Earned Value Management (EVM) in construction projects

From apppm
Revision as of 11:37, 15 September 2016 by Thorgeir11 (Talk | contribs)

Jump to: navigation, search

The Us federal government introduced Earned Value management(EVM) in 1967 as a part of the cost/schedule control systems criteria (C/SCSC) Earned Value management is a systematic process that is used to measure the performance of a project at different times throughout the life cycle of a project. EVM is useful to help project managers or people in general that are responsible for a project to determine whether a project is on schedule, or if the project is over or under budget. EVM can also be used to compare the actual work that has been performed to the work that was estimated and planned for the project at a certain time during the project, EVM can also be used to forecast projected performance. EVM is a technique that can be applied, to at least some degree, to the management of projects in any industry and using any contracting approach. The use of EVM requires



Contents

History

Concept overview

Implementation of the method

The following parameters are used to asses and compare in EVM

Parameter Description Formula
Planned Value (PV) Is a budget baseline that has been established for a project/work package/activity. It is a function of cost and time as can be seen in figure 1. PV baseline can be used to view the value to be earned at a certain time/phase in the project. PV is frequently referred to as the S curve simply because of the shape of the curve


Budget at completion (BAC) BAC is the final point and the highest value of the cumulative Planned value curve. BAC represents the total budget for the project/work package/activity.


Actual Cost (AC) Is the cumulative actual cost that has been spent on a project/work package/activity


Earned value (EV) is the cumulative value that has been earned for the work completed at a certain point in time. Earned value(EV)=total budget for activity*completed proportion
Earned Value Variances Description Formula BLAA
Cost Variance (CV) o = Earned Value (EV) - Actual Cost (AC) > 0 means under budget

< 0 means over budget

Schedule Variance (SV) o = Earned Value (EV) - Planned Value (PV) > 0 means ahead of schedule

< 0 means behind schedule

Earned Value Indices Description Formula BLAA
Cost Performance Index (CPI) o = EV/AC > 1 means better progress for the money spent

< 1 means less progress for the money spent

Schedule Performance Index (SPI) o = EV/PV > 1 means more work performed than had been scheduled

< 1 means less work performed than had been scheduled

Project Percent Complete o = (EV/BAC) * 100 Percent of project work complete at a given time.

Remember BAC = Budget at Completion

To Complete Performance Index (TCPI) o =(BAC-EV)/(BAC-AC) The cost performance index required to complete the project on the predetermined budget.
Earned Value Forecast Description Formula BLAA
Estimate at completion (EAC) o = BAC/CPI The estimated total cost at project completion.
Variance at completion (VAC) o = BAC-EAC The estimated variance between actual total cost(EAC) and planned total cost(BAC) at project completion.



Terminology

Example

In this section there will be an short simplified example of EVM in a project that has five tasks A,B,C,D,E. Figure 1. Step 1 For each of the tasks the duration has been estimated, the cost of each task per week and finally the total cost of each task. These cost are called Planned value(PV) in EVM. In more detailed examples and projects a Work Breakdown schedule"(WBS) can be very useful if used in the right ways.

Figure 1: Tasks.

To keep track of the status of each of the projects a Gantt Chartt has proven to be very useful since it provides much needed clarity, helps with coordination and last but not least time management, helping teams understand the overall impact of project delays which is an vital part of the EVM method. In this Gantt chart there can be seen the planned schedule and the actual performance of the project up until week 7 when the project manager decided to take a closer look at the progression of the project.

His report at the end of week 7 can be seen in table 2. Using the data from that table to fill up the GANTT Chart. According to the report and from the GANT Chart it can be concluded that task C and D are behind schedule.

Task Planned completion Actual completion
C 66% 33%
D 100% 50%

Now it is time from the project manager to analyze the situation and take a closer look at the Earned Value Variances(, Earned Value Indices and Earned Value Forecast

The project manager made some calculations which can be seen in table 3.


Task Schedule Variance (SV) Cost Variance(CV) Schedule Performance Index(SPI) Cost Performance Index(CPI)
A Exactly on schedule Exactly On budget Exact amount of work performed that has been scheduled Exact amount of progress for the money spent
B Exactly on schedule Over budget Exact amount of work performed that has been scheduled Less progress for the money spent
C Behind on schedule Over budget 50% of work performed that has been scheduled Less progress for the money spent
D Behind on schedule Exactly on budget 50% of work performed that has been scheduled Exact amount of progress for the money spent
E - - - -


Figure 1: Tasks.
Figure 2: Tasks.
table 3: Earned Value Variances, Earned Value Indices .
Figure 4: Tasks.

Advantages

The use of EVM to make progress payments on construction projects.

When undergoing a project there is often a risk that the owner of the project is going to overpay their suppliers for the work they completed. This is due to the fact that Cost-type arrangements have inherent risk for the sake of the owners focusing on the expense paid and forgetting to closely monitor the actual work done for the money spent. One way of mitigating this risk is to accurately measure the value of work completed, compare that against the original budget authorized for the completed work, and only pay for actual work completed. There are two broad contractual environments in the building industry, Cost type and fixed price

Cost type

Is often used in construction projects to cover the initial design work and both the first and final design. In project that are high risk, f.x. nuclear energy construction the cost type contract is sometimes used for all of the phases of the project.

Cost reimbursable type arrangement works in the following manner: the supplier will be refunded each month for the actual cost(AC)

Limitations

References

Further reading

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox