Critical Chain Project Management to cope with uncertainty

From apppm
(Difference between revisions)
Jump to: navigation, search
(Theory of Constraints)
Line 16: Line 16:
  
 
Since CCPM applies TOC’s concepts to project management, it is useful to understand the reasoning behind the theory.
 
Since CCPM applies TOC’s concepts to project management, it is useful to understand the reasoning behind the theory.
 +
 
TOC is a systems-management philosophy, originally applied to production system, based on the principle that any system must have a constraint that limits its output. If there were no constraints, system output would either rise indefinitely or would fall to zero. Therefore, a constraint( or bottleneck) limits any system with a nonzero output<ref> Lawrence P. Leach, 2005, "Critical chain Project Management," 2ed,  Artech House, ISBN 1-58053-903-3
 
TOC is a systems-management philosophy, originally applied to production system, based on the principle that any system must have a constraint that limits its output. If there were no constraints, system output would either rise indefinitely or would fall to zero. Therefore, a constraint( or bottleneck) limits any system with a nonzero output<ref> Lawrence P. Leach, 2005, "Critical chain Project Management," 2ed,  Artech House, ISBN 1-58053-903-3
 
</ref>.  
 
</ref>.  
 +
A system’s constraint may be physical (e.g. materials, machines, people, demand level) or managerial<ref> Rahman S., (1998), "Theory of Constraints: A review of the philosophy and its applications", International Journal of Operations and Production Management. 18(4), pp. 336-355) which hinder the system to achieve better performance.
  
 
=== TOC applied to Project Management ===
 
=== TOC applied to Project Management ===
 +
 
== Undesired effects of traditional approaches ==
 
== Undesired effects of traditional approaches ==
 
== Critical Chain Method ==
 
== Critical Chain Method ==

Revision as of 21:46, 21 September 2015

Critical Chain Project Management(CCPM) is an approach for managing project, initially developed by M. Goldratt and based on the Theory of Constraints(TOC) applied to project management. It has adquired increased importance since it has been proved to be an effective method to ensure project completed on time, reduction of project completition time, and increased resource productivity. The basics principle are: avoiding multi-tasking, focus on the critical chain tasks, aggregate all safety time to handle uncertainty

This article illustrates the theory behind the method, its application, [a comparison with the critical path method], and its limitation.

Critical Chain Project Management(CCPM) is a method to plan, execute, manage, and control both single and multi projects, which emphasizes the effects of resource allocation and activity duration uncertainty. CCPM is an outgrowth of the Theory of Constraints(TOC) and was introduced in 1997 in Eliyahu M. Goldratt’s book, “Critical Chain”[1] in response to many projects resulted in larger duration, increased cost, and less derivable than expected.

The Critical Chain method mainly differs from the traditional methodology, deriving from Critical Path, in how uncertainty is handled.


Theory of Constraints

Since CCPM applies TOC’s concepts to project management, it is useful to understand the reasoning behind the theory.

TOC is a systems-management philosophy, originally applied to production system, based on the principle that any system must have a constraint that limits its output. If there were no constraints, system output would either rise indefinitely or would fall to zero. Therefore, a constraint( or bottleneck) limits any system with a nonzero output[2]. A system’s constraint may be physical (e.g. materials, machines, people, demand level) or managerial[3]


Cite error: <ref> tags exist, but no <references/> tag was found
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox