Program evaluation and review technique (PERT)
The Program Evaluation and Review Technique (PERT) is a method used in project management for planning, scheduling and coordinating the tasks of a project. It is based on a network diagram analysis of the different tasks that are involved. PERT is specifically suited for large, complex and nonrepititive projects, since the network diagram varies in each project.
Contents |
General overview
- General presentation of the method (purpose, history) - How it works more or less - Difference compared to other similar methods (CPM)
Key concepts
- Definition of the key concepts that will be used
- Activities - Events - Network diagram and analysis - Critical Path
PERT has several concepts that need to be defined, to understand the whole method. Those are :
- Activities
- Events
- Network diagrams
- Critical path
A network diagram is a visual representation of a project's schedule. It presents all the information about the project on a time basis like the tasks, their starting/ending times, total duration. Using this kind of representation makes the whole management process much easier and less error-prone (to be checked).
The activities are the tasks that need to be completed. Each task has a predefined duration, a priority, a cost and an amount of workers associated with it. On a network level, they are represented as nodes connected by arrows. They can have predecessors - other tasks that need to be completed before them - and successors - tasks that can start only once this one has finished.
The events are points in time marking a phase of an activity like the start or the completion. Events can relate to one or more activities.
The critical path is the path through the network that includes the most time-consuming sequence of events and activities. Hence it represents also the total time that will be needed to complete the project. Any delay that occurs in one of the activities on this path will affect the completion date.
The process
- Detailed step by step presentation of the method
- building a network diagram - calculation of the times - possible modifications
The process of making a PERT analysis can be divided into 4 steps:
- Preparation of a list of all the tasks that will be involved in a given project
- Creation of a network diagram
- Estimation of the time required to finish each activity
- Calculation of the critical path
- Network analysis
Preparation phase
PERT starts with a standard step of defining the activities that will be involved in the project. This information is presented in a box representation. This box will later be filled with other time informations about the project.
Network diagram
Once the basic information about the activities has been gathered, the activities need to be put in order. The priority of the task and the dependencies between them are taken into consideration. In the network, activities are represented as arrows, whereas the events are the nodes.For instance, the preparation of the base of a building would be decoupled into "starting of preparation" and "end of preparations".
Estimation of the time
In this step we estimate the amount of time that can be taken by each activity. This time can be determined using a probabilistic or a deterministic approach. Three times need to be defined :
- the optimistic time (short time)
- the pessimistic time (shortest time)
- the normal time (most likely time)
The optimistic time is the shortest time an activity will take if everything goes right. In general, it is highly improbable that the project will finish in this time, due to all the other factors.
The pessimistic time is the longest time that an activity will take. During the calculations, several scenarios need to be considered with their respective probability in order to have a quite precise value.
The normal time is the most likely time of an activity. Usually, it is determined using the time other similar activities took in other projects. For instance, the time needed to build a cockpit for one aircraft might be based on the average time it took to build cockpits for comparable aircraft in the past.
Critical path estimation
Now that we have all the time uyt`
Applications and limitations
- Where is the method most useful and why - Why it cannot be used in other areas or is less efficient - Possible future ?