Earned Value Analysis : A tool for decision-making

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 33: Line 33:
  
  
== Earned Value (EV) ==
+
=== Planned Value (PV) ===
 +
 
 +
=== Earned Value (EV) ===
 +
 
 +
=== Cost Variance (CV) ===
 +
 
 +
=== Cost Performance Index ===
 +
 
 +
=== Budgeted Cost of Work Scheduled (BCWS) ===
 +
 
 +
=== Budgeted Cost of Work Performed (BCWP) ===
 +
 
 +
=== Actual Cost of Work Performed (ACWP) ===
 +
 
 +
=== Budget at completion (BAC) ===
 +
 
 +
=== Scheduled Variance (SV) ===
 +
 
 +
=== Schedule Performance Index (SPI) ===
 +
 
 +
 
 +
 
  
lololo
 
  
  

Revision as of 16:00, 12 June 2017

ATTENTION : This article is still a work in progress


The Earned Value Analysis (EVA) Is a method used in Project Managment for monitoring the performance and progress of a project through a comparison of the planned project and the actual project. Measurements of the three components of the Project management triangle, Time, Cost & Scope are used as input in the analysis to create an objective estimate of the project's health. The purpose of EVA is to enable to project manager to make informed decisions based on objective results that are directly derived from the project's main performance indicators Time, Cost & Scope.

Contents

History

The Earned Value Analysis, initially named PERT/COST was first used by the US government in the 1960s as the tool was imposed onto the contractors of the US Department Of Defense as a way of standardising the performance tracking of all the departments different projects. PERT/COST generated a large discontent amongst the contractors due to it's inefficiency and was ultimately changed by the US Department Of Defense in the late 1960s. From this a new analysis arose called Cost/Schedule Control Systems Criteria (C/SCSC) which is the criterion based approach that is now used widely through all of project management and known as the Earned Value Analysis (EVA) which further led to the practice of Earned Value Management (EVM)

Overview

EVA is a dynamic project management tool that allows a project manager to measure or forecast the performance of a project at any given time throughout the lifetime of a project. it's use of quantitative performance indicators makes it an objective tool which can be utilised in any scenario. The tool EVA is the fundamental element in the so called Earned Value Management (EVM) which is a management methodology in which a project is administered through decisions based on the results of the EVA. The methodology is widely used in the industry because of it's ability to facilitate informed objective decision-making and it's flexibility stemming from the time related inputs and outputs.

Depending on the size and complexity of the project the EVA might need different features in order to produce an adequate analysis of the project.

To perform a basic Earned Value Analysis the following features are required :

Adequate measurements from the following project indicators must be available.

  • Time
  • Cost
  • Scope

Prerequisites for EVA

  • A project plan, containing all the tasks of the project along with the time schedule (eg. Gantt chart )
  • An estimate of the cost of each task within the project plan also known as "budgeted cost of work scheduled" (BCWS) or "Planned value (PV)
  • An overview of the "Budgeted Cost Of Work Performed"(BCWP) or "Earned Value" (EV)

Application

When performing an EVA the following terms and definitions must be familiarised.


Planned Value (PV)

Earned Value (EV)

Cost Variance (CV)

Cost Performance Index

Budgeted Cost of Work Scheduled (BCWS)

Budgeted Cost of Work Performed (BCWP)

Actual Cost of Work Performed (ACWP)

Budget at completion (BAC)

Scheduled Variance (SV)

Schedule Performance Index (SPI)

Limitations

See also

References

Further reading


Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox