in this perspective could be profitability, growth, shareholder value, and budgets. [2]
The Customer Perspective address the very core of any business strategy which is the customer value proposition. It differentiates a company from its competitors in attracting, retaining and deepening customer relationship.[1][7] Many of the market leaders have only chosen one discipline and excels within it, the disciplines are: Operational excellence, Product leadership and Customer intimacy. [7] Lastly, it's important, that this perspective does not solely consists of customer surveys, but should include measurable like response time, customer acquisition and customer loyalty.[2][7]
The Internal Process Perspective address organizational and operational measures in which a company when excels is providing good financial performance and excellent value proposition to reach the customers.[1][7] It consist of four high-level processes: 1. build the franchise, 2. Increase customer value, 3. achieve operational excellence and 4. Become a good cooperate citizen. [1] Measures in this perspective when considering PPM could include operational availability, reliability and post-sale processes.[2]
The very last perspective is the Learning and Growth Perspective, this perspective is the enabler of the three previous. It is the foundation for the BSC since it concerns the employees and informative systems, which let you reach ambitious results and achieve a leading market position. During the identification of the other measures, it is almost certain that significant gaps will be identified during the development of this perspective, these would likely concern the human, informational and organizational capitals. Measures in relation to PPM could be planning accuracy, employee development and availability of information.[2][7] When this as the last perspective has been developed, then the strategy map is complete across all four perspectives of the strategy.[1]
Key Performance Indicator Balanced Scorecard
In relation to BSC, Kaplan and Norton (2001) have identified, during 200 consultancy projects, two main types of BSC. The first one is the Key Performance Indicator BSC (KPI-BSC) and the second is the Stakeholder BSC (S-BSC). In this section, the KPI-BSC will be discussed, while the S-BSC will follow in the next section.[1]
KPI-BSC is one of the major BSC types. KPI-BSC is typically straight forward to implement since it is often based on already existing KPIs within the organization. The identified KPIs need to be classified into the four above stated perspectives to ensure that they address the entire project portfolio and all the aspects. It is important that the KPI-BSC do reflect the entire strategy of the organization and not only parts, which is often the case. By looking solely at the KPI-BSC a person should be able to tell what the organizational strategy is since it should be based upon that. Also, the linkages between a specific KPI and its contribution to strategic objectives should be clarified and have a common acceptance. [1]
Stakeholder Balanced Scorecard
The second main type of BSC is S-BSC. In this type, the organization identifies all its stakeholders, including shareholders, employees, customer, suppliers and their point of contact with the community in which they engage. Then the organization develop goals for all these stakeholders and follow this by a set of measures and indicators. The S-BSC described, is not fulfilling the definition of the BSC, but by adjusting measures and indicators to also concern the aspect about how the organization is going to achieve this, while concerning the overall organizational strategy and their internal processes, then the S-BSC would be sufficient in the definition of a BSC.[1]
Either of the KPI-BSC nor the S-BSC is sufficient on their own, but in either cooperation or an inspired conceptualization based on the four perspectives, both can fulfill the definition of a BSC. Each PPM is different and the design of the BSC framework should carefully be considered and changed to match the strategy of the organization.
Project Portfolio Management
The PPM definition in this article follow the standards of PPM from the Project Management Institute (PPM-Standard):
- "Portfolio management is the centralized management of one or more portfolios to achieve strategic objectives. It is the application of portfolio management principles to align the portfolio and its components with the organizational strategy. Portfolio management can also be viewed as a dynamic activity through which an organization invests its resources to achieve its strategic objectives by identifying, categorizing, monitoring, evaluating, integrating, selecting, prioritizing, optimizing, balancing, authorizing, transitioning, controlling, and terminating portfolio components."[9]
Linkage between BSC and Project Portfolio Management
When considering PPM one of the critical actions or features is to carefully monitor, evaluate, controlling, balancing and optimizing portfolio components.[9] A framework which supports these portfolio components is the BSC. BSC give a structure, a strategy map and measures to manage, which when performed correctly will help to achieve an excellent PPM performance within the highlighted components.
Furthermore, the PPM-Standard also emphasize the importance of a direct link between the PPM and the organizational strategic objectives.
- "A portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. The portfolio components, such as programs and projects within the portfolio, are quantifiable. ...At any given time, a portfolio represents a collection of its selected portfolio components and reflects one or more organizational strategies and objectives for that point in time. Therefore, a functioning portfolio should be a representation of an organization’s intent, direction, and progress at any given moment."[9]
This facilitation can BSC ensure if properly designed and modified to the given organization.[7] Also see Figure 2, for visualization of the linkage in between BSC, appurtenant Strategy Map, and PPM.
Identification of Need
It's not all organizations which need to implement the BSC. It is very important to underline, that it takes a lot of work to initiate and implement. Therefore, organizations which already has an excellent performance measurement discipline, should not use the resources to implement the BSC, due to small return on investment if any.[7]
To identify if an organization could benefit from the implementation of a BSC system a questionnaire has been conducted as a subjective assessment tool for implementation of BSC. When answering the assessment you assign each statement a score from 1 to 5. The more you agree the higher a score you should assign to the statement. It is important to emphasize that the assessment is mostly aimed at an entire organization and that each project portfolio manager, program manager, and project manager should answer this short questionnaire to see if the current performance measurement system need to be reviewed or a new one should be implemented.
No. | Statement | Score (1-5) |
---|---|---|
1 | In our organization, we have invested in Total Quality Management (TQM) and other improvement initiatives, but we have not seen a corresponding increase in financial or customer results. | |
2 | If we did not produce our current performance reports for a month nobody would notice. | |
3 | We create significant value from intangible assets such as employee knowledge and innovation, customer relationships, and a strong culture. | |
4 | We have a strategy (or have had strategies in the past) but have a hard time implementing them successfully. | |
5 | We rarely review our performance measures and make suggestions for new and innovative indicators. | |
6 | Our senior management team spends the majority of its time together discussing variances from plan and other operational issues. | |
7 | Budgeting at in our organization is political and based largely on historical trends. | |
8 | Our employees do not have a solid understanding of our mission, vision, and strategy. | |
9 | Our employees do not know how their day-to-day actions contribute to the organizational strategic objectives. | |
10 | Nobody owns the performance measurement process at our project portfolio. | |
11 | We have numerous initiatives taking place at our organization, and it’s possible that not all are truly strategic in nature. | |
12 | There is little accountability in our project portfolio/program for the things we agree as a group to do. | |
13 | The information and communication flow between projects and programs is not clarified, and as a result, we have little collaboration among projects and programs. | |
14 | Our employees have difficulty accessing the critical information they need to perform their tasks or solve problems. | |
15 | Priorities in our programs and project portfolios are often dictated by current necessity or “firefighting”. | |
16 | The environment in which we operate is changing, and in order to succeed we too must change. | |
17 | We face increased pressure from stakeholders to demonstrate results. | |
18 | We do not have clearly defined performance targets for both financial and non-financial indicators. | |
19 | We cannot clearly articulate our strategy in a one-page document or “map”. | |
20 | We sometimes make decisions that are beneficial in the short term but may harm long-term value creation. | |
- | Total sum of all the scores |
Based on the averaged scores of the questionnaire following recommendations is given:
Score range | Recommendation |
---|---|
0-30 | If your score fell in this range you most likely have a strong performance measurement discipline in place. The program has been cascaded throughout your organization to ensure all employees are contributing to your success and is linked to key management processes. |
31-60 | You may have a performance measurement system in place but are not experiencing the benefits you anticipated or need to succeed. Using the Balanced Scorecard as a strategic management system would be of benefit to you. |
61-100 | Scores in this range suggest difficulty in executing your strategy successfully and meeting the needs of your customers and other stakeholders. A Balanced Scorecard system is strongly recommended to help you focus on the implementation of the strategy and align your project portfolios in your organization with overall strategic goals. |
This assessment is inspired by Niven (2002) and adapted to PPM, Source: Niven, P.R. (2002) Balanced Scorecard Step-by-Step New York, NY: John Wiley & Sons
Implementation
This chapter will propose a framework on how to apply BSC in a project portfolio. It is mainly based on chapter 2 in the book from Niven (2002)[7], the article Hoffman (2004)[10] and the Implementation guide provided by Tharp (2007)[2].
It is important to emphasize that the outcome from the implementation of a strategic BSC into project portfolio management is mainly providing linkage and a feedback system in relation to strategic objectives and project performance. As Hoffman (2004) quotes:
- "The tool establishes a limited set of key measures... channeled through a continuous feedback process toward strategic goals."[10]
Before initiating the implementation project (IP) responsible should carefully consider and plan the following four topics:
Guidance Rationale It is almost a necessity to ensure the guiding rationale behind the IP of BSC. It is important that the guiding rationale explains why the decisions have been made and what benefits it will provide, it should be very specific. From time to time the IP will lose momentum and in these situations, a guiding rationale will provide the IP team with reasoning and an objective of the IP. Also, the guiding rationale is an excellent tool to communicate with all employees about the goals of the implementation of BSC into the project portfolio.[7]
Executive Sponsorship One of the most important topics to have covered before launching the IP is to have sufficient executive commitment. Many IP of BSC fails due to a lack of executive attention[1][7]. The senior management has several qualities which are a necessity to implement a good BSC into a project portfolio. The first is knowledge and understanding of the strategy in the company. The senior management has an in-depth knowledge of the strategy and has the abilities to articulate this in the given project portfolio. Also, senior management has the decision-making power to take relevant decisions during the IP in relation to strategic goals and objectives. The last quality that senior management provides the IP is the commitment. Programmes and project, which have the emotional commitment from senior management are more successful than projects without[7].
Implementation Project Team The IP Team is crucial and an IP can hardly be successful if only driven by one person, since one person doesn't have all the knowledge needed. It should mainly be the executive sponsor, which ensures and allocate sufficient resources, both human and financial resources. It is very important that the person which is selected to be in the IP Team can see the opportunities and value during the changes necessary to implement the BSC in the project portfolio. One of the members should be chosen as the IP Manager and together with the executive sponsor will drive the project.
Implementation Plan When implementing the BSC the IP team needs to have a roadmap of where and when the BSC should be implemented. Therefore, an project portfolio, programme or project should be chosen. A good first candidate would be one of the project portfolios, programmes or projects which had a high score in the assessment conducted in the Identification of Need chapter. The higher score has a more urgent need for implementation of a BSC. The IP team can beneficially follow the scoring from the assessment from high to low when implementing BSC into the project portfolio.
Step Framework
When the planning phase has been carried out carefully, then the IP can be initiated. Since every project portfolio is different, generic implementation guidance cannot be provided. But in this article, a set of steps have been proposed, but they should be adjusted and modified to fit the given case in the project portfolio. The Step Framework proposed in this article follows the structure of Hoffman (2004) [10] but is further developed based on the implementation framework provided by both Niven (2002) [7] and Tharp (2007)[2]. The Step Framework consists of six steps:
1. Background Material
The first step to do, as the IP Team, is to collect and gather all sufficient background material on what the companies vision, mission, values, and strategy is and how its objectives relate to the project portfolio. Material for this can be earlier press releases, analyst reports, and annual reports.
2. Education and Strategy Map Development
This Step consists of two actions, which favorably could be facilitated through one or several workshops with relevant participants.
- The first action would be to educate senior management, this would be to gap any holes that exist in the reasoning of the IP of BSC into the project portfolio. A good approach would be to use the Guidance Rationale developed in the planning phase together with the Implementation Plan. This would allow you to communicate why this is highly relevant and how it should be done.
- The second action would be to conduct a Strategy Map. This need to be based on the first step as well as the first action in the second step. It should be developed either based on executives interviews or/and within a workshop with the IP Team and the executives. This action is absolutely critical in the success of the IP.
3. Develop Performance Measures and Linkage to the Strategy Map
After the Strategy Map have been conducted, then each objective in the map should be translated into corresponding performance measures, which would give insight into how each project, programme or project portfolio meet and develop towards the strategy. By doing this the linkage between each measure and the executed strategy will be easy to track.
4. Establish Targets and Prioritize
In this step, each performance measure will be provided with 'flesh' in form of identification and definition of relevant targets and initiatives to support each measure. As Niven (2002)[7] says:
- "...setting targets may be among the most challenging aspects of your entire implementation. Many organizations have little actual practice in or techniques for establishing meaningful performance targets."
5. Conduct the First Balanced Scorecard Report
Now when the BSC starts to take form, then it is important to conduct a very first report as fast as possible. This still takes a long time and much of the data and information needed in many of the performance measures are not available or ready yet. This should not comprehend the IP Team for conducting one. Its purpose is to provide stakeholders with a physical or visual product of the IP and to receive feedback on the process until now. Since there is a high chance that a lot of data is missing, then the IP Team should focus on the alignment to strategy, finalized measures and their targets, and also the established feedback process.
6. Future Development and Review Setup
The very last step of IP is to hand over the project with a development plan for future purpose. It is also very important that the feedback loop is closed which can be done by performance review meetings, monthly reports and/or dashboards. Without a good handover or closure of the feedback loop, then the IP will hardly be a success. These actions will ensure a continues learning process in regard to project portfolio performance in relation to strategic objectives.
Limitations and Risks
In this chapter limitations of BSC in PPM will be discussed. The discussion will be based on three articles. The first is by Rillo (2004)[11]. The second is by Voelpel, Leibold, and Eckhoff (2006)[12], and the last is by Nørreklit (2000)[13].
Rillo (2004)[11] do identify several limitations. One of them is that the top-down approach in the implementation of BSC in PPM is based on a result-driven centralized project portfolio. Thereby, it is not based on the internal needs of the employees. This might rise motivation problems, during to the neglect of the employee's abilities to contribute to the development of performance measures. Another major limitation which Rillo (2004) identifies is the assumption which the BSC is based and build upon. Which is large companies in stable situations, and therefore is able to allocate sufficient resources and time during both the preparation of the implementation, but also during the implementation. It is also stated that even re-engineering the BSC is not always sufficient to deliver reasonable results from the implementation. Lastly, he points at the focus on lagging and not so much on leading indicators in the very first article defining the BSC by Kaplan and Norton (1992)[14]
In the article by Voelpel, Leibold, and Eckhoff (2006)[12] they mainly discuss limitations of BSC in innovative economic systems. One of the significant limitations of BSC is its poor ability to cope with a rapidly changing and networked environment. This leads to an endangering of the firm's survival in such an environment. The first limitation is nested in the definition of the BSC as a measurement tool, which is rigid and not that flexible. Performance measures are mainly based on the four perspectives and this often limits the firms perspective and innovative capabilities. Also, this happens to limit the manager's view of the business, where they are not able to identify the changing in nature of the external environment. Another limitation emerges from the optimal implementation of BSC, which results in a high level of uniformity and a result orientated organization. This limits any initiatives which would go beyond the goals and targets, and the firm risks to miss business opportunities. Furthermore, the article identifies a limitation in the way that BSC handles and sees knowledge creation and learning loops. BSC is based on the classical R&D approach, where most of the innovations today is emerging in open networks. As they state:
- "Innovation, a key factor to intellectual capital, is viewed by the BSC as an internal business process and categorized under this perspective; it appears to be a routine process rather than a creative endeavor by skilled employees throughout the company."
In the last article by Nørreklit (2000)[13] she among others identifies three limitations or misunderstandings in the BSC framework. These are limitations are very severe and should be carefully considered before implementation of BSC. The first is how BSC is based on invalid assumptions. One of these invalid assumptions is that customer satisfaction yield good financial results, which not necessary is true. Secondly, she criticizes BSC for not ensure any organizational rooting, which she relates to the lack of environmental rooting in the tool/framework. The very last statement from the article is that the firm which implements BSC must expect a difference between the actions or initiatives executed to meet the strategy and then the actual planned strategic objectives.
Discussion
It is important that an organization before initiating the implementation of BSC, do carefully consider all its limitations. Even if the Assessment of Need recommends the organization to implement the BSC, then careful considerations should be made. BSC is an excellent framework to communicate strategic objectives and set up a feedback system which efficient and effective improves the project portfolio performance in a traditional and classic environment, such as construction-, production- and operation project portfolios.
Annotated Bibliography
In the article by Kaplan and Norton, they explain and elaborate on how balanced scorecard can be used for strategic management through the development of a strategy map together with an in-depth explanation of the four scorecard perspectives. Lastly, they modify the balanced scorecard framework to be applicable to NGOs.
- Kaplan, R. S., & Norton, D. P. (2001). Transforming the Balanced Scorecard from Performance Measurement to Strategic Management : Part I, 15(1), 87–104.
In the article by Tharp, she addresses the ability which balanced scorecard possess in translating strategic objectives into measures and targets, which projects and programmes directly can contribute and thereby show the strategical relevance. A simplistic implementation approach is provided.
- Tharp, J. (2007). Align project management with organizational strategy. Paper presented at PMI® Global Congress 2007—Asia Pacific, Hong Kong, People's Republic of China. Newtown Square, PA: Project Management Institute.
In the book written by Niven, an in-depth explanation of the implementation of balanced scorecard is provided, the very first two chapters provide knowledge and an outline of the balanced scorecard implementation, the rest of the chapters give an in-depth explanation of each topic and step in the implementation process in the proposed framework.
- Niven, P.R. (2002) Balanced Scorecard Step-by-Step New York, NY: John Wiley & Sons
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 Kaplan, R. S., & Norton, D. P. (2001). Transforming the Balanced Scorecard from Performance Measurement to Strategic Management: Part I, 15(1), 87–104.
- ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 Tharp, J. (2007). Align project management with organizational strategy. Paper presented at PMI® Global Congress 2007—Asia Pacific, Hong Kong, People's Republic of China. Newtown Square, PA: Project Management Institute.
- ↑ Toledo, R. (2011). Bridging the strategy gap. PM Network, 25(6), 18.
- ↑ 4.0 4.1 4.2 4.3 4.4 Olivier, A. J. (2007). Guideline for traveling [i.e. traveling] from vision to projects and back. Paper presented at PMI® Global Congress 2007—EMEA, Budapest, Hungary. Newtown Square, PA: Project Management Institute.
- ↑ Taggart, R. A. (1977), A MODEL OF CORPORATE FINANCING DECISIONS. The Journal of Finance, 32: 1467-1484. doi:10.1111/j.1540-6261.1977.tb03348.x
- ↑ Abernethy, M.A., Horne, M.H., Lillis, A.M., Malina, M.A., & Selto, F.H. (2005). A multi-method approach to building causal performance maps from expert knowledge, Management Accounting Research, 16(2), 135–155.
- ↑ 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 Niven, P.R. (2002) Balanced Scorecard Step-by-Step New York, NY: John Wiley & Sons
- ↑ 8.0 8.1 Toledo, R. (2011). From the balanced scorecard to the project portfolio. Paper presented at PMI® Global Congress 2011—North America, Dallas, TX. Newtown Square, PA: Project Management Institute.
- ↑ 9.0 9.1 9.2 Project Management Institute. (2018). The standard for portfolio management.
- ↑ 10.0 10.1 10.2 Hoffman, W. (2004). The view from 50,000 feet. PM Network, 18(7), 26–33.
- ↑ 11.0 11.1 Rillo, M. (2004, January). Limitations of balanced scorecard. In Proceedings of the 2nd Scientific and Educational Conference, Business Administration: Business in a Globalizing Economy, Parnu (pp. 30-31).
- ↑ 12.0 12.1 Sven C. Voelpel, Marius Leibold, Robert A. Eckhoff, (2006) "The tyranny of the Balanced Scorecard in the innovation economy", Journal of Intellectual Capital, Vol. 7 Issue: 1, pp.43-60, https://doi.org/10.1108/14691930610639769
- ↑ 13.0 13.1 Nørreklit, H. (2000). The balance on the balanced scorecard - A critical analysis of some of its assumptions. Management Accounting Research, 11(1), 65–88. https://doi.org/10.1006/mare.1999.0121
- ↑ Kaplan, R. S. and Norton, D. P., 1992. The balanced scorecard as a strategic management system, Harvard Business Review, January-February, 61-66.