Lean Approach to Scheduling in Construction Projects

From apppm
(Difference between revisions)
Jump to: navigation, search
(Abstract)
(Abstract)
Line 1: Line 1:
  
 
== Abstract ==
 
== Abstract ==
Scheduling of activities are of utmost importance when starting a new project whatever scale it might be on. It is done to ensure the resources are used efficiently and in most cost effective way<ref name="international">.  
+
Scheduling of activities are of utmost importance when starting a new project whatever scale it might be on. It is done to ensure the resources are used efficiently and in most cost effective way<ref name="internationl" />.  
 
According to PMI (2013) the Plan Schedule Management Process may involve “''choosing strategic options to estimate and schedule the project such as: scheduling methodology, scheduling tools and techniques, estimating approaches, formats, and project management software''”.  
 
According to PMI (2013) the Plan Schedule Management Process may involve “''choosing strategic options to estimate and schedule the project such as: scheduling methodology, scheduling tools and techniques, estimating approaches, formats, and project management software''”.  
  
There are various methods and techniques for scheduling of which the most widely used are the Critical Path Method (CPM) and Gantt Charts.  [http://www.internationaljournalssrg.org/IJCE/2017/Special-Issue/ICRTCETM/IJCE-ICRTCETM-P187.pdf]. However, criticism of the CPM and Gantt Chart has been expressed, especially in construction projects, for not sufficiently supporting building management during the construction phase, and not creating a continuous, and thus financial, flow of resources. (bygr167) [http://www.leanconstruction.dk/media/16573/Niclas%20Andersson.pdf].
+
There are various methods and techniques for scheduling of which the most widely used are the Critical Path Method (CPM) and Gantt Charts<ref name="internationl" />. However, criticism of the CPM and Gantt Chart has been expressed, especially in construction projects, for not sufficiently supporting building management during the construction phase, and not creating a continuous, and thus financial, flow of resources. (bygr167) [http://www.leanconstruction.dk/media/16573/Niclas%20Andersson.pdf].
  
 
Lean thinking aims at optimizing production flow and eliminate waste of resources. The ideology is adjusted to the construction industry and called Lean Construction. Lean Construction methods are becoming common practice on construction projects with the use of the Last Planner System (LPS) and Location Based Scheduling (LBS) as planning and scheduling tools [http://www.consultaegis.com/news/blog-posts/lean-construction-methods-cpm-scheduling-work-together/]
 
Lean thinking aims at optimizing production flow and eliminate waste of resources. The ideology is adjusted to the construction industry and called Lean Construction. Lean Construction methods are becoming common practice on construction projects with the use of the Last Planner System (LPS) and Location Based Scheduling (LBS) as planning and scheduling tools [http://www.consultaegis.com/news/blog-posts/lean-construction-methods-cpm-scheduling-work-together/]
Line 32: Line 32:
  
  
<ref>E. Miller, ''The Sun'', (New York: Academic Press, 2005), 23-5.</ref>
+
 
 +
<references>
 +
<ref name="international">Harithamahalakshmi, K. et al., 2017. Construction Scheduling Using Critical Path Method And Location Based Management System. ''SSRG International Journal of Civil Engineering''. Available at: www.internationaljournalssrg.org [Accessed February 8, 2018].</ref>
 +
</references>
  
 
== References ==
 
== References ==
 
<references />
 
<references />

Revision as of 21:47, 8 February 2018

Contents

Abstract

Scheduling of activities are of utmost importance when starting a new project whatever scale it might be on. It is done to ensure the resources are used efficiently and in most cost effective way[1]. According to PMI (2013) the Plan Schedule Management Process may involve “choosing strategic options to estimate and schedule the project such as: scheduling methodology, scheduling tools and techniques, estimating approaches, formats, and project management software”.

There are various methods and techniques for scheduling of which the most widely used are the Critical Path Method (CPM) and Gantt Charts[1]. However, criticism of the CPM and Gantt Chart has been expressed, especially in construction projects, for not sufficiently supporting building management during the construction phase, and not creating a continuous, and thus financial, flow of resources. (bygr167) [1].

Lean thinking aims at optimizing production flow and eliminate waste of resources. The ideology is adjusted to the construction industry and called Lean Construction. Lean Construction methods are becoming common practice on construction projects with the use of the Last Planner System (LPS) and Location Based Scheduling (LBS) as planning and scheduling tools [2]

This article aims at comparing the scheduling techniques CPM/Gantt Chart and the two Lean approaches to scheduling in construction projects; Last Planner System and Location Based Scheduling.

  • Firstly, a brief theoretical description of CPM and Gantt Chart is given, followed by an application-oriented description of the two Lean approaches to scheduling techniques.
  • Secondly, the two scheduling techniques, including advantages and disadvantages, are compared to CPM and Gantt Chart.
  • Lastly, the benefits of using Lean approaches to scheduling of construction projects are discussed.

Big idea

Describe the tool, concept or theory and explain it's purpose. The section should reflect the current state of the art on the topic.

Application

Provide guidance on how to use the tool/concept/theory and when it's applicable.

Limitations

Critically reflect on the tool/concept/theory. When possible, substantiate your claims with literature.

Recommendations

Annotated bibliography

Provide key references (3-q9), where a reader can find additional information on the subject. Summarize and outline the relevance of each reference to the topic (around 100 words per reference). The bibliography is not counted in the suggested 3000 words target length of the article


  1. Cite error: Invalid <ref> tag; no text was provided for refs named internationl

Cite error: <ref> tag with name "international" defined in <references> is not used in prior text.

References

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox