Parkinson's Law in Project Management
Parkinson's Law states that work expands to fill the time available for its completion.[1] It was formulated by British historian and author Cyril Northcote Parkinson in an essay for The Economist in 1955.[2]
Originally, Parkinson's Law described how a bureaucracy can grow unrelated to its actual workload because people make work for each other by complicating work. The growth of bureaucracy depends on two factors: (1) The Law of Multiplication of Subordinates and (2) The Law of Multiplication of Work. From statistical analyses, Parkinson determined the increase in staff per year to be around 5-7% independent of its workload. Based on this, he formulated a mathematical formula to determine the annual increase in staff in any public administrative department.[1]
The tendency in work behaviour Parkinson's Law describes, is one of the reasons why projects are delayed. Parkinson’s Law explains the behavioural aspect of scheduling. According to Parkinson's Law, a person will spent all the available time to complete a task regardless of the tasks size. This results in inefficient use of time and effort. Project managers can use this to understand employees motivation for completing tasks. In project schedule management, this is valuable knowledge when estimating activity duration. The project manager should account for this tendency when scheduling to enhance productivity. [3]
This article highlights areas in project management where techniques and tools are affected by Parkinson's Law. Tools to minimise the implications of Parkinson's Law are suggested and reflected upon.
Parkinson's Law is difficult to manage. It depends on how good the scheduling is, which also depends on how good resources are allocated and then there are risks, which makes scheduling uncertain at times.
Contents |
Theory
In Parkinson’s essay from 1955, the law refers to the relationship between the bureaucracy and its workload. The law describes how people make work for each other by complicating the work. Therefore, a bureaucracy can grow unrelated to its actual workload. The growth depends on two factors: (1) The Law of Multiplication of Subordinates and (2) The Law of Multiplication of Work. The Law of Multiplication of Subordinates states an overworked person, seeking promotion, in an organisation has incentives to multiply subordinates instead of creating rivals by sharing their work. The Law of Multiplication of Work states that people will make work for each other by complicating it so everyone is occupied. This gives the impression that the staff is overworked and missing resources. Therefore, more staff is hired.
Parkinson uses the bureaucracy of the British Civil Service as an example of Parkinson’s Law. He supports his statements with statistical analyses showing that the number of ships and men in the royal navy fell between 1914 and 1928, while the number of employees in administration rose. With these analyses, he determined the rate of staff per year to be around 5-7% independent of the amount of work. He formulated the following mathematical formula to determine the annual increase in staff in any public administrative department:[1]
x = (2k^m+p)/n
- k = number of staff with incentives multiply subordinates
- p = the difference between the ages of appointment and retirement
- m = number of hours devoted to answering minutes within the department
- n = number of effective units being administered
- x = number of new staff each year[1]
The definition of Parkinson’s Law as known today is the first sentence of the essay (Parkinson, 1955), "It is a commonplace observation that work expands so as to fill the time available for its completion." Parkinson describes how work is elastic in its demands on time. Work becomes more complex as to fill the time before completion. Parkinson uses the example of an elderly lady spending a whole day writing and sending a postcard. A busy man could do it in three minutes, yet the lady spends the day worrying and stressing over sending the postcard.
In project management, this is the definition applied. Parkinson’s Law describes the tendency that people will spent all of the allocated time to complete a task regardless of the time it actually takes to complete it. Likewise, a person will not complete a task before a deadline, resulting in inefficient use of resources and time (ref). For instance, a person has one week to complete a task that takes 8 hours, but instead of completing it on the first day using all of their effort, the person will use less effort and spent a week.
Affected Areas
The behaviour associated with Parkinson’s Law has a big influence on project performance. [4] Along with student syndrome, it is one of the main reasons why deadlines are not met.
Within project scheduling, it is important a project manager is aware of it. According to Parkinson's Law, it is assumed that a task either is completed on time or is delayed. The task is not completed before time. To achieve the most efficient use of resources and time, the time allocated for each task needs to correspond with the time it actually takes to complete it. If the allocated time is too short the task is delayed and if the allocated time is too long unnecessary time is spent on the task. However, it is difficult to accurately estimate the time needed as it depends on a number of factors, such as the estimators knowledge about task, the competencies of the person allocated to the task, and available resources.
Besides scheduling, risk management and decision-making are also affected by Parkinson's Law.
Scheduling
In project scheduling, the objective is to make a detailed plan of activity durations and dates to ensure timely completion of a project. The plan is continuously monitored and controlled and used as a tool for communication and managing stakeholder's expectations.[3] In terms of Parkinson's Law in scheduling, the concern is whether time and resources are used efficiently. Parkinson's Law can affect several aspects of scheduling and result in inefficiency if not properly managed. It is important project managers are aware of the behaviour caused by Parkinson's Law and how they can minimise it with scheduling. Clearly, the quality of the schedule also depends on other factors such as how many resources are available and how they are allocated. However, in the following section the focal point is purely project schedule management. According to the PMI standard 'Guide to the Project Management Body of Knowledge (PMBOK® Guide)' (2017), project schedule management consists of six processes to properly manage the completion of a project. The processes are: (1) Plan Schedule Management, (2) Define Activities, (3) Sequence Activities, (4) Estimate Activity Durations, (5) Develop Schedule, and (6) Control Schedule.
Some of the tools used to schedule and ensure resources are used efficiently could actually be subject to parkinson's law if not porperly managed. Some of these tools are highlighed here
scheduling techniques and tools from the PMI standard 'Guide to the Project Management Body of Knowledge (PMBOK® Guide)' (2017), are discussed in relation to Parkinson's Law. Project schedule management consists of six processes to properly manage the completion of a project. The processes are: (1) Plan Schedule Management, (2) Define Activities, (3) Sequence Activities, (4) Estimate Activity Durations, (5) Develop Schedule, and (6) Control Schedule. Inherently, all processes are important to managed to ensure a good scheduling plan. and achedlung also depends on the resources avaiable and how good they are allocated.
- Three-point estimating is used to determine the duration of an activity in the fourth process, estimate activity durations. Unlike techniques with the same purpose, three-point estimating considers estimation uncertainty and risk and estimates three durations: The most likely, the optimistic, and the pessimistic. While the three-point estimate clarifies the range of uncertainty, suggesting three durations allows for Parkinson’s Law. If the pessimistic estimate is the longest allowed time while meeting the project completion, people will assume they have more time.[3]
- Likewise, reserve analysis also allows for Parkinson’s Law. Contingency reserves are necessary to have when dealing with uncertainty, but following Parkinson’s Law, people will assume they have more time without delaying the project. When dealing with Parkinson’s Law, it is important to set realistic, but tight deadlines. If too much contingency reserve is allowed, people will consume it.[3]
- Critical path method (CPM) is one of the techniques used to schedule in the fifth process, develop schedule. This process consists of creating a schedule model based on the estimated durations and resources. The critical path method is used to identify the shortest time to complete a project. The schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations. CPM helps the project manager determine if a schedule is on the critical path. However, if not properly managed according to Parkinson’s Law, people will start an activity on its late start date, consuming all float and turning all paths critical.[3][5][6]
- Parallels can be drawn between the observations Parkinson describes in his essay and ‘The Mythical Man-Month’ (1975) by Frederick Brooks. Brooks' Law states that ‘adding people to a late software project makes it later’. This statement is based on Brook’s own experiences at IBM. When a project is behind schedule, the project is crashed. More resources are added to shorten the time to completion. However, by adding more people, bureaucracy and training increased. Instead of being more effective, the project is delayed further.[7][3]
- Crashing is a common technique and may be the solution to a project delayed by the implications of Parkinson's Law. However, crashing can have the opposite effect and delay the project further.
law corresponds well with Parkinson’s, people make work for each other. Regardless of the number of people, the workload stays the same. People will make work for each other so everyone is occupied. Work is overcomplicated as to occupy everyone, as Parkinson describes with the law of multiplication of work.
Crashing can be subject to Parkinson’s Law. People will make work for each other while the workload stays the same. By overcomplicating the work, time and resources are wasted.
Multitasking
Cost and Resource Management
DRAFT: Parkinson's Law takes time and resources, which otherwise could be saved. This leads to extra costs. By eliminating parkinson's in scheduling, costs and resources can be saved and spent somewhere else. find PL theory on costs
people feel stressed and assume they need more help. acquire more resources. Caused by PL. look into what happens if people think resources - standard
Risk Management
risk management is about planning for risk and uncertainty. Some of the ways to do this is by using safety buffers, which goes against PL. The use of buffers to account for risk and uncertainties. The more complicated work gets, more risks may appear. higher risks
Decision-making
Studies have shown that the size of a cabinet is negatively correlated with government effectiveness. In large groups, smaller groups begin to form and block each other, which is why decision-making is difficult to manage in large groups.[8]
Suggestions to minimise the implications of Parkinson’s Law
Incencitives to Encourage Early Finish
Risk Management
Monitoring and Controlling
This is important to handle parkinson's law
Annotated bibliography
References
- ↑ 1.0 1.1 1.2 1.3 Parkinson, C. Northcote (November 19, 1955) "Parkinson’s Law", The Economist. Retrieved 13 February 2021.
- ↑ Editors of Encyclopaedia Britannica "C. Northcote Parkinson", Britannica. Retrieved 13 February 2021.
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 Project Management Institute, Inc. (September 22, 2017). "Chapter 6: Project Schedule Management". Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute, Inc. (PMI). pp. 173–230. ISBN 978-1-5231-1232-6.
- ↑ Chen, B.; Hall, N. G. (June 12, 2020). "Incentive schemes for resolving Parkinson’s Law in project management". European Journal of Operational Research 288. pp. 666–682.
- ↑ Cite error: Invalid
<ref>
tag; no text was provided for refs namedpractice
- ↑ Kinser, J. (2008). "The top 10 laws of project management". Paper presented at PMI® Global Congress 2008—North America, Denver, CO. Newtown Square, PA: Project Management Institute. Retrieved 21 February 2021.
- ↑ Roth, D. (December 12, 2009) "QUOTED OFTEN, FOLLOWED RARELY", CNN. Retrieved 21 February 2021.
- ↑ Wen, T. (May 22, 2020). "The ‘law’ that explains why you can't get anything done", BBC. Retrieved 21 February 2021.